International Construction Law Review
SHUT YOUR EYES, GROPE IN THE DARK AND … NEVER LOOK BACK? ARE EXTENSION OF TIME PROVISIONS UNWORKABLE AND PRONE TO DISPUTES?
ANGEL GARCIA DOMINGUEZ
CENG MICE FCIARB*
Forensic delay expert
ABSTRACT
This article examines the efficacy of extension of time provisions in construction standard forms of contract such as JCT, NEC and FIDIC. It seeks to determine whether these provisions work effectively in practice or, to the contrary, if they should be revised to enhance their application. It relies on English case law, expanding into other jurisdictions for comparison. The aim is to improve the prospects of early resolution of claims and thereby reduce the escalation of disputes. It analyses the operation of these provisions and reviews the most common contentious issues encountered by the parties at project level. It concludes that there is room for reform to provide flexibility to manage time claims more effectively, ultimately leading to a desirable result without the need for formal dispute resolution.
INTRODUCTION
Time for completion is defined in most standard forms of contract.
A construction project is commonly subject to many changes, some of which will entitle the contractor to additional time to complete the works.1 An extension of time clause is an express contractual provision that enables the time for completion to be adjusted. It serves two purposes. The
* The author gratefully acknowledges comments provided on earlier drafts by Julian Bailey, Partner at Jones Day and Visiting Professor at The Dickson Poon School of Law, King’s College London.
Angel Garcia Dominguez is a Chartered Civil Engineer, Member of the Institution of Civil Engineers (CEng MICE) and Fellow of the Chartered Institute of Arbitrators (FCIArb). He has more than 15 years of construction experience working in both a contracting and consulting environment. He now acts as a Forensic Delay Expert. Angel holds a MEng in Civil and Structural Engineering from the University of Granada and specialised with an MSc in Design and Construction of Railway Infrastructures from the Universidad Politecnica of Catalunya with Distinction. He also holds an MSc in Construction Law and Dispute Resolution from King’s College London with Distinction and was awarded three prizes for his performance, two SCL prizes for best overall graduate, and best dissertation and the Worshipful Company of Arbitrators Charitable Trust for the best-assessed coursework performance in the second year.
1 Depending on the contractual rights and obligations set out in the particular form of contract.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
363
contractor is relieved of the consequences of breaching the contract and it is not obliged to pay liquidated damages.2 Additionally, the employer preserves its right to claim liquidated damages if the revised completion date is subsequently not achieved by the contractor due to delay for which the latter is deemed responsible.3
There is no general rule of law as to the circumstances under which a contractor is entitled to an extension of time: it is a question of construction of the time provisions in the contract.4 It is therefore essential for employers to draft clear and certain provisions defining the events following which a contractor may be entitled to additional time to complete the works, in order to protect “their right both to a fixed […] completion date and to deduct liquidates damages”.5 In the absence of clarity, the courts may have to imply a term to provide “business efficacy” to the contract.6 That said, even when such provisions are sufficiently clear and enable the parties to deal effectively with the matter, most disputes about time arise after the works have been completed, as a “wait and see” approach continues to be the norm when assessing extensions of time. A decision maker may have to reach a conclusion based on what actually happened and not solely on what was sufficiently understood at the time. The courts will base their conclusions on legal principles and common sense. However, some of those principles may not be in harmony with the parties’ risk apportionment under the contract. The numerous High Court-level cases seem to point in varying directions. In some, particular approaches have been undermined by judicial decisions, leading to uncertainty concerning how time entitlement should be assessed by the parties.7 This has caused speculative parties to take a commercial advantage to operate extension
of time provisions in a way that militates against the principle of reaching a “fair and reasonable” result, creating a disconnect, which is not a satisfactory result.
2 Mailbox (Birmingham) Ltd v Galliford Try Construction Ltd [2017] EWHC 1405 (TCC); [2017]
BLR 443; 172 Con LR 198 at paragraph 60.
3 Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd
(1970) 1 BLR 111 at paragraph 121.
4 Arnold v Britton [2015] UKSC 36; [2015] AC 1619 [2015] 2 WLR 1593; [2016] 1 All ER 1.
5 North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744; [2018] BLR 565; 180 Con
LR 1 at paragraph 12 (Coulson LJ).
6 Attorney General of Belize v Belize Telecom Ltd [2009] UKPC 10; [2009] 1 WLR 1988; [2009] 2 All ER 1127 at paragraph 23.
