Delay and Disruption in Construction Contracts
| Delay and Disruption in Construction Contracts, 6th Edition, (c) 2025 |
Page 1277
Index
- Acceleration
- breach of contract 12–002
- constructive see Constructive acceleration
- costs 11–090
- culpable delay, and 11–031
- design programmes 2–106
- effect 11–087
- entitlement to extension of time, and 11–072
- estimates of cost 11–087
- failure to accelerate 12–008–12–209
- breach of obligation 12–011, 12–013
- causation 12–197, 12–201
- compensation 12–008
- completion on time 12–012, 12–014
- culpable delay 12–014, 12–020, 12–041, 12–051, 12–052
- demurrage claims 12–206
- foreseeable delay 12–033
- foreseeable losses 12–188, 12–190
- identification of loss 12–195, 12–205
- instructed acceleration 12–071
- instructions to recover 12–041, 12–051, 12–053–12–057
- limitation on liability 12–204
- liquidated damages 12–049, 12–050, 12–057, 12–065, 12–116, 12–118, 12–123, 12–125, 12–126, 12–127, 12–132, 12–134, 12–135
- redress 12–074, 12–096
- termination of contract 12–207–12–209
- instructed 12–071, 12–077, 12–130
- lost productivity, and 18–043–18–049
- meaning 12–015–12–018
- methods 12–136–12–186
- power to instruct 12–041, 12–053, 12–068
- programme of 4–208
- standard form provisions 12–021–12–092
- Access 4–163–4–169
- Act of God 4–055, 4–058, 4–069
- Activity coding 8–230
- Activity durations 8–125–8–141
- Acts and/or omissions of developer 4–028–4–036
- Acts of State 2–153
- Acts of third parties 4–172–4–187
- Acts or omissions of third parties
- causation, and 4–173
- Additional work
- guidelines 13–016
- Adjudication 25–022–25–028
- final and binding 25–029
- Adjudication in United Kingdom 26–001–26–063
- complex decisions 26–003, 26–007–26–022
- costs 26–004, 26–023–26–037, 26–063
- definition of construction contract 26–005, 26–038–26–044
- human rights aspects 26–003, 26–007–26–022
- interest 26–004, 26–023–26–037
- limitation periods 26–002
- recovering costs 26–063
- residential occupiers 26–045–26–047
- sequential 26–006, 26–048–26–062
- single disputes 26–006, 26–048–26–062
- Adverse weather
- Alliancing 3–063–3–066
- Alternative dispute resolution 25–003, 27–033, 31–007
-
Ambiguities 13–110–13–135Page 1278
- American law
- equitable adjustment 1–015
- Antiquities 4–263–4–265
- Apportionment 21–001–21–073
- A/B estimates approach 21–058–21–061
- balance of evidence 21–005
- burden of proof approach 21–042
- but-for test 21–005
- case law 21–003
- causation 21–001–21–007
- City Inn approach 21–068–21–070
- common law 21–009–21–010
- compensation, and 21–010–21–012
- delay to completion 21–013–21–031
- delta estimates approach 21–062
- Devlin approach 21–043–21–045
- dominant cause approach 21–005, 21–046–21–053
- jury verdict approach 21–054–21–055
- logical processes 21–005
- loss and/or expense 21–032–21–036
- methods of apportionment of loss or expense 21–037–21–073
- modified global claim approach 21–056
- modified total cost approach 21–065
- nature of 21–004
- net effect approach 21–071–21–073
- prolongation issues, and 21–006
- tortious solution 21–040–21–041
- Approval of programmes 9–001–9–089
- Approximate bills
- Arbitration 25–030–25–034
- Arrow diagram 9–035–9–040
- Artificial obstructions 4–156
- As-built programme 8–058
- As-built impacted
- As-planned updated versus as-planned updated analytical method 16–068–16–075
- As-planned versus as-built 15–201–15–209
- Assessor
- discretion of court, and 24–040
- Bar chart 9–007–9–017, 10–122–10–126, 15–193–15–200
- Baseline programme 8–028–8–037
- Best endeavours
- Biddability risk 2–117–2–128
- bills of quantities 2–126
- claims conditions 2–123
- greenfield sites 2–120
- itemised bills of quantities 2–126
- lowest tendering contractor 2–122
- manifest error 2–125
- nature of 2–040
- precision in communication 2–124
- predetermined cost and time effect of variations 2–127
- preparation of tender documentation 2–121
- price, and 2–024
- Bill of quantities 13–075–13–109
