Law of Tug and Tow and Offshore Contracts, The
| Law of Tug and Tow and Offshore Contracts, 5th edition (c) 2026 |
Page 1159
Index
- abandonment of the tow obligations of the tug, and 1.78, 4.293, 8.72
- absence of delay payments and free time Towhire 2021 4.474
- additional charges
- Towcon 2008 4.101
- additional equipment
- Supplytime 2017, and 5.58–5.66
- adjusters’ rules of practice
- general average 13.19
- adjustment of hire
- Supplytime 2017, and 5.74, 5.110–5.112, 5.267
- Admiralty Court
- jurisdiction 1.80–1.81
- admiralty jurisdiction
- claims in nature of towage 14.30–14.34
- features in respect of towage 14.7–14.36
- historical background 14.1–14.4
- jurisdiction in rem 14.7–14.8
- no maritime lien 14.9–14.11
- other available heads 14.35–14.36
- present-day 14.5–14.6
- towage in respect of ship 14.12–14.29
- advance notices
- Heavycon 2007 7.66–7.68
- discharging 7.67
- loading and discharging responsibilities 7.49–7.55
- adverse weather see also delays
- delays 10.113
- deviation from original rate 4.148
- agency
- Heavycon 2007, and 7.105
- aggregation of tug and tow for purposes of limitation fund 12.18 – 12.56
- Alexander G. Tsavliris Ltd v OIL Ltd (The Herdentor)
- text 1123 – 1157
- allocation of responsibility
- liability and indemnity 4.178
- AMS clause for voyage charterparties
- Heavyliftvoy 7.176–7.178
- anti-deduction clause
- Towhire 2021, and 4.72–4.79, 4.473
- approval of transportation
- Heavycon 2007, and 7.69–7.74
- approval of vessels and condition of cargo 7.185, 7.214
- Projectcon 7.185, 7.214
- arbitration
- Wreckhire 2010 10.72–10.74
- area of operation
- Supplytime 2017, and 5.81
- assignment
- Supplytime 2017, and 5.241–5.242
- ASVtime form 5.363 – 5.364
- charter period 5.370–5.372
- employment of vessel by charterer 5.375–5.385
- extended offshore operations 5.385–5.386
- liabilities and indemnities 5.391–5.392
- owner/charterer to provide and pay for 5.387–5.390
- particulars 5.369–5.392
- special aspects 5.365–5.368
- structure 5.368
- text 915 – 952
- the vessel 5.373–5.374
- audits and inspections
- Supplytime 2017 5.68–5.73
- authority of master
- contract to be towed, to
- on behalf of owners 1.46–1.52
- on behalf of vessel’s cargo 1.53–1.54
- take vessel in tow, to
- master of tug 1.55
- master of vessel not a tug 1.56–1.58
- bailment
- towage contract, and 1.12–1.30
- ballast
- Bargehire 2021
- ballast engineer 6.120–6.122
- ballast water management 6.5, 6.113, 6.116–6.117
- barge engineer
- ballasting, and 7.210–7.212
- Projectcon, and 7.211
- remuneration 7.185
- services 7.212
- Bargehire 2021
- ballast engineer 6.120–6.122
- ballast operations 6.113–6.122
- ballast water management 6.5, 6.113, 6.116
- cancelling 6.56–6.62
- changes to barge 6.96–6.97
- consequential loss 6.139
- consumable oil and stores 6.76
- definitions 6.25
- delivery 6.32–6.43, 6.76–6.86
- demobilisation 6.55
- early redelivery 6.132
- employment 6.63–6.64
- excluded cargoes 6.63–6.64
- excluded loss 6.139
- force majeure 6.138
- general provisions 6.7–6.24
- genesis 6.1–6.6
- hire 6.46–6.54
- indemnity 6.140–6.142
- inspection 6.87–6.89
- insurance 6.123–6.131
- inventories 6.76
- late redelivery 6.132
- limits on charterer’s employment of barge 6.63–6.75
- maintenance and operation 6.90–6.102
- maintenance and repair 6.9
- mobilisation 6.55
- non-lien 6.140–6.142
- organisation 6.21–6.24
- period of charterparty 6.26–6.31
- position under “Bargehire 2008” 6.12–6.15
- position under “Bargehire 2021” 6.16–6.20
- redelivery 6.76–6.86, 6.132–6.137
- repairs 6.103–6.112
- restrictions on charterer’s use of barge 6.98–6.102
- revision 6.1–6.6
- species of demise charterparty 6.7–6.9
- standard boilerplate provisions 6.143–6.147
- structure 6.21–6.24
- substitution 6.44
- Supply of Goods and Services Act 1982, and 6.10–6.11
- surveys 6.76–6.86
- text 953 – 966
- time for delivery 6.45
- trading limits 6.63–6.64
- best endeavours
- Towcon 2008 and ,4.35–4.38
- bill of lading
- Heavycon 2007 7.97–7.100
- Heavyliftvoy 7.171–7.174
- Projectcon 7.232–7.233
- BIMCO forms
- genesis of Supplytime form 5.1–5.13
- Heavyliftvoy see also Heavyliftvoy
- background 7.1–7.19
- Part I 7.115
- Part II 7.116–7.178
- structure 7.113–7.114
- Supplytime 2005 5.4–5.5, 5.7–5.8
- Supplytime 2017 see Supplytime 2017
- structure 5.17–5.25
- Towcon 2021
- Part I 4.12–4.30
- Part II 4.31–4.32
- structure 4.11–4.32
- BIMCO Forms Towcon 2021 and Towhire 2021 4.1–4.482
- BIMCO ocean towage 1.35–1.42
- bonus for prompt completion
- Wreckhire 2010 10.53–10.54
- both to blame omnibus time charter provisions
- Supplytime 2005 5.255–5.256
- brokerage
- Heavycon 2007 7.106
- bunker escalation
- Heavycon 2007 7.82
- bunker price adjustment
- Heavyliftvoy 7.163–7.166
- bunkers
- Supplytime 2005 5.96–5.102
- Supplytime 2017 5.103–5.107
- Towhire 2021 4.475–4.480
- Windtime 5.359
- cancellation of charter
- Heavycon 2007 7.59–7.65
- cancellation in light of war
- Supplytime 2017 5.245
- cancelling
- Bargehire 2021 6.56–6.62
- Projectcon 7.59–7.65
- cargo description
- Heavyliftvoy 7.136
- cargo discrepancy
- Heavyliftvoy 7.137–7.138
- cargo notes
- Projectcon 7.232–7.233
- cargo requirements
- Heavyliftvoy 7.125–7.135
- certificates
- Supplytime 2017 5.75
- change of method of work and/or personnel, craft and equipment
- Wreckhire 2010 10.33–10.37
- charges
- Heavycon 2007 7.57
- Heavyliftvoy 7.159, 7.161–7.162
- charter period
- Supplytime 2017 5.370–5.372
- clause paramount
- Heavyliftvoy 7.176
- collisions involving tug and tow
- collision between tug and tow 11.43–11.44
- collisions during towage which involve third vessel 11.45–11.68
- control not necessarily decisive 11.58
- doctrine of control 11.47–11.48
- irrelevance of contract 11.45–11.46
- effect of common ownership of tug and tow 11.63–11.68
- general scheme for apportioning liability 11.14–11.15
- liabilities between tug, tow and third party vessel 11.59–11.68
- navigation 11.4–11.13
- Collision Regulations, role of 11.6–11.13
- navigation by tug and tow 11.16–11.42
- application to water-borne objects 11.33–11.36
- duties upon tow 11.19–11.21
- duties upon tug 11.18
- lights and shapes 11.23–11.29
- navigational rules 11.4–11.5
- sound signals 11.30–11.31
- special aspects of Collision Regulations 11.22–11.42
- towage contract, role of 11.16–11.17
- tug and tow: how treated 11.37–11.42
- special features 11.22–11.42
- third party vessel also to blame 11.60–11.62
- third party vessel not to blame 11.59