7 Northern Ireland Housing Executive v Healthy Building (Ireland) Ltd [2017] NIQB 43.
364
The International Construction Law Review [2024
NOTICE CLAIMING AN EXTENSION OF TIME
Notice Provisions in Standard Forms
In most standard forms of contract, a contractor’s entitlement to an extension of time is conditional on notifying the employer within a set period of an event likely to cause delay to the works.8 Failure to do so may cause the loss of any entitlement to claim additional time and may provide the employer with a complete defence, depending on the wording of the clause.9 There are no general legal rules on this issue. It is a matter of contract interpretation. In Bremer Handelgesellschaft mbH v Vanden Avenne Izegem PVBA
10 it was held that a notice provision should be construed as
a condition precedent if it states the precise time within which the notice
is to be served and makes plain that the claimant will lose this right if it
fails to do so.11
NEC imposes a positive obligation on the contractor to notify the project manager of an event that has happened or is expected to happen, and if it does not:
“… within eight weeks of becoming aware […] the Completion Date or a Key Date are not changed unless the event arises from the Project Manager […] giving an instruction.”12
Similarly, the FIDIC form states that:
“… the [contractor] shall give a Notice to the Engineer […] and no later than 28 days after the [contractor] became aware, or should have become aware, of the event or circumstance [if it fails to do so] the Time for Completion shall not be extended, and [the employer] shall be discharged from all liability in connection with the claim.”13
It is evident that both NEC and FIDIC fulfil both conditions stated in Bremer and the relevant provisions should clearly be considered a condition precedent. By contrast, under JCT, there is no stipulated strict time limit in which the contractor must serve its notice to the employer nor is it stated to be a loss of right in the event of a failure to comply with such provision.
“… if it becomes reasonably apparent that the progress of the Works or any Section is being or is likely to be delayed the contractor shall forthwith give notice to the Architect/Contract Administrator […] including the causes of the delay.”14 (Emphasis added.)
Previous JCT forms required the notice to be served within a reasonable time. The meaning of this phrase was considered in London Borough of Merton
8 Bailey, J, Construction Law, 3rd Edition, (London, 2020), Vol II, Ch 11, paragraph 11.81.
9 The Contract Administrator may have a discretion to award the contractor an extension of time in circumstances where no notice has been given.
11 Ibid, paragraph 98 (Lord Salmon).
12 NEC4 2017 clause 61.3.
13 FIDIC 2017 sub-clause 20.2.1.
14 JCT SBC/Q 2016 clause 2.27.1.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
365
v Stanley Hugh Leach Ltd,15 where it was held that “it must not be made so late that the architect can no longer form a competent opinion […] that the contractor has suffered the loss or expense claimed”.16 This implies that the fact that no precise timing is stated does not by default mean that the contractor is under no obligation to serve notice. This conclusion was supported in Steria Ltd v Sigma Wireless Communications Ltd,17 where Davies J held that a wording to the effect of giving notice within a reasonable period gave rise to a condition precedent even though no express words to that effect were included. The basis for determining what a reasonable period is depends on the facts of the case.18 Consequently, JCT seems to be more open to interpretation and the specific facts of the case, although the additional reference to “receiving a notice” before fixing the completion date clarifies that it is also a precondition to entitlement.19 However, complications may arise where the contractor is late in notifying, or where the notice is deemed invalid under the requirements stated in the contract.
Failure to Comply
Standard forms of contract contain provisions that stipulate specific events for which the contractor may be entitled to claim time compensation.20 These are typically known as “excusable delays” and are divided into neutral events and employer delay events. The former are matters that neither the employer nor the contractor can be held responsible for. These are normally related to exceptionally adverse weather, ground conditions or force majeure events. The latter are matters for which the employer has responsibility and which arise by either an act of prevention or breach of contract by the employer or contract administrator or by an instruction to perform additional or varied work.
In the latter case, there are two possible outcomes. First, the employer has no right to claim damages for the consequences of an obligation it has breached irrespective of a notice requirement being fulfilled.21 Winser argues that it is unconscionable for the employer to levy liquidated damages for the consequent delay, unless the employer unknowingly caused the delay.22 Alternatively, the risk remains with the contractor until it exercises its contractual right, so it is not automatically entitled to additional time. Morris concludes that the delay is in fact caused by the contractor’s failure
15 (Ch D) (1986) 32 BLR 51.
