Construction Law Reporter
EIGER FUNDING (PCC) LTD v RIDGE AND PARTNERS LLP
[2026] EWHC 609 (TCC), Technology and Construction Court, Mr Adrian Williamson KC, sitting as a Deputy Judge of the High Court, 16 March 2026
Professional negligence – Scope of duty – Breach of duty – Loss recoverable
The claimant, Eiger Funding (PCC) Ltd, brought a claim for damages for professional negligence against the defendant, Ridge
and Partners LLP. In 2018 the claimant lent £12.9 million to Signature Living Residential Ltd, part of a group of companies,
in order to fund the completion of a development in Liverpool. At the time of the loan it was anticipated that the development
would be completed in the first half of 2019 so that the loan would be repaid within 12 months. This did not happen and in
April 2020 the Signature companies were placed in administration. The outcome of all of this was that the claimant sustained
a significant loss on the transaction and it sought to recover damages from the defendant, who had acted as independent fund
monitoring surveyors, in respect of the losses which it had sustained. The Deputy Judge held that the defendant owed to the
claimant a duty to advise with reasonable care and skill upon: (i) the adequacy of the contract sum for the project; (ii)
any risks which could result in a cost overrun; (iii) any risks which could impact on the completion of the development in
accordance with the programme; and (iv) the costs to complete the development. It was held that that duty had been breached
in relation to project pricing and the cost to completion, the failure to give advice in connection with the relationship
between the different parts of Signature group of companies which increased the risk to the claimant and in failing appropriately
to handle the conflict of interest which arose from the fact that it had acted both for the Signature group and the claimant.
These breaches of duty were also found to be causative of loss to the claimant. In relation to the proof of loss and scope
of the duty owed by the defendant to the claimant, it was held that the risk that the duty of the defendant was supposed to
guard against was that the claimant would enter into a loan agreement to provide financing for the development on the basis
of construction costs or costs to complete the development which made the loan unduly hazardous. Based on the findings made
by the Deputy Judge, there was "a significant risk that substantial costs would be incurred over and above those put forward
by Signature" and the loss suffered "represented the fruition of that risk". Thus there was "a sufficient nexus between a
particular element of the harm" for which the claimant sought to recover damages and the subject matter of the duty of care
owed by the defendant to the claimant. It was held that the present case was a "distressed asset" case in the sense that
the loss was suffered by the claimant as soon as the loan was made. Taking account of benchmarked evidence in relation to
the cost of completion of a project such as the one funded by the claimant, it was held that the loss was fixed at £2.5 million
and damages of that sum were awarded in favour of the claimant.