- commencement of loading
- Heavycon 2007 7.59–7.65
- Projectcon 7.189, 7.207, 7.218–7.221
- common European towage forms 1.43
- common understanding in trade
- UK Standard Conditions for Towage and Other Services 3.7–3.8
- company representative
- Wreckhire 2010 10.30–10.32
- completion of service
- obligations of the tug 2.53
- compliance with ISPS and MTSA
- Supplytime 2017 5.108–5.110
- Towcon 2021 4.451–4.461
- condition of cargo
- Projectcon 7.195
- condition of vessel
- Heavycon 2007 7.33–7.42
- Supplytime 2017 5.50–5.52
- Windtime 5.354
- confidentiality
- Supplytime 2017 5.271–5.273
- consequential damage
- Heavycon 2007 7.94
- Supplytime 2005 5.192
- Supplytime 2017 5.190–5.192
- consequential loss
- Bargehire 2021 4.190, 6.139
- BIMCO 1.77, 4.6, 4.181
- Heavycon 2007 7.94
- Supplytime 2005 5.192
- Supplytime 2017 5.190–5.192
- Towcon 2021 4.6
- Wreckhire 2010 10.64
- Wreckhire 99 10.64
- construction of towage contracts 1.69–1.79
- contracts of towage
- Admiralty Court, effect of 1.80–1.81
- bailment, and 1.14–1.30
- BIMCO ocean towage 1.35–1.42
- common European towage forms 1.43
- construction
- no special rules 1.69–1.79
- Consumer Rights Act 2015 1.66
- contract for services, as 1.12–1.13
- exemption clauses 1.66–1.68
- gratuitous towage 1.9–1.11
- implied terms 1.44–1.45
- jurisdiction of Admiralty Court 1.80–1.81
- legislative control of exemption clauses 1.66–1.68
- making of
- authority of master to contract to be towed 1.46–1.54
- authority of master to take vessel in tow 1.55–1.58
- The Kingalock 1.59–1.65
- pre-contractual disclosure 1.59 – 1.65
- no special rules 1.69–1.79
- offshore industry forms 1.35–1.42
- pre-contractual disclosure 1.59–1.65
- relationship between towage and salvage 1.4–1.8
- salvage and towage, relationship between 1.4–1.8
- standard form contract, role of 1.31–1.45
- towage arises from 1.3–1.11
- UK Standard Conditions 1.34
- Convention on Limitation 1976 see limitation of liability
- co-operation
- obligations of the tow 2.66–2.83
- course of dealing
- UK Standard Conditions for Towage and Other Services 3.7–3.8
- crew
- Salvcon 2005 9.62
- Supplytime 2017 5.83–5.89, 5.336–5.337
- Towcon 2021 4.124–4.130
- Windtime form 5.356–5.357
- damage to or caused by tug and tow
- Towcon 2008 4.248–4.250
- danger
- salvage, and 8.14
- dangerous cargo
- Heavycon 2007 7.83
- Supplytime 2017 5.76–5.81
- death
- Salvcon 2005 9.89–9.90
- Towcon 2021 4.227–4.247
- deck cargo
- Heavyliftvoy 7.167–7.170
- definitions
- Bargehire 2021 6.25
- Heavycon 2007 7.29–7.31
- Heavyliftvoy 7.120–7.122
- Projectcon 7.189
- Salvcon 2005 9.42–9.45
- Supplytime 2017 5.26–5.34
- UK Standard Conditions for Towage and Other Services 3.6–3.41, 3.107–3.148
- Windtime form 5.351–5.353
- Wreckhire 2010 10.22–10.23
- Wreckstage 2024 10.93–10.94
- delay payments
- Projectcon 7.226–7.229
- Salvcon 2005 9.52–9.57
- Towcon 2021 4.84–4.97
- Towhire 2021 4.474
- delays see also delay payments
- Heavycon 2007 7.44–7.48
- Projectcon 7.210
- Wreckhire 2010 10.40–10.46
- delivery
- Bargehire 2021 6.32–6.43, 6.45, 6.76–6.86
- Supplytime 2017 5.39–5.49, 5.53–5.54
- Wreckhire 2010 10.49–10.50
- Wreckstage 2010 10.49–10.50
- demarcation of scope of work
- Heavycon 2007 7.23–7.26
- demobilisation
- Bargehire 2021 6.55
- Heavycon 2007 7.80
- Supplytime 2017 5.35, 5.38, 5.48, 5.71
- Towhire 2008 5.48
- Towhire 2021 4.472
- demurrage
- Heavycon 2007 7.79
- Heavyliftvoy 7.158
- Towcon 2021 3.95, 4.96, 4.215, 7.81, 9.56
- detention
- Heavyliftvoy 7.158
- deviation
- Heavycon 2007 7.44–7.48
- Projectcon 7.210
- Towcon 2021
- deviation from original route 4.148
- impermissible deviations 4.154
- liberties to deviate 4.149–4.153
- necessary deviation 4.145–4.155
- notification of deviations 4.155
- Towhire 2021 4.482
- discharging
- Heavycon 2007 7.54
- loading and discharging responsibilities 7.50–7.55
- Heavyliftvoy
- discharging of cargo and “free-in” and “liner-in-hook” options 7.155–7.156
- Projectcon 7.213–7.216
- disease
- Supplytime 2017
- infectious or contagious diseases clause 5.246, 5.254
- ports and places affected by ice conditions and disease 5.246–5.254
- disposal of vessel
- Wreckhire 2010 10.49–10.50, 10.59
- dispute resolution
- BIMCO 4.29, 5.274, 7.16, 10.69, 10.73
- Heavycon 7.16, 7.108
- Salvcon 9.104
- Supplytime 2017 4.29
- Supplytime 89
- Towcon 2021 4.461–4.466
- Wreckhire 2010 10.69
- double banking
- Heavycon 2007 7.107
- drugs and alcohol policy
- Supplytime 2017 5.261
- employment
- Bargehire 2021 6.63–6.74
- Salvcon 2005 9.58–9.61
- Supplytime 2017 5.74–5.80, 5.375–5.384
- engaged services
- salvage 8.111–8.130
- entire agreement
- Supplytime 2017 5.279–5.283
- epidemic/fever
- Supplytime 2005 5.246, 5.251
- Supplytime 2017 5.246, 5.253
- exemption clauses
- legislative control 1.66–1.68
- Supplytime 2017 5.175–5.184
- towage contracts 1.66–1.68
- Towcon 2021 4.251–4.274
- UK Standard Conditions for Towage and Other Services 3.55–3.82
- expenses
- general average 13.11–13.19
- expert evaluation
- Wreckhire 2010 10.69–10.72
- Wreckstage 2024 10.117–10.123
- extension hire
- Supplytime 2017 5.111
- extension to cancelling date
- Towcon 2021 4.98–4.101, 4.481
- extra costs
- of disposal of vessel 10.59
- Salvcon 2005 9.83–9.84
- Towcon 2021 4.102–4.107
- Wreckhire 2010 10.56–10.59
- Wreckstage 2010 10.85
- financial security
- Towcon 2021 4.437
- fitness
- of tow 2.69–2.77
- of tug for towage service 2.17–2.28
- force majeure
- Bargehire 2021 6.138
- Supplytime 2005 5.268–5.269, 5.292–5.293, 5.301, 5.305, 5.324
- Supplytime 2017 5.146, 5.293, 5.301, 5.305
- free-in
- Heavyliftvoy
- discharging of cargo and “free-in” and “liner-in-hook” options 7.155–7.156
- “free-in” 7.141–7.145
- loading of cargo and “free-in” and “liner-in-hook” options 7.139–7.140
- provisions common to both “free-in” and “liner-in-hook” options 7.151, 7.157
- free time
- Heavycon 2007 7.79
- Projectcon 7.226–7.229
- Salvcon 2005 9.54–9.57
- Towcon 2021 4.84–4.97
- Towhire 2021 4.474
- freight
- Heavycon 2007 7.75–7.78
- Heavyliftvoy 7.158
- Projectcon 7.225
- general average
- as between tug and tow 5.255–5.257, 13.20–13.55
- basis of contribution between respective interests 13.34
- commonality of adventure 13.26–13.33, 13.52
- commonality of maritime adventure 13.38–13.39
- continuation of common adventure 13.48–13.50
- disconnection an act of 13.48–13.50
- fundamental requirements 13.20
- importance of York-Antwerp rules 1994 and 2004 13.23–13.25