- BIM 14–078–14–086
- acronym 14–071
- case law 14–115–14–116
- case studies 14–094–14–095
- collaboration 14–084–14–085
- communication of information 14–113–14–114
- conventional practice, and 14–074–14–077
- Cookham Wood 14–096–14–112
- definition 14–072–14–073
- future projects 14–100
- investment 14–090–14–091
- key documents 14–093
- legal, contractual and insurance issues 14–086
- levels of maturity 14–078–14–079
- overcoming barriers 14–092
- perceived barriers against adoption 14–083
- perceived benefits 14–081–14–082
- retrieval of information 14–111–14–112
- significance 14–080
- standard forms of contract 14–101–14–106
- UK and management of information 14–078
- what is arguably not 14–080
- Black Monday 2–149
- Bricklaying
- calculating duration 8–147
- Build-only contracts 3–019–3–032
- Buildability risk 2–113–2–116
- Building control 2–193–2–196
- Building Information Modelling (BIM) 14–067–14–119 see also BIM
- Business efficacy
- Calculating durations 8–142–8–162
- bricklaying 8–147
- Calculating time-related compensation 11–089
- Cascade diagram 9–045–9–046
- Cash flow monitoring 10–105–10–109
- Catastrophes
- Causation 15–021–15–147
- acts or omissions of third parties 15–054–15–062
- as-planned versus as-built 16–060–16–067
- bar charts 15–193–15–200
- collapsing technique 15–210–15–215
- completion delayed 15–128–15–137
- completion likely to be delayed 15–120–15–127
- completion likely to be or has been delayed 15–123–15–127
- contemporaneous analysis 15–018, 15–122
- delay to completion of works 15–085–15–15–107
- delay to progress of works 15–063–15–073
- developer’s acts or omissions 15–039–15–053
- expenditure of prime cost and provisional sums 15–033–15–038
- factual materials available 15–143–15–147
- failure to perform 15–077–15–084
- inference 15–166–15–219 see also Inference of causation
- instructed changes 15–027
- instructed variations 15–027–15–030
- matters to be identified 15–029
- occurrences 15–060–15–061
- primary 15–025–15–032
- proof of 15–108–15–165
- proportionality 15–148–15–165
- retrospective delay analysis 15–019–15–020
- secondary 15–063–15–073
- smoke and mirrors 15–220–15–231
- subject-matter of proof 15–138–15–142
- suspension of works 15–074–15–076
- terms of contract 15–112–15–119
- tertiary 15–085–15–107
- three-part chain 15–021–15–107
- visualisations 15–216–15–219
- voluntary or implied variations 15–027
- whatever is fair and reasonable 15–133–15–137
- Cause and effect matrix 15–174–15–179
- CDBs 27–040
- Change 13–001–13–199 see also Variation
- Change control 14–026–14–041
- clear factual evidence, need for 14–033
- Change management 11–045–11–070
- definitions 11–049
- effects of change see also Managing effect of change
- acceleration 11–085–11–088
- ad hoc changes 11–078
- change order procedure 11–077
- changed resources 11–072
- design changes 11–076
- disruption 11–074
- extensions of time 11–018, 11–020
- need for instructions 11–075
- sequence of works 11–020
- significance of change 11–073
- tenders, and 11–031–11–033
- variation 11–072, 11–077
- electronic submittals 11–056–11–057
- key dates 11–059–11–060
- management information structure 11–048
- programme 11–050–11–055
- progress records 11–058
- relationships 11–061–11–070
- roles 11–061–11–070
- supplements 11–045–11–070
- Change order procedure 4–109
- CIOB
- working group 11–031
- CIOB Complex Projects Contract
- CIOB Contracts for Use with Complex Projects (CPC 2013) 3–009–3–015 see also CPC 2013
- Circumstances beyond control 4–042–4–051
- Civil commotion 4–240–4–252
- Claim preparation 24–019–24–022
- Claims consultants 24–026–24–027
- Classification of change 4–011–4–027
- Collapsed as-built
- Commercial risk allocation
- implied terms, and 2–085
- Compensation see Damages
- Compensation conditional upon notice 6–151–6–165
- Complex projects characteristics 3–004
- Complex projects
- Computer generated evidence 14–183–14–189
- Computer software 10–007