16 Ibid, paragraph 67.
17 [2007] EWHC 3454 (TCC); [2008] BLR 79; 118 Con LR 177.
18 Above, paragraph 91.
19 JCT SBC/Q 2016 clause 2.28.1.
20 JCT SBC/Q 2016 Relevant Events, clause 2.29, NEC4 2017 Compensation Events, clause 60, FIDIC 2017 sub-clause 8.5.
21 Gaymark Investments Pty Ltd v Walter Construction Group Ltd [1999] NTSC 143.
22 Winser, C, “Shutting Pandora’s Box: The Prevention Principle after Multiplex v Honeywell”, (2007) 23 CLJ 511.
366
The International Construction Law Review [2024
to trigger its entitlement to additional time.23 In Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)
24 Jackson J held that the main concern is that otherwise a contractor could benefit by simply disregarding the notice machinery, thereby setting time at large “with impunity”.25 This is the current position in English law.
This has attracted criticism. Jones argues that it results in the employer’s risk being implicitly transferred to the contractor by non-compliance with an administrative requirement.26 Coggins points out that if an employer does not provide access for the contractor, the fact that the latter has not issued a notice does not change the effect of the delay caused by the employer.27 Stephenson highlights that it does not transmute into something different, nor does it break the chain of causation.28 At best, the contractor’s delay as a result of its failure could be considered to have not stopped the delay but cannot be deemed the precursor of the delay.29 The courts have also expressed their reservations to a strict interpretation of a condition precedent. In Obrascon Huarte Lain SA v Her Majesty’s Attorney General for Gibraltar
30 Akenhead J stated that he could see no reason why a condition precedent clause was to be construed strictly against the contractor “given its serious effect on what could otherwise be good claims for instance for breach of contract by the Employer”.31 A contractor may be unable to claim an extension due to an event over which it has no control and which may even be the result of an employer’s instruction for additional work.32 The condition precedent clause was upheld but the court softened its application by allowing the contractor to raise a notice when the delay “started to be incurred”.33 Recently, however, in Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC
34 the Court of Appeal of Dubai challenged the findings in Obrascon, concluding that the contractor cannot choose the point at which the notification of the claim can be made: it must be issued within the period of becoming aware of the potential delay.35 The reasoning for this
23 Morris, D, “When is a Condition Precedent Not a Condition Precedent”, (1992) 1(2)
SISV Journal 43.
24 (QBD (TCC)) [2007] EWHC 447 (TCC); [2007] BLR 195; 111 Con LR 78.
25 Above, paragraph 103.
26 Jones, D, “Prevention, Time-bars and Multiplex (UK) Ltd v Honeywell Control Systems Ltd (No 2)”, chp 19,
Construction Law, Costs and Contemporary Developments, A Festschrift for Lord Justice Jackson, Bailey J (ed), (2018) pp 335–355.
27 Coggins, J, “The Application of the Prevention Principle in Australia – Part 2”, (2009) 21(5) Aust Cons Law Bulletin 45.
28 Stephenson, A, “Concurrency, Causation, Common-sense and Compensation (Part 1)”, [2010] ICLR 166, 183.
29 Above fn 26 p 346.
30 (QBD (TCC)) [2014] EWHC 1028 (TCC); [2014] BLR 484.
31 Ibid, paragraph 312.
32 NEC4 2017 clause 61.3 expressly excludes project manager’s instructions from the operation of the condition precedent.
33 Obrascon at paragraph 312.
34 [2022] DIFC CA016; [2023] BLR 552.
35 FIDIC 2017 sub-clause 20.2.1.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
367
decision is that “delay to the contractual Time for Completion only occurs when the works are not completed by the contractual completion date” which would render the purpose of notification entirely ineffective.36 However, actual delay can occur on day one of a project. If the employer does not provide access, the contractor remains obliged to complete the works before the completion date, and therefore it is equally entitled to the whole period to complete the works.37 The fact that after a delay, the works could be completed on time does not change the fact that these were critically delayed at the outset of the project. Non-compliance with a procedural obligation places the contractor in a vulnerable position. Why is it so crucial for the employer to be notified of a delay when it is itself the party causing it?