- measure as to 13.40
- position prior to 1994 Rules 13.26–13.34
- practical importance for tug and tow 13.21–13.22
- questions specific to tug and tow 13.10
- recovery of towage expenses 13.11–13.19
- adjusters’ rules of practice 13.19
- leading cases 13.13–13.18
- resort to port or place of refuge 13.55
- special issues 13.1–13.10
- Supplytime 2005 5.255–5.257
- tow-line slipped to save vessel(s) 13.41–13.47, 13.53–13.54
- York-Antwerp Rules 13.1–13.9
- York-Antwerp Rules 1994/2004 Rule B 13.35–13.50
- York-Antwerp Rules 2016 13.51–13.55
- gratuitous towage 1.9 – 1.11
- hazardous or noxious substances
- Supplytime 2017 5.216–5.221
- health and safety
- Supplytime 2017 5.260–5.261
- Heavycon 2007
- advance notices 7.66–7.68
- agency 7.105
- Annex A 7.23–7.26
- approval of transportation 7.70–7.74
- background 7.1–7.14
- bill of lading 7.97–7.100
- boxes 7.22
- brokerage 7.106
- bunker escalation 7.82
- canal transit 7.81
- cancellation of charter 7.59–7.65
- cancelling date 7.59–7.65
- cargo receipt 7.97–7.100
- charges 7.57
- commencement of laydays 7.59–7.65
- commencement of loading 7.59–7.65
- condition of cargo 7.70–7.74
- condition of vessel and cargo 7.70–7.74
- consequential damages 7.94
- dangerous cargo 7.83
- definitions 7.29–7.31
- delays 7.44–7.48
- demarcation of scope of work 7.23–7.26
- demobilisation 7.80
- demurrage 7.79
- deviation 7.44–7.48
- discharging 7.54
- double banking 7.107
- duties 7.57
- free time 7.79
- freight 7.75–7.78
- Himalaya clause 7.103
- indemnities 7.87–7.93
- insurance 7.101–7.102
- knock for knock 7.87, 7.89, 7.91, 7.94, 7.96, 7.100, 7.101, 7.107
- liabilities 7.87–7.93
- lien 7.84
- limitation of liability 7.104
- loading and discharging responsibilities 7.49–7.55
- marine surveyor 7.70–7.74
- mobilisation 6.55
- notice of readiness 7.69
- obligation as to seaworthiness of vessel 7.33–7.42
- obligation of despatch 7.43
- obligation to transport cargo 7.32
- Part I 7.22
- Part II 7.27–7.107
- part cargo 7.44–7.48
- permits 7.56
- pollution 7.95–7.96
- purpose of revision 7.15
- quarantine 7.58
- structure 7.20–7.21
- substitution 7.85
- taxes 7.57
- termination 7.86
- text 981 – 997
- the transportation 7.70–7.74
- voyage 7.32–7.43
- Heavyconbill 2007
- text 1027 – 1028
- Heavyconreceipt 2007
- text 1029 – 1030
- Heavyliftvoy
- AMS clause for voyage charter parties 7.177–7.183
- background 7.108
- bills of lading 7.171–7.174
- BIMCO clause for special US Customs requirements 7.177–7.178
- BIMCO US Customs advance notifications 7.177–7.178
- boxes 7.115
- bunker price adjustment 7.163–7.166
- cargo description 7.136
- cargo discrepancy 7.137–7.138
- cargo requirements 7.125–7.135
- carrier’s right to indemnity 7.131–7.134
- defence of insufficiency of packing 7.135
- requirements 7.126–7.130
- charges 7.159, 7.161–7.162
- clause paramount 7.176
- deck cargo 7.167–7.170
- definitions 7.120–7.122
- demurrage 7.158
- detention 7.158
- discharging of cargo and “free-in” and “liner-in-hook” options 7.155–7.156
- dues 7.161–7.162
- “free-in” 7.141–7.145
- “free-in” option 7.139–7.140, 7.151, 7.155–7.157
- freight 7.158
- Gencon form, and 7.111, 7.140, 7.142, 7.146, 7.161, 7.171–7.172
- “liner in hook” option 7.139–7.140, 7.151, 7.155–7.157
- loading of cargo 7.139–7.140
- merchant’s option to terminate 7.175
- Part I 7.115
- Part II 7.116–7.178
- part cargoes 7.160
- port congestion 7.153–7.154
- provisions common to both “free-in” and “liner-in-hook” options 7.151, 7.157
- purpose 7.108
- scope of voyage 7.123–7.124
- standard of sea fastening 7.152
- structure 7.113–7.114
- swell 7.153–7.154
- taxes 7.161–7.162
- terminal charges 7.159
- text 999 – 1016
- time waiting to berth 7.153–7.154
- Heavyliftvoybill
- text 1031 – 1032
- Himalaya clause
- Heavycon 2007 7.103
- Supplytime 2017 5.215
- Towcon 2021 4.411–4.416
- UK Standard Conditions for Towage and Other Services 3.195–3.198
- Wreckhire 2010 10.68
- hire
- Bargehire 2021 6.46–6.54
- Supplytime 2017 5.111–5.133
- adjustment of hire 5.111
- Towhire 2021 4.472–4.474
- daily rate of hire excluding bunkers 4.475
- daily rate of hire including bunkers 4.475
- Wreckhire 2010 10.55, 10.69–10.72
- hirer’s representative
- Salvcon 2005 9.76
- hirer’s right to cancel
- Towcon 2021 4.98–4.101
- hirer’s warranty of authority
- UK Standard Conditions for Towage and Other Services 3.42, 3.149–3.152
- ice clause
- Supplytime 2017 5.247–5.250
- Towcon 2021 4.156–4.160
- implied terms
- obligations of the tow 2.66–2.83 see also obligations of the tow
- obligations of the tug 2.2–2.65 see also obligations of the tug
- towage and allied contracts 1.44–1.45
- incorporation
- UK Standard Conditions for Towage and Other Services 3.7–3.8
- indemnities
- Bargehire 2021 6.140–6.142
- Heavycon 2007 7.87–7.93
- Projectcon
- mutual 7.230–7.231
- Towcon 2021
- mutual 4.176–4.274
- Supplytime 5.391–5.392
- Windtime form
- mutual 5.360–5.361
- insurance
- Bargehire 2021
- Heavycon 2007
- Salvcon 2005
- Supplytime 2017
- Wreckhire 2010
- interest
- Salvcon 2005 9.82
- Towcon 2021 4.108–4.112
- interruptions in course of towage
- obligations of the tug 2.54–2.58
- ISPS, compliance with
- Supplytime 2017 5.108–5.110
- Towcon 2021 4.451–4.461
- ISU 9.7
- standard forms for sub-contract 9.10–9.18
- Julia, The
- obligations of the tow 2.66–2.68
- obligations of the tug 2.5–2.11
- jurisdiction see also Admiralty jurisdiction
- Admiralty Court 1.80–1.81
- UK Standard Conditions for Towage and Other Services 3.98, 3.199–3.203
- jurisdiction of Admiralty Court 1.80 – 1.81
- in rem 14.7–14.8
- towage contracts 1.76–1.78
- Kingalock, The 1.59–1.65
- knock for knock
- Bargehire 2021 6.60
- Heavycon 2007 7.100–7.101
- Projectcon 7.230–7.231
- Supplytime 2017 5.160–5.174
- “group” coverage of knock for knock 5.164–5.166
- main changes to knock-for-knock regime 5.160–5.163
- Towcon 2021 4.191–4.193
- Windtime form 5.360–5.361
- Wreckhire 2010 10.76–10.78
- late payment, termination for non or
- Salvcon 2005 9.53
- laydays, commencement of
- Heavycon 2007 7.59–7.65
- liability and indemnity
- ASVtime form 5.391–5.392
- Heavycon 2007 7.87–7.93
- Supplytime 2017 5.160–5.221
- Projectcon 7.230
- Towcon 2021 4.176–4.274
- allocation of responsibility 4.176, 4.181, 4.216, 4.221, 4.257
- commercial common sense 4.204, 4.207
- contra proferentem, and 4.198, 4.206–4.208, 4.211–4.213, 4.215–4.216, 4.218
- contractual remedies 4.208
- correct approach to construction 4.194–4.224