- Computerised database 14–045–14–046
- Computerised simulation
- risk, and 2–061
- Computers
- critical path method, and 8–068
- Conciliation 25–012–25–015 see also Dispute Resolution, Mediation
- Concurrency 19–001–19–139
- application of theory 19–007
- concurrent delays to completion 19–066–19–079
- delay to progress, and 19–015–19–065
- distinguishing concurrent and pacing delays to progress 19–024
- distinguishing concurrent and parallel delays 19–018–19–022
- distinguishing concurrent and sequential delays 19–023
- distinguishing delay and financial loss 19–035–19–038
- distinguishing delay to progress from delay to completion 19–015–19–016
- distinguishing primary, secondary and tertiary causation 19–017
- distinguishing timing of primary cases 19–025–19–028
- entitlement 19–014
- extensions of time, and 19–066–19–101
- inconsistency in treatment of issues 19–012
- legal concepts of relief and compensation 19–029–19–034
- meaning 19–001
- pacing, and 19–024, 19–121–19–139
- parallel causes of delay to completion 19–096–19–101
- parallel delays to progress 19–059–19–065
- parties 19–013
- prolongation, and 19–100–19–120 see also Prolongation
- sequential causes of delay to completion 19–080–19–095
- sequential delays to progress 19–044–19–058
- Consequential changes 13–198–13–199
- Constructing Excellence 1–005
- Construction industry
- decrease in output 18–063
- Construction management contracts 3–039–3–049
- Construction records 14–001–14–273
- Constructive acceleration 12–093–12–136
-
Construction risk 2–129–2–145Page 1281
- Constructive change 13–158–13–199
- alternative materials 13–190
- avoiding disputes 13–180
- consequential changes 13–198–13–199
- essence of claim 13–161
- estoppel, and 13–171–13–172
- implied changes, and 13–164
- quality 13–181–13–191
- quality or quantity 13–048
- quantity 13–192–13–197
- reasonable satisfaction 13–061
- treated as variation 13–176
- variations in writing 13–167
- waiver, and 13–171
- Constructive notice 6–030–6–032
- Consumer Insurance (Disclosure and Representation) Act 2012 2–167–2–168
- Contingency
- Contingency planning 17–005
- Contra proferentem rule
- Contract administrator 1–022
- Contract programme 10–016
- Cookham Wood
- Cost and time management
- Cost management 5–101–5–103
- Cost monitoring 10–110–10–114
- Costs 24–009–24–022
- Count the squares chart monitoring 10–127–10–134
- Counterclaim 25–056–25–060
- CPC 2013 3–009
- CPM programming 8–077–8–078, 8–083
- Critical path 1–027–1–032
- extension of time, and 6–081
- Critical Path Method 8–068–8–0848
- DABs 27–039, 27–042–27–044
- Damage caused by carrying out works 4–254–4–258
- Damages 22–001–22–290
- burden of proof 22–162
- compensation, entitlement to 22–013–22–039
- contractor has actually suffered loss or expense 22–172–22–173
- direct labour costs 22–042–22–052
- direct loss or expense 22–172–22–183
- Eichleay formula 22–184–22–186
- Emden formula 22–188
- exclusion clauses 22–263–22–290
- financing costs 22–119–22–137
- formula adjustments 22–159–22–290
- four-phase analysis 22–008
- goods and materials 22–074–22–078
- Hadley v Baxendale, rule in 22–003, 22–005, 22–007, 22–123
- head office costs 22–111–22–116
- Hudson formula 22–187
- insurances 22–117–22–118
- Lilley Ames Co v United States 22–189
- liquidated see Liquidated damages
- loss of future profits 22–140–22–145
- loss of productivity 22–089–22–097
- loss or expense not recovered elsewhere 22–174
- loss or expense remained unabsorbed 22–175
- management costs 22–068–22–073
- non-productive overtime 22–053–22–057
- plant and equipment 22–079–22–088
- potential heads of claim 22–040–22–158
- preliminaries 22–100–22–110
- profit on costs 22–138–22–139
- propositions 22–004, 22–232
- quantifying predictive loss 22–246–22–290
-
quantum meruit 22–191–22–222 see also Quantum meruitPage 1282
- resort to formula approach 22–176–22–183
- staff costs 22–058–22–067
- temporary works 22–098–22–009