Relevance of a Notice
The purpose of a notice has been rationalised by accepting that the contractor is better positioned to determine the likely consequences that an employer’s variation may have on the works, and whether any additional time would be required.38 In Multiplex, Jackson J observed that once the employer is fully aware of the likely consequences of such variation, it can decide to either withdraw the instruction or proceed with the change and award the contractor an appropriate extension of time.39 Recently, in Energy Works (Hull) Ltd v MW High Tech Projects UK Ltd
40 Pepperall J confirmed that this principle remains valid, restating that the purpose of time bar provisions is to enable one party (the contractor in that case) to request the other to desist from carrying out the work.41 From the employer’s perspective, the notice requirement acts as a backstop against introducing additional scope for which no funding can be obtained, thereby minimising the risk of not completing the project.42 If an employer breaches the contract and the contractor suffers a delay, can the employer benefit from its own breach even when it is clearly aware of the circumstances?
Employers, particularly in major construction contracts, are not parties who possess little knowledge of what the construction process entails. Rather, they are sophisticated organisations demonstrating sufficient expertise and competence to have a thorough understanding of the processes involved in construction and are even supported by highly qualified consultancy firms acting in the role of contract administrators.43 Furthermore, delay risk events are commonly managed by early warnings and a continued review process
36 Above fn 34 at paragraph 45.
37 Glenlion Construction Ltd v The Guinness Trust (QBD) (1988) 39 BLR 89.
38 Wallace, I, “Prevention and Liquidated Damages: A Theory Too Far”, (2002) 18 BCLJ 82, paragraph 3.
39 Above fn 24 at paragraph 103.
40 [2023] EWHC 1142 (TCC); 208 Con LR 202.
41 Ibid, paragraph 78.
42 Mewing, A, “The Old Rule, the True Rule and Contract Administration Notices in Construction”, (2014) 30 BCL 88.
43 Pickavance, K, Delay and Disruption in Construction Contracts, 3rd Edition, (London, 2005), p 143.
368
The International Construction Law Review [2024
involving both the contractor and the employer.44 Collaborative features such as early contractor involvement and partnering also play a significant role in managing these risks.45 Major changes are scrutinised before they are formally instructed. These risk management procedures have even become a binding common feature of some standard forms of contracts,46 with the sanction for non-compliance being the reduction of any potential extension of time by assessing the entitlement as if the early warning had been given.47 Despite that, a separate formal notice to claim entitlement is still required within a strict period.48 In Glen Water Ltd v Northern Ireland Water Ltd,49 Keegan J acknowledged that “the failure to notify prevents a claim being made […] may seem harsh when commercial parties anticipated that a claim might come to pass”.50 Although the parties had had multiple discussions regarding the potential claim event which were recorded in numerous meeting minutes over a substantial period of time, those did not constitute a proper notification of the claim and the contractor’s claim was time-barred. The formal notice should have been raised as a separate notification. The court prioritised commercial certainty as “an overarching consideration”51 since the introduction of a condition precedent represents the intention of the parties to freely
agree to their contractual terms and should be given full effect.52
It appears difficult to reconcile a scenario in which, having been early involved in risk meetings, an employer could claim to be unaware of any potential ramifications of its actions simply because it has not been formally notified by the contractor. Actual knowledge should defeat the position argued in Multiplex.53 Normal site communications should be sufficient for that purpose.54 In such a scenario, it is at best arguable that the purpose of a formal notice seems more related to an opportunistic strategy to defend any potential claims than to the necessity of dialogue to determine the extent of the delay. A contractor’s failure to formally notify ought to not render the employer’s breach irrelevant.
The English courts have concluded that if time bars do not displace the prevention principle then their purpose becomes irrelevant, which would militate against the agreement of the parties.55 However, construction
44 Smith, N et al, Managing Risk in Construction Projects, 3rd Edition, (London, 2014), p 139.
45 Mosey, D, Collaborative Construction Procurement and Improved Value, 1st Edition, (London, 2019), paragraph 18.2.
46 Early warning NEC4 2017 clause 15, Advance warning, FIDIC 2017 sub-clause 8.4.
47 NEC4 2017 clause 63.7, NEC Guidance Notes, clause 15.3.
48 Separate claim notices to other communications under JCT 2.27, NEC4 2017 clause 61.3 or FIDIC 2017 sub-clause 20.1. Eight weeks under NEC4 2017 clause 61.3, 28 days under FIDIC 2017 clause 20.1.
49 [2017] NIQB 20.