- damage to or caused by tug and tow 4.247–4.250
- death of those engaged in towage 4.227–4.247
- exclusion/exemption 4.251–4.274
- generally 4.176–4.183
- gross negligence 4.184–4.190
- injury to those engaged in towage 4.227–4.247
- knock-for-knock 4.191–4.193
- loss of or caused by tug and tow 4.247–4.250
- mutual nature 4.197
- wilful misconduct 4.184–4.190
- licences
- Heavycon 2007 7.56
- Supplytime 2017 5.75
- lien
- Admiralty jurisdiction 14.9–14.11
- Heavycon 2007 7.84
- Supplytime 2017 5.241
- Towcon 2021 4.408–4.410
- Wreckhire 2010 10.68
- lights and shapes
- collisions involving tug and tow 11.23–11.29
- limitation of liability
- aggregation of tug and tow for purposes of limitation fund 12.18–12.56
- The Bramley Moore 12.31–12.36
- Canadian and American cases 12.46–12.49
- cases before Merchant Shipping Act 1958 12.21–12.29
- cases following Merchant Shipping Act 1958 12.30–12.49
- flotilla issues 12.18–12.20
- Merchant Shipping Act 1995 and 1976 Limitation Convention 12.50–12.54
- question of aggregation 12.18–12.20
- The Sir Joseph Rawlinson 12.37–12.44
- special problem of flotilla’s physical structure 12.55–12.56
- summary of law before Merchant Shipping Act 1979 12.45
- wording of 1894 Act as amended 12.21–12.22, 12.30
- application of Limitation Convention between tug and tow 12.62–12.81
- how the question arises 12.62
- position under 1976 Convention 12.63–12.76
- Smit v Mobius, decision in 12.77–12.81
- application of Limitation Convention to ships 12.15–12.17
- “arising on any distinct occasion” 12.57–12.61
- English approach 12.4
- framework of 1976 Convention and Merchant Shipping Act 1995 12.13
- general principles 12.1–12.14
- Heavycon 2007 7.104
- historical background 12.1–12.12
- Merchant Shipping Act 1894 12.5–12.8
- Merchant Shipping Act 1979 12.9–12.12
- Merchant Shipping Act 1995 12.9–12.13
- new regime 12.9–12.12
- policy, question of 12.1–12.13
- section 503
- Merchant Shipping Act 1894 12.5–12.8
- special questions arising in relation to tug and tow 12.14
- Supplytime 2017 5.215
- limitation fund
- aggregation of tug and tow for purpose of 12.18–12.56
- limits, trading
- Bargehire 2008 6.22
- Supplytime 2017 5.18
- “liner in hook” option
- Heavyliftvoy 7.139–7.140, 7.151, 7.155–7.156
- loading
- Heavycon 2007
- commencement of 7.41
- loading and discharging responsibilities 7.50–7.55
- Heavyliftvoy
- loading of cargo 7.139–7.140
- Projectcon 7.213–7.216
- commencement of loading 7.216
- Supplytime 2017
- of fuel 5.103–5.107
- Lloyd’s Open Form (LOF) 1.62 , 8.7, 9.3 , 9.67 , 9.100
- loss
- Bargehire 2021
- excluded 6.139
- Salvcon 2005
- liabilities
- loss of or damage caused to or by vessels involved 9.90–9.91
- other losses and statutory limitations 9.92
- Supplytime 2017
- liabilities
- excluded losses 5.190–5.191
- heads of excluded loss and damage 5.185–5.189
- scope of losses excluded 5.193–5.205, 5.211–5.213
- Towcon 2021
- The A Turtle 4.300–4.371
- loss of or caused by tug and tow 5.247–4.248
- Wreckhire 2010
- expert evaluation of 10.69–10.72
- lump sum
- Salvcon 2005 9.48–9.51
- Supplytime 2017
- lump sum mobilisation charge 5.18, 5.48
- Towcon 2021
- earning of lump sum 4.72–4.79
- lump sum 4.66–4.71
- marine surveyor
- Heavycon 2007 7.70–7.74
- marine warranty surveyor
- Projectcon 7.223–7.224
- master
- authority of
- towage contracts 1.46–1.58
- of tug 1.55
- of vessel not tug 1.56–1.58
- master and crew
- Salvcon 2005 9.62
- Supplytime 2017 5.83–5.89
- Windtime form 5.356–5.357
- mediation
- Wreckhire 2010 10.73–10.74
- Merchant Shipping Act 1894, section 503 12.5 – 12.8
- Merchant Shipping Act 1958
- cases before 12.21–12.29
- cases following 12.30–12.49
- Merchant Shipping Act 1979 12.9 – 12.12
- summary of law before 12.45
- Merchant Shipping Act 1995
- framework of 1976 Convention and Merchan Shipping Act 1995 12.13
- Merchant Shipping Act 1995 and 1976 Limitation Convention 12.50–12.54
- Merchant Shipping (Distress Signals and Prevention of Collisions) Regulations 1989 11.5
- Rule 24
- text 1113 – 1114
- Rule 35
- text 1114 – 1115
- Minnehaha, The
- obligations of the tug 2.5–2.11
- salvage 8.25–8.26
- mobilisation
- Bargehire 2021 6.55
- Heavycon 2007 7.80
- Supplytime 2017 5.48
- MTSA, compliance with
- Supplytime 2017 5.108–5.110
- Towcon 2021 4.451–4.461
- mutual waiver of recourse
- Supplytime 2017 5.4, 5.22–5.23
- named tug
- contract for 2.29–2.41
- navigation
- by tug and tow 11.16–11.42
- rules 11.4–11.5, 11.32–11.42
- negligence, gross
- Towcon 2021 4.184–4.190
- Netherlands Tug Owners Conditions 1951
- text 1117 – 1120
- New Jason clause
- Supplytime 2005 5.255–5.257
- non-lien
- Bargehire 2021 6.140–6.142
- non-suit clause
- UK Standard Conditions for Towage and Other Services 3.97
- non-waiver clause
- Towcon 2021 4.119
- notice of readiness
- Heavycon 2007 7.69
- Projectcon 7.222
- notices
- Heavycon 2007 7.66–7.68
- Projectcon 7.222
- Supplytime 2017 5.275–5.276
- Towcon 2021 4.462–4.466
- Wreckhire 2010 10.68
- noxious or hazardous substances
- Supplytime 2017 5.216–5.221
- obligations of the tow
- duty of co-operation 2.82–2.83
- fitness for towage service 2.69–2.77
- The Julia 2.66–2.68
- proper seamanship during towage service 2.78–2.81
- obligations of the tug
- abandonment of towage 2.59–2.65
- completion of service 2.53
- contract for named tug 2.29–2.42
- control, question of 2.51–2.52
- fitness of tug for towage service 2.17–2.28
- identifying which vessel is in control 2.50
- interruptions in course of towage 2.54–2.58
- The Julia 2.5–2.14
- The Minnehaha 2.5–2.14
- nature of 2.18–2.28
- performance of service 2.43–2.52
- preparation for towage 2.15–2.16
- Supply of Goods and Services Act 1982 2.2–2.14
- tug in control of service 2.51–2.52
- offshore industry forms
- towage contracts 1.35–1.42
- offshore unit, meaning
- Windtime form 5.352
- order of precedence
- Supplytime 2017 5.24
- overpayments
- Salvcon 2005 9.52
- passage through canals
- Towcon 2021 4.88
- payment
- Projectcon
- delay payment 7.226–7.229
- Salvcon 2005
- free time and delay payments 9.54–9.57
- price and conditions of payment 9.48–9.53
- delay payments 9.52
- lump sum 9.48–9.50
- overpayments 9.52
- termination for non or late payment 9.53
- time for payment and interest 9.82
- Supplytime 2017 5.111–5.133
- Towcon 2021
- delay payments 4.94–4.97
- free time/delay payments 4.84–4.97
- price and conditions of payment 4.66–4.79
- Towhire 2021
- absence of delay payments and free time 4.474