- time-related costs 22–021, 22–027
- unabsorbed overheads 22–146–22–158
- work-related costs 22–027
- Database records 14–172–14–182
- Databases 14–215–14–233
- DBs 27–001–27–092
- ad hoc 27–029–27–038
- advantages 27–017–27–028
- context 27–005–27–016
- costs 27–078–27–084
- enforcement of decisions 27–070–27–075
- independence of members 27–051–27–055
- international developments 27–085–27–092
- national developments 27–085–27–092
- operations 27–056–27–069
- rules 27–045–27–050
- standing 27–029–27–038
- use of 27–007, 27–015
- Decennial liability
- Defence, statement of 25–053
- Defined provisional sums 13–101–13–103
- Delay
- adverse effect 1–032
- advice as to cause of delay 6–010
- analysis, nature of 7–063
- apportionment 21–013–21–031
- build-only contracts 4–090
- catastrophes 4–259–4–262
- causation
- “causes” of delay 19–080–19–101
- comparative term, as 1–031
- completion 1–001
- concurrent
- completion, to 19–080–19–090
- distinguishing concurrent and pacing delays to progress 19–024
- distinguishing concurrent and parallel delays 19–018–19–022
- distinguishing concurrent and sequential delays 119–023
- distinguishing delay and financial loss 19–035–19–038
- distinguishing delay to progress from delay to completion 19–012
- parallel causes of delay to completion 19–096–19–101
- parallel delays to progress 19–059–19–065
- progress, and 19–015–19–016, 19–024, 19–039–19–065
- SCL Protocol 11–014–11–044
- sequential causes of delay to completion 19–080–19–095
- sequential delays to progress 19–044–119–058
- culpable delay 7–100 7–105
- extensions of time
- developer’s time risk event occurring in period of culpable delay to completion date 7–100–7–105
- facts of delay 14–191–14–233
- forecasting delay 11–005–11–013
- managing effects of delay 11–016
- meanings 1–029–1–031
- nominated sub-contractors and suppliers’ delay 4–188–4–202
- receiving instructions, in 4–203–4–230
- retrospective analysis 7–037, 14–194–14–201
- standard clauses of delay 4–028–4–265
- standard form provisions, meaning of delay 2–027
- Design
- meaning 13–070
- Design and build contracts 3–033–3–038
- Design risk 2–099–2–112
- accelerated design programmes 2–106
- approximate bills 2–112
- errors 2–101
-
fitness for purpose 2–100Page 1283
- freezing design at scheme design stage 2–108
- key concepts 2–100
- M&E engineering consultants 2–107
- needs of client 2–103
- post-contract design 2–109–2–111
- reappraisal of design 2–110
- reasonable skill and care 2–100
- relevant factors 2–102
- remedial work 2–104
- Detailed plan 8–024
- Developer’s acts or omissions
- Development control 2–197
- Development programme 8–038–8–042
- Diligently
- Dilution of supervision
- Direct labour costs
- Disclosure 14–234–14–273
- Discovery 14–234–14–273
- Discrepancies 13–110–13–135
- Dispute boards 27–001–27–092 see also DBs
- Dispute resolution 25–001–25–075 see also Conciliation, Mediation
- Dispute risk 2–090–2–098
- Disruption
- Divergences 13–110–13–135
- Document management systems 14–224
- Documentary evidence 14–168–14–171
- DRBs 27–039–27–044
- Duress 24–064–24–073
- Early completion
- Early warnings 6–003–6–007
- Earned value monitoring 10–115–10–117
- Economic duress 24–064–24–073
- EDI agreement 14–055–14–061
- Editing standard forms 2–080
- Egress 4–163–4–169
- Eichleay formula 22–184–22–186
- Electronic data exchange 14–051–14–066
- technologies 14–052
- Electronic documents
- Emden formula 22–188
- Equitable adjustment 1–015
- Errors
- Errors in contract documents 4–081–4–102
- Evidence 14–160–14–233
- computer generated 14–183–14–189
- database records 14–172–14–182
- documentary 14–168–14–171
- facts of delay 14–191–14–233
- manual sorting of 14–202–14–205
- multi-volume collections 14–206–14–207
- oral 14–161–14–167
- presentation 14–160–14–189
- retrospective assembly 14–194–14–201
- single-volume tagged collections 14–208–144–214
- sorting on databases 14–215–14–233
- strength of records 14–190