50 Ibid, paragraph 64.
51 Ibid.
52 Lal, H, “The Rise of ‘Time-Bar’ Clauses: The ‘Real Issue’ for Construction Arbitrators”, [2007] ICLR 118, 131.
53 Rae, S, “Prevention and Damages: Who takes the risk for employer delays”, (2006) 22 CLJ 307, 322.
54 Bailey, I, “Concurrency, Causation, Common-sense and Compensation (Part 2)”, [2010] ICLR 197, 205.
55 Above fn 24 at paragraph 130.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
369
contracts have careful risk allocation, and acts of prevention are at the employer’s risk.56 Shifting the blame to the contractor defies that risk allocation57 and would mean that the contractor has unknowingly accepted that risk58 which “would require very clear language”.59 Time-bar provisions play a crucial role in construction but they are not of such cruciality that a failure to comply overrides the risk allocation agreed by the parties.60 Risk allocation should take precedence if a conflict arises, so the outcome of displacing the prevention principle must be regarded as unintentional.61
Waiver or Discretion
Extensions of time as a result of an employer’s delay should be assessed irrespective of whether notice has been given. The employer (or its representative) should have the discretion to override any condition precedent and award an extension to the contractor based on the merits of the claim.62 This mechanism would primarily protect the employer against the effect of prevention and would also eliminate the risk of a contractor failing to activate any entitlement under the contract.63 A discretion to waive the requirement of a notice for a claim for an extension of time is a common feature under some standard forms of contract.
Under JCT, the Contract Administrator shall no later than 12 weeks after the date of practical completion give details fixing the completion date for the works or, in other words, decide whether any extension of time claimed by the contractor is warranted.64 This provision is not subject to a notice so it acts as a power to dispense with any procedural requirements to grant an extension of time.65 Similarly, FIDIC has recently introduced a provision whereby a time-bar clause can be waived by a Dispute Adjudication Board (DAB) which can award the contractor additional time, irrespective of whether a notice was validly issued, providing late submission is justified.66 One of the mitigating factors stated in this provision is whether the employer had prior knowledge of the event in question.67
In other jurisdictions, standard forms have also introduced a discretion to temper the effect of non-compliance with a notice requirement in the case
56 Stulic, M, “Prevention and the Allocation of Risk of Project Delays: Evolution or Revolution?’”, SCL 18 May 2010, 1–2.
57 Above fn 53, p 322.
58 Jones, D, “Can Prevention be Cured by Time Bars?”, [2009] ICLR 57, 68.
59 Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (CA) (1970) 1 BLR 111 at
paragraph 121.
60 Above fn 26, p 348.
61 Above fn 54, p 206.
62 Hrustanpasic, D, “Time-bars and the Prevention Principle: Using Fair Extensions of Time and Common-sense Causation”, (2012) CLJ 28(5), 379.
63 Above fn 56, p 3.
64 JCT SBC/Q 2016 clause 2.28.5.
65 City Inn Ltd v Shepherd Construction Ltd (CSOH) [2007] CSOH 190; [2008] BLR 269 at paragraph 148.
66 FIDIC 2017 2nd Edition, sub-clause 20.3 “Waiver of Time-limits”.
67 Above and further explained at FIDIC 2017 Contracts Guide, 2nd Edition, (2022), p 506.
370
The International Construction Law Review [2024
of a claim for an extension of time. Swedish ABT06 General Conditions of Contract waive the obligation to serve a notice in circumstances where the employer was aware or ought to have been aware of the effect.68 Australian AS 4000-1997 confers a “reserve power” to grant an extension of time to the contractor irrespective of whether it has complied with the notice provisions in the contract.69 In Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd
70 Hodgson JA held that this power should be conditional on a duty to act fairly and impartially in the exercise of that discretion resulting in the contractor being granted an extension of time in circumstances where relevant events, for which the employer would be at fault, caused the works to be critically delayed.71 In Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd
72 McColl JA affirmed the reasoning in Peninsula and applied this principle to extend time notwithstanding that a notice provision had not been followed.73 Such power should be disconnected from any failure to notify under the contract to avoid the prevention principle argument, but it should not be viewed as an “absolute” power which excludes an obligation to act reasonably.74 Recently, in Growthbuilt Pty Ltd v Modern Touch Marble & Granite Pty Ltd
75 Henry J held that if a clause confers an absolute power there is no obligation on the superintendent to extend or make any decision whether or not to extend. The issue of prevention principle would not arise in that case.76
The courts have also shown a degree of leniency and applied alternatives to a strict rejection of an extension of time claim. These range from the contractor bearing any costs resulting from that delay to applying a reduction arguing that had the employer been notified, it would have been able to mitigate the delay. In Hervey Bay (JV) Pty Ltd v Civil Mining and Constructions Pty Ltd
77 an employer had granted an extension of time but rejected a claim for delay costs as a result of an expired claim. Similarly, a contract may expressly specify that non-compliance with a notice provision will prevent the contractor from claiming “consequential delay costs”.78 Some forms of contract have tested this approach and may reduce entitlement to account for the effect of a non-timely notification.79
That said, as Jones clarifies, a condition precedent should be enforced for a failure to notify a “neutral” delay such as that due to a force majeure or bad weather and no discretional extension of time should be granted, as