- anti-deduction clause 4.473
- hire 4.472–4.474
- price and payment clause 4.472–4.474
- Wreckhire 2010
- price and conditions of payment 10.51–10.52
- Wreckstage 2010 10.84
- performance of service
- obligation of the tow 2.43–2.52
- permits
- Heavycon 2007 7.56
- Salvcon 2005 9.77
- Towcon 2021 4.120–4.123
- Wreckhire 2010 10.39
- Wreckstage 2024 10.109–10.110
- place of departure
- Towcon 2021 4.50–4.63
- Towhire 2021 4.469, 4.472
- place of destination
- Towcon 2021 4.64–4.65
- pollution
- Heavycon 2007 7.95–7.96
- Supplytime 2017 5.222–5.225
- Wreckhire 2010 10.76–10.78
- port congestion
- Heavyliftvoy 7.153–7.154
- pre-contractual disclosure 1.59 – 1.65
- preparation for towage
- obligations of the tug 2.15–2.16
- price
- Heavyliftvoy
- bunker price adjustment 7.163–7.166
- Salvcon 2005
- price and conditions of payment 9.48–9.53
- Towcon 2021
- bunker price adjustment clause 4.80–4.83
- price and conditions of payment 4.66–4.79
- Towhire 2021
- price and payment clause 4.472–4.474
- Wreckhire 2021
- price and conditions of payment 10.51
- Wreckstage 2010
- price and conditions of payment 10.84
- Projectcon
- advance notices 7.222
- approval of cargo and vessels 7.223–7.224
- bills of lading 7.232–7.233
- boxes 7.185
- cancelling 7.218–7.221
- cargo notes 7.232–7.233
- commencement of loading 7.218–7.221
- contractual voyage 7.190
- definitions 7.189
- delays 7.210
- delay payments 7.226–7.229
- delivery 7.218–7.221
- deviation 7.210
- discharging 7.213–7.216
- free time 7.226–7.229
- freight 7.225
- knock for knock 7.230–7.231
- loading 7.213–7.216, 7.218–7.221
- lying aground 7.191–7.193
- marine warranty surveyor 7.223–7.224
- mutual indemnities 7.230–7.231
- notes 7.232–7.233
- notice of readiness 7.222
- obligation of due despatch 7.209
- obligation as to seaworthiness of vessels 7.194–7.208
- Part I 7.185
- Part II 7.186–7.233
- parties’ responsibilities for ballasting of barge for cargo operations 7.211–7.212
- parties’ responsibilities for loading and discharging 7.213–7.216
- period within which barge is to be delivered 7.218–7.221
- readiness 7.222
- receipts 7.232–7.233
- rights to cancel 7.218–7.221
- structure 7.184
- taxes 7.217
- proper seamanship during towage service 2.78 – 2.81
- control, question of 2.79
- tow in control 2.80
- tug in control 2.81
- protection of environment
- Salvcon 2005 9.66–9.69
- provide and pay for clauses
- Supplytime 2017 5.90–5.94
- charterers to provide 5.93–5.94
- owners to provide 5.92
- quarantine
- Heavycon 2007 7.58
- readiness for departure
- Towcon 2021 4.58–4.63
- redelivery
- Bargehire 2021 6.76–6.86, 6.108–6.111, 6.132–6.137
- Supplytime 2017 5.39–5.49
- reduced daily rate of hire for late completion
- Wreckhire 2010 10.55
- removal, wreck
- cost of 10.1
- importance of 10.1
- Supplytime 2017 5.226
- repudiatory breach
- Supplytime 2017
- termination for, and accumulated off hire 5.302–5.304
- reservation of special rights
- UK Standard Conditions for Towage and Other Services 3.92–3.93, 3.191
- restricted waters
- Towcon 2021 4.88–4.91
- riding crew
- towage contracts 4.124–4.130
- rotation and replacement of craft, equipment and personnel
- Wreckhire 2010 10.79
- salvage see also Salvcon 2005 see also Salvhire 2005
- burden of proof 8.64–8.69
- danger 8.37–8.55
- effect of conversion into salvage upon towage contract 8.70–8.75
- engaged services 8.111–8.130
- Salvage Convention 1989, and 8.119–8.130
- essential criteria for 8.9–8.10
- from towage service to salvage service 8.22–8.110
- historical relationship with towage 8.1–8.4
- issues and questions arising 8.23–8.24
- The Minnehaha 8.25–8.26
- misconduct of tug, effect of 8.101–8.110
- early authorities 8.102–8.104
- modern approach 8.105–8.110
- nature of 8.5–8.7
- principal feature 8.7
- relationship under common forms of contract 8.76–8.88
- relationship with towage 8.1–8.4
- Salvage Convention 1989 8.8–8.21
- service or services outside scope of contract 8.56–8.63
- services rendered under existing contracts 8.35
- standard of proof 8.64–8.69
- sub-contracting of tugs 8.95–8.100
- subject of 8.11–8.13
- success 8.18–8.21
- Supplytime 2017 5.235–5.240
- liberty to perform 5.237–5.238
- rendered to charterer’s property 5.239–5.240
- text as expressed in Salvage Convention 8.18
- towage contracts providing for “no salvage charges” 8.89–8.94
- effect upon rights of tug crew 8.94
- Towcon 2021 4.161–4.166
- tug and tow, of 8.131–8.133
- unforeseen circumstances putting tow in danger 8.37–8.55
- circumstances creaive of danger for tow 8.46–8.51
- danger to tow no of itself sufficient 8.52–8.54
- no need for danger to tug 8.55
- unforeseen circumstances 8.38–8.45
- voluntariness 8.15–8.17
- Salvcon 2005 9.1 – 9.9
- box 4 9.23–9.25
- box 3 and 5 9.26
- boxes 6–8 9.27–9.28
- box 9 9.29–9.31
- boxes 10–16 9.32
- box 17 9.33
- commentary on Part II 9.40–9.104
- definitions 9.42–9.45
- employment and area of operations 9.58–9.61
- extra costs 9.83–9.84
- free time and delay payments 9.54–9.57
- general provisions 9.93–9.99
- genesis 9.10–9.18
- hirer’s representative 9.76
- insurance 9.85–9.87
- law and arbitration procedure 9.100–9.104
- liabilities 9.88–9.92
- injury to or death of those involved in service 9.90
- loss of or damage caused to or by vessels involved 9.91
- other losses and statutory limitations 9.92
- master and crew 9.62
- nature of 9.19–9.20
- nature of services to be provided by owner 9.46–9.47
- organisation 9.21–9.39
- owner’s obligations 9.63–9.75
- no claims for salvage 9.70–9.75
- protection of environment 9.66–9.68
- Part I 9.22–9.33
- Part II 9.34–9.104
- permits 9.77
- price and conditions of payment 9.48–9.53
- delay payments 9.52
- lump sum 9.48–9.51
- overpayments 9.52
- termination for non or late payment 9.53
- seaworthiness of vessel 9.79
- security 9.85–9.87
- structure 9.21–9.39
- substitution of vessel 9.80
- termination 9.81
- text 1033 – 1040
- time for payment and interest 9.82
- towing gear and equipment 9.78
- Salvhire 2005 9.105
- genesis 9.10–9.18
- nature of 9.19–9.20
- text 1041 – 1048
- saving of life
- Supplytime 2017 5.235–5.240
- Scandinavian Tugowners Standard Conditions 1959 revised
- text 1121–1123
- seamanship during towage 2.78 – 2.81
- control, question of 2.79
- tow in control 2.80
- tug in control 2.81
- seaworthiness
- Heavycon 2007
- obligation as to seaworthiness of vessel 7.33–7.42
- Projectcon
- obligations as to seaworthiness of vessel 7.194–7.208
- Salvcon 2005