- Excepted risks 2–155–2–157
- Exceptionally inclement weather 4–123, 4–127–4–128
- Exclusion clauses
- Expert determination 25–016–25–021
- Expert opinion
- Experts 24–028–24–055
- Experts’ documents
- Extended working hours
- Extensions of time 7–001–7–172
- bar chart 7–064–7–067
- calculating entitlement 15–104
- change management, and 11–045–11–070
- coldly logical approach 7–046, 7–057
- concurrency, and see Concurrency
- conditional upon notice 6–110–6–165
- conduct requiring 12–110–12–121
- consequences 7–028–7–029
- constructive change 7–059
- contract administrator, role of 7–014–7–030
- critical delay to the work 7–030
- delay actually occurred 7–036–7–038
- delay to progress 7–031–7–043
- developer’s time risk event occurring in period of culpable delay to completion date 7–100–7–105
- fair and reasonable 7–020–7–030, 7–056
- forming opinion 7–044–7–068
- holiday period 7–003–7–005
- inoperable power 7–134–7–172
- likely and actual delay to completion date 7–031–7–105
- logical analysis 7–056, 7–061, 7–063, 7–066
- measurement of interim extensions of time 11–018
- negotiating award 7–069–7–074
- no power, where 7–130–7–133
- original planned programme, and 7–018
- purpose 7–001
- relevant delay 7–042
- restricted working calendars 7–006
- reviewing award 7–088–7–099
- rules of measurement, and 7–060
- time risk event 7–100–7–105
- timing of award 7–075–7–087
- Facts of delay 14–191–14–233
- Failure to pay 4–037–4–041
- Failure to perform
- Familiarisation
- planning, and 8–021
- Financial risk 2–146–2–151
- Financing costs
- Fire
- Fitness for purpose
- Float
- calculation 17–006–17–040
- data 17–008
- definition 17–055–17–057
- elusive concept 17–006
- free 17–011–17–016
- independent 17–017–17–018
- interfering 17–019–17–020
- meaning 17–001–17–005
- negative 17–040
- standard form provisions 17–055–17–069
- time contingencies 17–041–17–054
- total 17–021–17–039 17–085–17–142 see also Total float
- who owns 17–070–17–142
- Flow chart 9–018–9–019
- Force majeure 4–053–4–080
- Forecasting delay 11–005–11–013
- Forensic
- meaning 16–001
- Forensic programme analysis 16–001–16–174
- analytical methods 16–060–16–162
- as-built programme 16–047–16–059
- as-planned impacted 16–076–16–115
- as-planned updated versus as-planned updated 16–068–16–075
- as-planned versus as-built 16–060–16–067
- collapsed as-built 16–116–16–147
- correcting planned programme 16–019–16–036
- dynamic methods 16–006
- planned programme 16–017–16–059
- preparing materials 16–017–16–059
- static methods 16–005
-
time impact analysis 16–148–16–162Page 1285
- updating planned programme with progress 16–037–16–046
- use of 16–004
- watersheds 16–163–16–174
- windows 16–163–16–174
- Formula adjustments
- Fossils 4–263–4–265
- Free float 17–011–17–016
- Fraud 24–074–24–083
- Gantt chart 9–008–9–009
- Global claim 20–001–20–072
- Goods and materials
- Government acts 4–172, 4–180–4–181
- Graphs 15–187–15–192
- Greenfield sites
- Groundworks
- Guaranteed maximum price 3–059–3–062
- Head office costs
- Health and safety 4–253
- Hierarchy of documents 4–081–4–084
- High-rise building projects
- risk 2–005
- Histograms 15–187–15–192
- Holyrood 2–009
- Hong Kong forms
- project planning and programming 2–053
- Hudson formula 22–187
- Human rights
- Identifying cost of project controls 11–090
- Implied instruction for change 13–003
- Implied terms 2–080–2–088
- Inclement weather 4–123–4–127
- Inconsistencies in contract documents 4–081–4–102
- Independent float 17–017–17–018
- Independent information management 14–120–14–134
- Inference of causation 15–166–15–219
- Inflation 2–151
- Ingress 4–163–4–169
- In-house departments 24–023–24–025
- Injury or damage to property 2–161–2–170
- Inspection 14–234–14–251
- Instructed variation
- causation, and 15–073
- Instructed variations and changes 4–103–4–120
- Insurable risk 2–154–2–166
- Interfering float 17–019–17–020
- Internet
- weather information via 4–130
- Interpretation of contracts