68 Swedish ABT06 General Conditions of Contract, clause 4.4 “notification of hindrance”.
69 Australian AS 4000-1997, clause 34.5.
70 [2002] NSWCA 211.
71 Above, paragraph 79.
72 [2017] NSWCA 151.
73 Ibid, paragraph 128.
74 Macquarie International Health Clinic Pty Ltd v Sydney Local Health District [2020] NSWCA 161 at paragraphs 268–269.
75 [2021] NSWSC 290.
76 Ibid, paragraphs 71 and 80.
77 (2010) 26 BCL 130.
78 Shoalhaven City Council v Firedam Civil Engineering Pty Ltd (2011) 244 CLR 305 at paragraph 323.
79 FIDIC 2021 Green Book sub-clause 13.2.2.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
371
entitlement in those cases should be proactively sought by the contractor.80 The discretion should only apply to those delays caused by an employer’s act of prevention, which would result in the employer being paid liquidated damages by the contractor if no extension of time is granted.81 Bell highlights that this apportionment of responsibility would focus on the function of the remedy of liquidated damages, namely to compensate the employer for delay caused by the contractor.82 This approach would enable a decision-maker to retrospectively assess any extension of time based on the period of delay caused by an employer’s act of prevention.83
Summary and Conclusion
A review concerning the strict operation of condition precedent to an extension of time is due. There are increasing reservations concerning the adequacy and fairness of such clauses, particularly when an employer knowingly benefits from its own breach, obtaining liquidated damages. Many standard forms of contract have introduced a discretion to circumvent those scenarios where the contractor is deprived of a fair and reasonable entitlement due to its failure to notify the employer. JCT and FIDIC include provisions to dispense with the failing of notice provisions enabling the contract administrator to exercise independent judgement under a duty to act fairly and impartially.84 Standard forms of contract should continue embracing this approach and relaxing notice provisions by including this discretion, prescribing for what events and under what circumstances it should apply.
There should be no reason to argue that a contractor would gain an advantage by not giving notice for an extension of time in anticipation of subsequently raising an argument of prevention. As discussed in the next section, a contractor significantly benefits from dealing with claims early as the facts are fresh and information readily available.
TIME OF ASSESSMENT
Assessment of Extension of Time in Standard Forms
The approach to determining when the assessment of a potential contractor’s entitlement is to be undertaken is governed by the particular extension of time provisions in the contract.85 Most standard forms of contract give
80 Above fn 58, p 69.
81 Above fn 54, p 206.
82 Bell, M, “Scaling the Peak: The Prevention Principle in Australian Construction Contracting”, [2006] ICLR 318, p 354.
83 Above fn 26, p 352.
84 A decision maker is required to “act in a manner […] described as independent, impartial, fair and honest”. Scheldebouw BV v St James Homes (Grosvenor Dock) Ltd (QBD (TCC)) [2006] EWHC 89 (TCC); [2006] BLR 113; 105 Con LR 90 at paragraph 34 (Jackson J).