- seaworthiness of vessel 9.79
- Supplytime 2017
- description, class and seaworthiness as at delivery 5.53–5.54
- seaworthiness and class during service 5.55–5.58
- Towcon 2021
- seaworthiness of tug 4.131–4.133
- UK Standard Conditions for Towage and Other Services
- personal fault of tug owner as to seaworthiness 3.68–3.70
- security
- Salvcon 2005 9.85–9.87
- Towcon 2021
- financial 4.437
- for claims 4.462–4.466
- Wreckhire 2010 10.60
- severability
- Supplytime 2017
- boilerplate severability clause 5.278
- shapes
- collisions involving tug and tow 11.23–11.29
- sound signals
- collisions involving tug and tow 11.30–11.31
- space
- Supplytime 2017 5.76–5.77
- standard form contract
- role of 1.31–1.45
- structural alterations
- Supplytime 2017 5.59–5.67
- sub-contracting
- salvage 4.165, 8.95–8.100, 9.5, 9.7–9.10
- wreck removal 10.43–10.46
- sublet
- Supplytime 2017 5.242
- substitution
- Bargehire 2021 6.44
- Heavycon 2007 7.85
- Salvcon 2005 9.80
- Towcon 2021 4.143–4.144
- UK Standard Conditions for Towage and Other Services 3.83–3.91, 3.189–3.190
- success
- salvage 8.18–8.21
- Supply of Goods and Services Act 1982
- Bargehire 2008 6.10–6.11
- obligations of the tug 2.2–2.4
- Supplytime 2005
- both-to-blame omnibus time charter provisions 5.255–5.257
- bunkers 5.95–5.107
- charterer’s right of termination 5.296–5.297
- consequential damages 5.190–5.191
- early termination 5.291–5.295
- epidemic/fever 5.246, 5.252
- events giving rise to right to terminate 5.314–5.329
- breakdown 5.316–5.321, 5.323
- force majeure 5.324
- loss of vessel 5.315
- repudiatory breach 5.314, 5.325–5.329
- general average 5.255–5.257
- New Jason clause 5.255–5.257
- procedure for termination for cause 5.306–5.313
- survey 5.68–5.73
- termination by either party for cause 5.305
- text 873 – 888
- Supplytime 2017
- additional equipment 5.59–5.67
- adjustment of hire 5.112
- Annexes 5.330–5.343
- charterers’ personnel (passengers) 5.340
- crane operations 5.339
- crew qualification 5.336–5.337
- dynamic positioning 5.341–5.342
- extended offshore support 5.335
- helicopter and helideck operations 5.334
- walk to work 5.338
- area of operation 5.74–5.82
- assignment 5.242
- audits and inspections 5.69–5.73
- banking days 5.31
- BIMCO anti-corruption clause for time charter parties 5.262
- BIMCO designated entities clause for time charter parties 5.265
- BIMCO dispute resolution clause 2016 5.274
- BIMCO sanctions clause for time charter parties 5.264–5.265
- boilerplate severability clause 5.278
- both-to-blame omnibus time charter provisions 5.255–5.257
- bunkers 5.95–5.107
- cancellation in light of war 5.245
- cancelling clause 5.45
- cargo and services 5.39–5.49
- certificates 5.75
- charter period 5.370–5.372
- charterer’s right of termination 5.296–5.297
- cleanliness on delivery 5.41
- CMID 5.73
- condition of vessel 5.50–5.58
- confidentiality 5.271–5.273
- consent to proposed change or alteration 5.61
- consequential damages 5.190–5.191
- contractual definitions 5.26–5.34
- delivery 5.39–5.49
- demobilisation 5.38
- description, class and seaworthiness as at delivery 5.53–5.54
- description of parties to contract 5.35
- disease 5.251–5.254
- drugs and alcohol policy 5.261
- drydocking 5.152–5.153, 5.158
- early termination 5.291–5.329
- employment 5.74–5.82
- entire agreement 5.279–5.284
- epidemic/fever 5.246, 5.252
- explosives and dangerous cargo 5.78
- extension hire 5.111–5.133
- force majeure 5.146, 5.268–5.269, 5.300–5.301, 5.324
- fuel 5.96–5.102
- general average 5.255–5.257
- general provisions 4.467–4.468
- genesis 5.1–5.13
- “Group” coverage of knock for knock 5.164–5.166
- “Groups,” concepts of 5.27
- hazardous or noxious substances 5.216–5.221
- headings 5.277
- health and safety 5.260
- hire 5.111–5.133
- hull and machinery 5.53, 5.57
- ice clause 5.246–5.247, 5.249
- ice conditions 5.246–5.250
- identity and name of vessel chartered 5.35
- infectious or contagious diseases clause 5.246, 5.254, 5.268
- insurance 5.227–5.234
- invoicing 5.111–5.133
- ISPS, compliance with 5.108–5.110
- knock for knock
- charterers 5.167–5.170
- “Group” coverage 5.164–5.166
- main changes to regime 5.160–5.163
- more limited form 5.167–5.174
- owners 5.167–5.169, 5.171
- lay up 5.82, 5.289–5.290
- lay-up clause 5.82
- liabilities
- consequential damages 5.190–5.209
- excluded losses 5.190–5.191, 5.210–5.214
- “Group” coverage of knock-for-knock 5.164–5.166
- hazardous and noxious substances 5.216–5.221
- heads of excluded loss and damage 5.185–5.189
- Himalaya clause 5.215
- knock-for-knock 5.167–5.174
- limitation of 5.215
- main changes to knock-for-knock regime 5.160–5.163
- scope of exemption/indemnity 5.175–5.184
- scope of losses excluded 5.193–5.205
- liberty to deviate 5.236
- liberty to perform salvage 5.237–5.238
- licences 5.75, 5.384
- lien 5.241
- loading of fuel 5.103–5.107
- lump sum mobilisation charge 5.18, 5.48
- main changes to knock-for-knock regime 5.160–5.163
- maintenance 5.152–5.159
- master and crew 5.83–5.89
- compliance with orders 5.84–5.8
- ordinary features 5.83
- MLC 2006 5.263
- mobilisation 5.48–5.49
- mutual waiver of recourse 5.22–5.23
- New Jason 5.255–5.257
- notices 5.275
- off hire 5.302–5.304
- maintenance and dry-docking 5.152–5.159
- offshore units 5.32, 5.186, 5.188
- omnibus provisions 5.255–5.285
- order of precedence 5.24
- organisation 5.17–5.25
- “original condition” 5.64–5.65
- OVID 5.73
- payment for fuel 5.103–5.107
- payments 5.111–5.133
- period 5.35–5.38
- permission 5.75, 5.384
- ports and places affected by ice conditions and disease 5.246–5.250
- principal change to Supplytime 2005 5.19
- provide and pay for clauses 5.90–5.94
- charterers to provide 5.93–5.94
- owners to provide 5.92
- redelivery 5.39–5.49
- repudiatory breach 5.302–5.304
- requirements for services 5.74
- salvage 5.239–5.240
- salvage rendered to charterer’s property 5.239–5.240
- saving of life 5.239–5.240
- scope of each party’s group 5.29
- scope of exemption/indemnity 5.175–5.184
- seaworthiness and class during service 5.55–5.58
- singular/plural 5.285
- species of time charterparty 5.14–5.16
- standard BIMCO time charter provisions 5.258–5.285
- structural alterations 5.59–5.67
- structure 5.17–5.25
- sublet 5.242
- substitute vessel 5.243
- survey 5.69–5.73
- suspension and termination 5.111–5.133
- taxes 5.266
- termination by either party “for cause” 5.298–5.301
- bankruptcy 5.300
- for cause 5.298
- confiscation 5.300