- Itemised bills of quantities
- biddability risk, and 2–126
- Investment decision 2–146
- Jagged line monitoring 10–135–10–139
- JCT forms
-
JCT Major Projects ContractPage 1286
- Key dates 11–059–11–060
- Latent conditions 4–153
- Learning curve
- Legal risk 2–064–2–089
- Line-of-balance chart 9–020–9–025
- Liquidated damages 22–223–22–245
- Litigation 25–035–25–038
- Local authorities
- Logical relationships 8–115–8–124
- Logistics
- Loss of future profits
- Loss of morale
- lost productivity, and 18–062
- Loss of productivity
- Loss or expense, recovery of 5–068–5–073
- CIOB Complex Projects Contract 5–059–5–100
- claims procedure 5–034–5–055
- compensable events 5–014–5–033
- compensable risks 5–029–5–030
- compensation for disruption to progress 5–056 5–058
- conditions contrary to public interest 5–033
- developer’s cost risk events 4–025
- direct loss and/or expense 5–001, 5–035
- JCT Major Projects Contract 5–059–5–100
- priced activity programme 5–013
- standard forms provisions 5–049–5–058
- valuation 5–048–5–049, 5–063–5–065
- variations 5–021
- Lost productivity
- acceleration 18–043–18–049
- accounting for effects of separate events 18–134–18–143
- adverse weather 18–056–18–061
- analysis 18–085–18–143
- burden of proof 21–042
- causation 19–017
- conditions causing 18–029–18–084
- difficulty of measurement 18–016
- dilution of supervision 18–072–18–074
- errors 18–050–18–052
- expert opinion 18–156–18–158
- extended working hours 18–063–18–066
- industry productivity norms versus actual 18–105–18–114
- learning curve 18–075–18–077
- logistics 18–078–18–079
- loss and expense suffered 18–004–18–008
- loss of morale 18–062
- matters to be proved 18–044
- measured mile 18–130–18–133, 18–144–18–155
- omissions 18–050–18–052
- partial possession 18–053–18–055
- reassignment of manpower 18–067–18–071
- records, and 18–023–18–028
- recovery 18–043–18–049
- ripple 18–080–18–082
- resource-based planning 18–017–18–022
- site restrictions 18–078–18–079
- staffing 18–032–18–034
- trade stacking 18–083–18–084
- variations 18–035–18–042
- M & E engineering consultants
- design risks, and 2–107
- Management contracting
- Management contracting contracts 3–050–3–058
- Management costs
- Managing effect of change 11–071–11–089
see also Change Management disruption
- first step-programme update 11–080
- frozen design 11–076
- negotiation of variations 11–077
- potential fifth step-acceleration 11–085–11–088
- potential fourth step-event impacting 11–084
- second step-programme review for better information 11–081
- significance 11–073
- third step-recovery 11–082–11–083
- variation 11–072
- Mandatory laws in international construction contracts 28–001–28–028
- Manifest error
- biddability risk, and 2–125
- Master programme 8–028
- Measured mile 18–130–18–133, 18–144–18–155
- Mediation 25–007–25–011 see also Dispute Resolution, Conciliation
- Milestone monitoring 10–118–10–121
- Milestone programme 9–028–9–031
- Milestones 8–098–8–109
- Mismanagement of time
- Misrepresentation 24–074–24–083
- Mitigation 12–001–12–020
- Modelling 14–067–14–070
- Monitoring
- Natural justice
- dispute risks, and 2–098
- Negative float 17–040
- Negligence
- Network diagrams 9–032–9–034
- Nominated sub-contractors and suppliers 4–188–4–202
- Non-productive overtime
- Notice as condition precedent 6–110–6–165
- Notices 6–008–6–109
- Occupational programme 8–055–8–057
- Omissions 13–136–13–153
- Oral evidence 14–161–14–167
- Outline plan 8–022
- Pacing 19–121–19–139
- Partial possession
- Partnering 3–063–3–066
- Penalties 22–231–22–240
- PIX Protocol 141–061–14–066
- Planning
- Plant and equipment
- Political risk 2–152–2–153
- Poor project programming 1–008
- Poor record keeping 1–008
- Postponement 4–170–4–171
- Precedence diagram 9–041–9–044
- Preliminaries
- Presentation of programmes 9–001–9–090
- compliance with programming specifications 9–006
- Prevention principle