85 Furst, S and Ramsey, V, Keating on Construction Contracts, 11th Edition, ch 8, paragraph 8.020.
372
The International Construction Law Review [2024
that power to the certifier to assess the contractor’s entitlement during the course of the project, or prospectively.86
Under JCT, the contractor is required to give particulars of the expected effect, “including an estimate of any expected delay in the completion of the Works beyond the relevant Completion Date”.87 The certifier must make a determination and notify the contractor “as soon as is reasonably practicable and in any event within 12 weeks of receipt of the required particulars” or before the completion date, whichever is earlier.88 Similarly, under FIDIC, the contractor is entitled to an extension of time “if and to the extent that completion … is or will be delayed” by an event for which the contract states it is not responsible.89 After the contractor has complied with the notice requirements under the contract, the Engineer is then required to “agree or determine […] the extension (if any) of the Time for Completion (before or after its expiry)”.90 NEC deals with extensions of time in a more prescriptive way, as it sets out the point at which the assessment shall be carried out as a “dividing date” that separates the work done (actual) from the work not done (forecast). It is defined as either the date of a project manager’s communication or the date of the contractor’s notification of a compensation event.91
In practice, it seems reasonable to promote a prospective analysis for the interest of the project as a whole, as applications for additional time can be granted at the earliest opportunity.92 It provides the parties with certainty over the duration of the project, resetting any rights and obligations under the contract.93 The courts have also been supporters of this prompt approach to dealing with time issues, as the contractor “can replan the remaining works in the most efficient way by deploying resources or resequencing the works”.94 However, there is a significant weakness. The determination is largely done on a theoretical basis, by estimating the extent of delay, so in a dispute forum, after the actual effect is known, the English courts have been critical of prospective assessments performed after the event.95
86 In this context, certifier refers to the third party responsible for administrating the contract and for the decision making in relation to the rights and obligations of the parties under the construction contract. In JCT, could be the architect or contract administrator, in NEC is the project manager, in FIDIC is known as the engineer or in Australia, the superintendent.
87 JCT SBC/Q 2016, clause 2.27.2.
88 Ibid, clause 2.28.2.
89 FIDIC 2017, sub-clause 8.5.
90 FIDIC 2017, sub-clause 20.2.5(b).
91 NEC4 2017, clause 63.1.
92 Bahl, M, “The crystal ball, or the microscope: deciding upon a prospective, or retrospective approach to delay analysis”, (2019) 35 CLJ 4, p 2.
93 Bailey, J, “The Society of Construction Law Delay and Disruption Protocol: A Retrospective Analysis”, SCL Paper 189, November 2014, p 7.
94 Ascon Constructing Ltd v Alfred McAlpine Construction Isle of Man Ltd (1999) 66 Con LR 119 at paragraph 128.
95 McAlpine Humberoak Ltd v McDermott International Inc (No1) (CA) [1992] 58 BLR 1 at paragraph 45, Great Eastern Hotel Company Ltd v John Laing Construction Ltd and Another (QBD (TCC)) [2005] EWHC 181 (TCC); 99 Con LR 45 at paragraph 184, Costain Ltd v Charles Haswell & Partners Ltd (QBD (TCC)) [2009] EWHC 3140 (TCC); 128 Con LR 154 at paragraph 181 and Bluewater Energy Services BV v Mercon Steel Structures BV (QBD (TCC)) [2014] EWHC 2132 (TCC); 155 Con LR 85 at paragraph 324.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
373
Second Stage Assessed Retrospectively
Both JCT and FIDIC include a “second stage” of assessment by which the certifier is required to decide whether any retrospective adjustment
must be made, with the restriction that the time for completion cannot be reduced. Under JCT:
“… after the Completion Date for the Works or of a Section … the Architect/Contract Administrator may … fix a Completion Date for the Works later than that previously fixed if in his opinion that is fair and reasonable.”96
FIDIC similarly includes a provision to review or adjust any previous entitlement already awarded:
“When determining each extension of time under sub-clause 20.1, the Engineer shall review previous determinations and may increase, but shall not decrease, the total extension of time.”97
This begs the question of why there is a proviso preventing the reduction of entitlement in these forms of contract?98 The answer must be certainty. Parties need to know when the project will be completed to enable the works to be planned efficiently. In practice, however, the inability to reduce the entitlement creates an undesired rigid contractual framework. When a contractor claims an extension of time on a prospective basis, the employer may fear awarding too much time until the actual effect of the delay is known, without the power to adjust it downwards later. The potential consequence is overpaid costs for the extended period and the loss of its right to claim any delay damages.99 This is known as a “wait and see” approach which militates against the primary purpose of extension of time provisions.100
What would the effect be if a potential reduction could be applied? Taking cost management as an example, if an inflated interim payment application is submitted during the course of the project, the certifier may decide to award the claimed sum in the knowledge that it could still resort to a final account reconciliation through which any necessary adjustments can be made.101 The contractor is eventually paid what it actually deserves. The same rationale can be applied to time management. If, for example, a contractor was awarded an additional 10-week period, but then a retrospective review proved that it was only entitled to an eight-week period, two weeks would be deducted. There may be an argument that, as a result of the additional
96 JCT SBC/Q 2016 clause 2.28.5.
97 FIDIC 2017 sub-clause 8.5.
98 Under JCT SBC/Q 2016 clause 2.28.5.2 a previous extension of time can only be reduced if a Relevant Omission warrants it, namely if critical works have been omitted since the previous award of additional time.