- events giving rise to termination under 5.305–5.329
- force majeure 5.300–5.301
- insurance 5.300
- loss of vessel 5.300–5.301
- procedure 5.306–5.313
- requisition 5.300
- termination for repudiatory breach and accumulated off hire 5.302–5.304
- text 873 – 888
- United States MTSA legislation, compliance with 5.108–5.110
- use with Supplytime 89 and 5.343
- vessel’s space 5.76–5.77
- war cancellation clause 5.245
- war risks 5.244
- wreck removal 5.226
- survey
- Bargehire 2021 6.76–6.86
- Supplytime 2005 5.68
- Supplytime 2017 5.69–5.73
- Windtime 5.355
- suspension or termination
- Wreckhire 2010 10.47–10.48
- Wreckstage 2010 10.82
- swell
- Heavyliftvoy 7.153–7.154
- taxes
- Heavycon 2007 7.57
- Heavyliftvoy 7.161–7.162
- Projectcon 7.217
- tender
- UK Standard Conditions for Towage and Other Services 3.9
- terminal charges
- Heavyliftvoy 7.159
- termination
- Heavycon 2007 7.86
- Salvcon 2005 9.81
- for non or late payment 9.53
- Supplytime 2005
- charterer’s right of 5.296–5.297
- early termination 5.291–5.329
- by either party for cause 5.305
- events giving rise to right 5.314–5.329
- procedure for termination for cause 5.306–5.313
- Supplytime 2017
- charterer’s rights to termination 5.298–5.301
- early termination 5.286, 5.291–5.329
- by either party for cause 5.298–5.301
- for repudiatory breach and accumulated off hire 5.302–5.304
- Towcon 2021
- by hirer 4.167–4.169
- by tugowner 4.170–4.175
- in whole 4.428–4.429
- Windtime form
- early termination 5.362
- Wreckhire 2010
- suspension or termination 10.47–10.48
- Wreckstage 2010
- suspension or termination 10.82
- time charterparty
- Supplytime 2017 5.14–5.16
- time waiting to berth
- Heavyliftvoy 7.153–7.154
- towage
- definition 1.1–1.2
- towage contracts
- Admiralty Court, effect of general equitable jurisdiction of 1.80–1.81
- bailment, and 1.14–1.30
- BIMCO ocean towage 1.35–1.42
- common Europe towage forms 1.43
- construction
- no special rules 1.69–1.79
- Consumer Rights Act 2015 1.66
- contract for services, as 1.12–1.13
- exemption clauses 1.66–1.68
- gratuitous towage 1.9–1.11
- implied terms 1.44–1.45
- jurisdiction of Admiralty Court 1.80–1.81
- making of
- authority of master to contract to be towed 1.46–1.54
- authority of master to take vessel in tow 1.55–1.58
- The Kingalock 1.59–1.65
- pre-contractual disclosure 1.59–1.65
- offshore industry forms 1.35–1.42
- pre-contractual disclosure 1.59–1.65
- relationship between towage and salvage 1.4–1.8
- standard form contract, role of 1.31–1.45
- towage arises from 1.3
- UK Standard Conditions 1.34
- Towcon 2008 4.2
- genesis 4.1
- Part I 4.12–4.30
- Annex A 4.16–4.20
- boxes 4 to 12 4.13
- boxes 13 to 21 4.14–4.15
- boxes 18 to 21 4.21–4.224
- boxes 22 to 24 4.25
- boxes 25 to 30 4.26–4.18
- box 38 4.29
- boxes 39 and 40 4.30
- text 787 – 806
- Towcon 2021 4.3 – 4.6
- additional charges and extra costs 4.102–4.107
- additional costs 4.433
- anti-deduction clause 4.72–4.79
- The A Turtle, decision in 4.275–4.392
- causes of excluded losses 4.353–5.356
- circumstances of application 4.372–4.392
- development of definition of heads of loss 4.236–4.352
- heads of excluded loss and damage 4.300–4.323, 4.357–4.371
- other (financial) losses 4.324–4.325
- bunker price adjustment clause 4.80–4.83
- cancelling date and hirer’s right to cancel 4.98–4.101
- dispute resolution 4.462–4.466
- due fulfilment 4.433
- earning of lump sum 4.72–4.79
- free time and delay payments 4.84–4.97
- bunkering 4.92
- connection/disconnection 4.85–4.87
- legal nature of “delay payment” 4.94–4.97
- restricted waters 4.88–4.91
- when payment is due 4.93
- general provisions 4.467–4.468
- genesis 4.1
- heads of excluded loss and damage 4.300–4.323
- Himalaya clause 4.411–4.416
- hirer’s group 4.39
- ice clause 4.156–4.160
- insurance 4.393–4.407, 4.433
- interest 4.108–4.112
- ISPS, compliance with 4.451–4.461
- liabilities and mutual indemnities 4.176–4.274
- construction of clause 4.194–4.224
- contractual indemnities 4.225–4.226
- generally 4.176–4.183
- gross negligence 4.184–4.190
- hybrid knock-for-knock clauses 4.191–4.193
- injury to or death of those engaged in towage 4.227–4.247
- loss of or damage to or caused by tug and tow 4.248–4.250
- scope of exclusion/exemption 4.251–4.274
- wilful misconduct 4.184–4.190
- liberty to deviate 4.432
- lien 4.408–4.410
- lump sum 4.66–4.79
- nature of 4.7–4.10
- necessary deviation or slow steaming 4.145–4.155
- deviation from original route 4.148
- generally 4.145–4.147
- impermissible deviations 4.154
- liberties to deviate 4.149–4.153
- notification of deviations 4.155
- non-towage specific BIMCO standard charterparty clauses 4.434–4.436
- organisation 4.11–4.32
- Part I 4.12–4.30
- Annex A 4.16–4.20
- boxes 4 to 12 4.13
- boxes 13 to 21 4.14–4.15
- boxes 18 to 21 4.21–4.224
- boxes 22 to 24 4.25
- boxes 25 to 30 4.26–4.18
- box 38 4.29
- boxes 39 and 40 4.30
- Part II 4.31–4.274
- permits and certification 4.120–4.123
- place of connection 4.39, 4.50–4.63
- place of departure 4.39, 4.50–4.63
- place of disconnection 4.39, 4.64–4.65
- place of destination 4.39, 4.64–4.65
- price and conditions of payment 4.66–4.79
- readiness of tow for departure 4.58–4.61
- reasonable judgment 4.423–4.427
- restricted warriors 4.39
- riding crew 4.124–4.130
- salvage 4.161–4.166
- security 4.437, 4.462–4.466
- services 4.42–4.49
- short or alternative performance 4.430
- structure 4.11–4.32
- substitution of tugs 4.143–4.144
- taking of route longer than contemplated route 4.431–4.468
- termination by hirer 4.167–4.169
- termination by tug owner 4.170–4.175
- termination in whole or refusal to perform in part 4.428–4.429
- text 767 – 786
- time bar provisions 4.447–4.450
- the tow 4.39–4.41
- towing gear and use of tow’s gear 4.134–4.142
- tow-worthiness of the tow 4.113–4.119
- certificate of tow-worthiness 4.117–4.118
- fitness of tow 4.113–4.116
- non-waiver clause 4.119
- tug 4.39
- tugowner’s group 4.39
- tug’s seaworthiness 4.131–4.133
- US MTSA legislation, compliance with 4.451–4.461
- war and other risks and difficulties 4.417–4.422
- warranty of authority 4.438–4.446
- Towhire 2008
- absence of delay payments and free time 4.474
- anti-deduction clause 4.473
- bunkers and allied matters 4.475–4.480
- cancelling date 4.481
- deviation during charterparty 4.482
- hire 4.472
- price and payment clause 4.472–4.474
- Towhire 2021 4.3 – 4.6
- genesis 4.1
- nature of 4.7–4.10
- organisation 4.469–4.471