- Private finance initiative 3–067–3–075
- Private international law 28–006–28–008
- Private nuisance 2–187–2–188
- Privileged communications
- Probability estimates
- risk, and 2–059
- Procurement arrangements 3–059–3–075
- Productivity see also Lost productivity
- Profit on costs
- Programme 1–024–1–026
- activity coding 8–230
- approval 9–001–9–090
- contract document, as 8–220–8–226
- core principles 1–025
- method of compilation 8–227
- presentation 9–001–9–090
- pricing requirements 8–241–8–245
- specifying requirements 8–227–8–240
- standard form requirements 8–177–8–245 see also Standard form requirements for programmes
- subject-matter 8–172
- varieties 8–026–8–067
- Programme logic 7–078
- Programme preparation 8–068–8–162
- Programme revision 10–061–10–068
- Programme updating 10–069–10–088
- Programming see also “Critical path method” approval and presentation
- activity-based CPM programme 9–002
- complex projects 9–002
- computer programmes 9–001
- contract requirements 9–005
- contract specification 9–003–9–004
- CPM-based algorithms 9–002
- development process 8–025
- electronic information 9–004
- engineering contracts 9–004
- generally 9–001
- line of balance charts 9–020–9–025
- management information 9–004
- methods 9–002
- milestone charts 9–028–9–031
- nature of 8–001
- network diagrams 9–032–9–034
- network planning techniques 9–035
- precedence diagrams 9–041–9–044
- resource loading 9–002
- software 9–002
- specifications 9–006
- standard form contracts 9–004
- time change diagrams 9–026–9–027
- contract administrators 8–006–8–007
- delay analysis 8–002
- development process 8–025
- excusable delay 8–008
- late 9–005
- planning
- programming 8–025
- progress monitoring 10–089–10–169
- reporting 10–005
- updating 10–069
- Progress monitoring 10–089–10–169
- Progress records 14–015–15–025
- Progress reporting 10–146–10–156
- Project control 11–001–11–094
- Project planning and programming
- Project planning model statements 8–163–8–176
- Project procurement 3–001–3–075
- Project time manager 3–010
- Projects
- meaning 3–004
- Prolongation 19–102–19–120
- Proportionality
- PSSC 3–016
- Public private partnership 3–067–3–075
- Quality control 4–231–4–239
- Quantifying predictive loss 22–246–22–290
- likely outgoings 22–261
- Quantum meruit 22–191–22–222
- Rate of progress
- meaning 12–080
- Reasonable skill and care
- risk, and 2–049
- Reassignment of manpower
- Record keeping 14–003–14–014
- Record retrieval 14–042–14–050
- Records
- Recovery
-
RegularlyPage 1290
- Re-measurement
- build-only contract 3–031
- Re-measurement contracts
- risk 2–036
- Reporting
- Request for further information 25–067–25–070
- Retrospective delay analysis 8–077
- Residential occupiers
- Resource-based planning
- Resource monitoring 10–097–10–104
- Revision
- RIBA Plan of Work 3–017
- Ripple
- Risk 2–001–2–197
- acts of prevention 2–046
- advice on 2–014
- allocation 2–038–2–168
- bespoke form, and 2–044
- biddability see Biddability risk
- buildablity see Buildability risk
- categorisation 2–017
- commercial negotiation 2–041
- complex projects 2–004
- computerised simulation 2–061
- conflicting interests of parties 2–040
- construction see Construction risk
- design see Design risk
- design and build contracts 3–034–3–035
- dispute see Dispute risk
- distribution 2–042
- financial see Financial risk
- fitness for purpose, and 2–047–2–050
- high-rise building projects 2–005
- identifying 2–016
- ill-considered transference 2–025
- influence of variables 2–012
- insurable 2–154–2–166
- JCT forms 2–019–2–020
- judicial interpretations of common law and statute 2–047
- legal see Legal risk
- management 2–015–2–016
- management contracting 2–037
- managing risk of change 2–031
- obligations of professional and tradesman 2–048
- political see Political risk
- probability estimates 2–059
- project planning and programming 2–051–2–063
- reasonable skill and care 2–049
- registers 2–033
- re-measurement contracts 2–036
