Building Law Monthly
RIGHT TO DEDUCT LIQUIDATED AND ASCERTAINED DAMAGES SURVIVES GRANT OF AN EXTENSION OF TIME
Reinwood Ltd v L Brown & Sons Ltd [2007] EWCA Civ 601; [2007] All ER (D) 228 (June)
In
Reinwood Ltd v L Brown & Sons Ltd
[2007] EWCA Civ 601; [2007] All ER (D) 228 (June) the Court of Appeal held that the cancellation of a certificate of non-completion
by the subsequent grant of an extension of time did not have the consequence that the employer could no longer rely on the
certificate of non-completion for the purpose of deducting liquidated and ascertained damages. The right to deduct liquidated
and ascertained damages was held, as a matter of construction of the contract, to crystallise on the giving by the employer
of notice of intention to deduct and the exercise of that right was not affected by the subsequent grant of an extension of
time. To the extent that the grant of an extension of time reduces the liquidated and ascertained damages which an employer
can retain, the employer must repay that sum within a reasonable time; but the grant of an extension of time was held not
to deprive the employer of the initial right to deduct the liquidated and ascertained damages.