- structure 4.469–4.471
- towing
- UK Standard Conditions for Towage and Other Services
- cesser of towing 3.34–3.41
- service other than towing 3.44
- ‘whilst towing’: meaning 3.11–3.16
- towing gear
- Salvcon 2005 9.78
- Towcon 2021 4.134–4.142
- tow-worthiness of tow
- Towcon 2021 4.113–4.119
- certificate of tow-worthiness 4.117–4.118
- fitness of tow 4.113–4.116
- non-waiver clause 4.119
- transportation
- Heavycon 2007 7.70–7.74
- tug
- obligations of the
- contract for named tug 2.29–2.41
- fitness of tug for towage service 2.17–2.28
- tug in control of service 2.51–2.52
- tug and tow
- aggregation for tug and tow for purposes of limitation fund 12.18–12.54
- application of Limitation Convention between tug and tow 12.15–12.17
- as between tug and tow 3.45–3.54
- collisions 11.1–11.68 see also collisions involving tug and tow
- effect of common ownership of tug and tow 11.63–11.68
- navigation by tug and tow 11.16–11.42
- practical importance for tug and tow 13.21–13.22
- questions specific to tug and tow 13.10
- salvage
- tug and tow, of 8.131–8.133
- special questions arising in relation to tug and tow 12.14
- Towcon 2021
- damage to or caused by tug and tow 4.248–4.250
- loss of or caused by tug and tow 4.248–4.250
- tug and tow: how treated 11.37–11.42
- UK Standard Conditions for Towage and Other Services
- effect as between tug and tow 3.45–3.46
- effect as between tug and tow and third parties 3.47–3.54
- tugowner
- Netherlands Tug Owners Conditions 1951
- text 1117 – 1121
- Scandinavian Tugowners Standard Conditions 1959 revised
- text 1121 – 1123
- Towcon 2021
- termination by tugowner 4.170–4.175
- UK Standard Conditions for Towage and Other Services
- personal fault of tug owner as to seaworthiness 3.68–3.70
- UK Standard Conditions 1.34
- UK Standard Conditions for Towage and Other Services 3.1 – 3.5
- cesser of towing 3.34–3.35, 3.133–3.135
- commencement of service 3.137–3.138
- commencement of towing 3.17–3.32, 3.121–3.132
- end of service 3.139–3.141
- exemption clause 3.55–3.82, 3.158–3.188
- further exemption clause 3.94–3.96, 3.192–3.195
- genesis and rationale 3.99–3.106
- Himalaya clause 3.196–3.198
- hirer’s warranty of authority 3.42, 3.149–3.152
- introductory and definitions 3.6–3.40, 3.107–3.148
- involvement of more than one tug 3.33
- law and jurisdiction clause 3.98, 3.199–3.203
- non-suit clause 3.97, 3.196–3.198
- personal fault of tug owner as to seaworthiness 3.68–3.70
- reservation of special rights 3.92–3.93, 3.191
- substitution of tug 3.83–3.91, 3.189–3.190
- text
- revised 1986 765 – 766
- revised 2024 763 – 764
- tug not in position of proximity or risk 3.71–3.73
- vicarious liability of tow for tug 3.43–3.54, 3.153–3.157
- whilst towing 3.11–3.35
- US Customs
- Heavyliftvoy
- BIMCO clause for special US Customs requirements 7.177–7.178
- BIMCO U.S. Customs advance notifications 7.177–7.178
- vessel
- UK Standard Conditions for Towage and Other Services 3.26
- vessel, condition of
- Supplytime 2017 5.50–5.58
- Windtime form 5.354
- vessel, loss of
- Salvcon 2005 9.91–9.92
- vessel specification
- Towcon 2021 4.16–4.20
- vessel substitute
- Supplytime 2017 5.243
- vessel, third party
- collisions involving tug and tow
- effect of common ownership of tug and tow 11.63–11.68
- liabilities between tug, tow and third party vessel 11.59–11.68
- third party vessel also to blame 11.60–11.62
- third party vessel not to blame 11.59
- vessel’s space
- Supplytime 2017 5.76–5.77
- vicarious liability of tow for tug 3.43 – 3.54
- voluntariness 8.15 – 8.17
- voyage
- Heavycon 2007 7.32–7.43
- Heavyliftvoy 7.123–7.124
- Projectcon 7.190
- war cancellation clause 5.245
- war risk escalation clause 4.108
- war risks
- Supplytime 2017 5.244
- Towcon 2021 4.417–4.422
- warranty of authority
- Towcon 2021 4.438–4.446
- UK Standard Conditions for Towage and Other Services
- hirer’s warranty of authority 3.42, 3.153–3.157
- ‘whilst towing’ meaning of term in UK Standards Conditions 3.11–3.16
- Windtime
- text 889 – 914
- Windtime form
- bunkers 5.359
- condition of vessel 5.354
- conduct 5.358
- definitions 5.352–5.353
- early termination 5.362
- knock-for-knock 5.360–5.361
- master and crew 5.356–5.357
- mutual indemnities 5.360–5.361
- offshore unit, meaning 5.352
- special aspects 5.349–5.351
- time charterparty for special offshore service 5.344–5.348
- vessel audit and survey 5.355
- wreck removal
- cost of 10.56–10.59
- importance of 10.1
- Supplytime 2017 5.226
- Wreckcon 10.2 – 10.6 , 10.61 – 10.62 , 10.125
- Wreckfixed 2010
- general description 10.125–10.128
- text 1101 – 1112
- Wreckstage 2010, and 10.129
- Wreckhire 2010
- Annexes 10.21
- arbitration and mediation 10.73–10.74
- bonus for prompt completion by contractor 10.53–10.54
- change of work method and/or personnel, craft and equipment 10.33–10.37
- company representative 10.30–10.32
- definitions 10.22–10.23
- delays 10.40–10.46
- delivery or disposal of vessel by contractor 10.49–10.50
- expert evaluation of alteration of rates of hire and losses of time 10.69–10.72
- extra costs incurred in disposing of vessel 10.59
- extra costs incurred in relation to services 10.56–10.58
- general provisions 10.80
- Himalaya clause 10.68
- hire, rates of 10.69–10.72
- insurance 10.75
- knock-for-knock 10.76–10.78
- liabilities 10.61–10.67
- lien 10.68
- losses of time 10.69–10.72
- miscellaneous responsibilities of parties 10.38
- notices 10.68
- Part I 10.16–10.20
- Part II 10.22–10.80
- permits 10.39
- pollution 10.76–10.78
- price and conditions of payment 10.51
- rates of hire 10.69–10.72
- reduced daily rate of hire for late completion 10.55
- rotation and replacement of craft, equipment and personnel 10.79
- security 10.60
- services 10.24–10.29
- standard provisions 10.68
- structure 10.15
- suspension or termination 10.47–10.48
- text 1049 – 1062
- time, losses of 10.69–10.72
- time for suit 10.68
- Wreckstage 2010 10.81
- delivery and/or disposal 10.83
- extra costs 10.85
- price and conditions of payment 10.84
- suspension or termination 10.82
- Wreckstage 2024
- Annexes 10.91
- change of method and project changes 10.107–10.108
- company representative 10.99
- definitions 10.93–10.94
- delays 10.111–10.113
- expert evaluation 10.117–10.123
- genesis 10.86–10.88
- liabilities 10.115
- miscellaneous and permits 10.109–10.110
- Part I 10.89–10.90
- Part II 10.92–10.124
- permits 10.109–10.110
- risk allocation procedure 10.100–10.106
- services 10.95–10.98