- sources 2–010–2–011
- standard form provisions 2–018–2–037
- statistics 2–001
- theories of apportionment 2–043
- Risk allocation
- tort, and 2–172
-
SCL Protocol
1–003–1–004, 11–014–11–044
- calculating entitlement to extension of time 11–036
- complex programming and record-keeping equipment 11–042
- concurrent causes of delay 11–040
- contemporaneous project control 11–019
- critical path network 11–023
- float 11–037
- identification of activities 11–024
- information 11–025
- managing effects of delay 11–016
- measurement of interim extensions of time 11–018
- nature of 11–015
- objection to electronic access to programme 11–031
- programme and records 11–020
- public health guide, as 11–043
- record-keeping 11–026–111–027
- retrospective analysis 11–017
- update of contractor’s programme 11–028–11–030
- Scott programmes 15–180–15–186
- Second notice 6–081–6–089
- Sectional completion 8–098–8–109
- Sequencing problems 2–115
- Service of notice 6–097–6–109
-
Settlement 24–001–24–083Page 1291
- Simple projects
- characteristics 3–004
- Site restrictions
- Smoke and mirrors 15–220–15–231
- Soft-spots 4–144
- Special circumstances 4–052
- Specified perils 2–154–2–155
- Staff costs
- Staffing
- Standard clauses of delay 4–028–4–265
- Standard form provisions
- Standard form provisions for time and cost 4–001–4–366
- Standard form requirements for programmes 4–001–4–265
- Standard forms
- Statements of case 25–039–25–045
- Statement of claim 15–182, 20–061, 25–039–25–044, 25–046, 25–053
- Statutory compensation schemes 2–185
- Statutory duties 2–169–2–197
- Statutory undertaker 4–173
- Strategic plan 8–023
- Strikes 4–240–4–252
- Structured reading
- meaning 14–226
- Sub-contractors
- Sub-contractor’s programmes 8–059–8–067
- Suspension of works
- Target costs 3–059–3–062
- Target CPM programme monitoring 10–091–10–096
- Target programme 8–028–8–037
- Temporary works
- Tender programme 8–028, 8–043–8–046
- Terminology 1–018–1–032
- Terms of contract
- Terrorism 4–247, 4–250
- The contractor 1–020
- The developer 1–021
- The works 1–023
- Time and cost
- Time at large 7–106–7–129
- Time-bar clauses
- Time chainage diagram 9–026–9–027
- Time contingencies 17–042–17–045
- Time impact analysis 17–147
- Time management
- Tort 2–169–2–197
- Total float 17–022–17–042
- Total loss claim 20–001–20–072
- Total time claim 20–001–20–072
- Trade stacking
- Trade usage
- implied terms, and 2–087
- Unabsorbed overheads
- Undefined provisional sums 13–101
- Unforeseeable physical conditions 4–143–4–162
- Unjust enrichment 21–193
- Updating
- US government procurement contracts 1–014
- Utilities
- Value engineering 13–154–13–157
- Variation 13–001–13–199
see also Change
- ambiguities 13–110–13–135
- definition 13–032–13–036, 13–038, 13–043, 13–048–13–049, 13–056, 13–059
- discrepancies 13–110–13–135
- divergences 13–110–13–135
- drawings 13–019
- extra work 13–026
- instruction, definition 13–055
- legitimate power to instruct 13–015
- lost productivity, and 18–035–18–042
- necessary work 13–023–13–024
- omissions 13–136–13–153
- post-contract design 13–021
- price 13–017
- right of reasonable objection 13–050
- standard form provisions 13–030–13–157
- VATFP 18–011–18–012
- Visual aids 10–157–10–169
- activity lists 10–163
- assessment tables 10–164
- bar charts 10–165
- cascade diagrams 10–163
- computer printouts 10–163
- computer-generated visualisations 14–186
- descriptive visualisations 10–158, 14–186, 15–217
- electronic spreadsheets 10–169
- evidential visualisations 10–161, 14–189
- graphs 10–166–10–168
- histograms 10–165
- illustrative visualisations 10–160, 14–188, 15–219
- introductory visualisations 10–159, 14–187, 15–218
- probative value 10–073
- progress reports 10–162
- Visualisations
- Voluntary change 13–002
- War 4–248–4–251
- Watersheds
- Weather 4–121–4–142
- Windows
- Work content 8–110–8–114
- Work content monitoring 10–140–10–145
- Working programme 8–047–8–054