International Construction Law Review
UNEARTHING A MINEFIELD OF UNCERTAINTY: THE IMPACT OF SITE INFORMATION DISCLAIMERS ON LATENT CONDITIONS RISK ALLOCATION
Dr Jeremy Coggins
Associate Professor, University of South Australia
I. INTRODUCTION
While carrying out construction works, a contractor may encounter unexpected adverse physical conditions at site which cause it to incur additional costs in carrying out the works and/or experience delay to the completion of the works. Such adverse conditions are, by nature, latent and most commonly encountered subsurface during excavation works with typical examples including contaminated soil, groundwater, hard rock and disused utilities.1 Such subsurface and latent conditions risks have been identified as amongst the most frequently occurring and troublesome risks on construction projects.2 Absent any express provisions to the contrary in the construction contract, the traditional common law position is that the contractor bears all the risk with respect to site conditions encountered on the basis that sanctity of contract requires parties to do what they have agreed to do, even if performance turns out to be much more difficult and expensive than originally supposed.3 In other words, the employer does not warrant that the site conditions will be suitable for building the contract works,4 but rather the contractor warrants it can build the contract works at the site. Placing all latent site conditions risk on the contractor, however, leaves tenderers with the commercially formidable task of trying to determine a suitable cost contingency to include in their tender prices
1 Although, latent conditions may also sometimes occur above ground level (e.g., concealed asbestos insulation within an existing building) or adjacent to a site (e.g., unstable ground conditions at the site boundary).
2 Sharkey AM, J, Greenham, P, Bell, M, Jocic, W, Korolkova, J and Hu, D, “The Health of the Australian Construction Industry, Research Report”, The University of Melbourne, Society of Construction Law Australia, Australian Construction Industry Forum, September 2020, 24–26.
3 Dermott v Jones 69 US 1 (1864), Thorn v London Corporation (1876) 1 App Cas 120 and Re Carr and the Shire of Wodonga [1925] VLR 238.
4 In the US, however, pursuant to the Spearin doctrine, there may be situations where the court implies a warranty into the contract that prescriptive plans and specifications provided by the employer are accurate and workable with respect to their buildability at site – see US v Spearin 248 US 132 (1918). Although, the Spearin doctrine is only likely to apply in relation to warranting suitable site conditions where the contract specifications prescribe a method of construction performance. Additionally, for the Spearin doctrine to apply, there must be no express term in the contract that excludes or waives the doctrine, and the contractor must reasonably rely on the defective contract specifications.
Pt 2] Unearthing a Minefield of Uncertainty
107