99 Burr, A and Palles-Clarke, R, “The consideration of critical path analysis in English law”, (2005) 21 CLJ 224.
100 SCL Delay and Disruption Protocol, 2nd Edition, (February 2017), core principle 4.
101 JCT SBC/Q 2016 clause 4.25, FIDIC 2017 clause 14.13 or newly introduced in NEC4 2017 under clause 53.
374
The International Construction Law Review [2024
10 weeks, the contractor “paced itself” to gain a commercial advantage of any windfall already awarded. Standard forms contain provisions that would prevent this scenario by compelling the contractor to carry out the works “with due diligence”.102 Another possible argument is that the contractor may be retrospectively deprived of time which might lead to liquidated damages being levied for a period that had already been accounted for as “excusable delay”. In such a scenario, the principle held in Balfour Beatty Building Ltd v Chestermount Properties Ltd
103 would apply whereby an extension of time would only be retrospectively awarded for periods of “excusable delay” by deducting any periods for which the contractor is deemed responsible.104 Specific periods of entitlement relating to specific excusable events would consequently be added to the completion date. The outcome (length of the extension) would be a matter of fact and degree with the burden of proof falling on the employer.105 No additional cost would be incurred as expert evidence would have to be provided if the parties disagree on the extent of the extension awarded or if no extension at all had been previously awarded. The benefit of enabling a reduction outweighs such potential complications as it defuses the much more common scenario in which no entitlement at all is given, by enabling the certifier to give incremental extensions of time with the safeguard that a subsequent adjustment can be done, once the true impact can be measured.
Prospective Approach
Under NEC, no such second stage mechanism exists as the philosophy is for claims to be settled at the time by predicting the future effect of an event and without later revision if the assessment is proven wrong.106 At first inspection, NEC would appear to be watertight against the scenarios described above as it requires the parties to act and resolve claims before the completion of the project, stimulating good project management. In reality, disputes arise under NEC when the parties disagree on the assessment of the project manager.107 The prescriptive nature of NEC would suggest that a prospective approach should be taken, even in a dispute forum after the event. However, recent authorities indicate that is not the case. In Northern Ireland Housing Executive v Healthy Buildings (Ireland) Ltd
108 the court held that, although the NEC3 regime is underpinned by prospective analysis, the assessment after the event should “be informed by the best information as to the actual cost and time incurred” which in this case was evidence of what
102 JCT SBC/Q 2016 clause 2.4, FIDIC 2017 sub-clause 8.1, NEC4 2017 clause 63.9.
103 (1993) 62 BLR 1.
104 This aligns with the approach stated at footnotes 82 and 83.
105 West Faulkner Associates v London Borough of Newham (CA) (1995) 71 BLR 1.
106 NEC4 2017 clause 66.3.
107 NEC4 2017 clause 64.1.
108 (NIQB) [2017] NIQB 43.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
375
happened.109 Similarly, in Imperial Chemical Industries Ltd (ICI) v Merit Merrell Technology Ltd,110 the court held that although an earlier assessment may carry “powerful evidential weight” it was not binding and could be opened up and reviewed in a dispute context, as “there is nothing in the NEC form […] that states that a Project Manager’s assessment is conclusive as to the rights of the parties”.111 Irrespective of the prescription for a prospective assessment under NEC, the English courts would not disregard evidence showing what actually happened after the event. A retrospective analysis based on the best evidence at their disposal would still be preferred. As Lord Machnaghten put it, “with the light before him, why should he shut his eyes and grope in the dark?”.112
In Healthy Buildings and ICI, however, neither party operated the contract as stipulated, so it is suggested that the courts resorted to the compensatory principle set out in The Golden Victory
113 by which events that have occurred after the breach reducing the claimant’s loss must be taken into consideration to prevent over-compensating.114 It is yet to be seen what the outcome would be if a compliant claimant disputed the entitlement awarded. Case law suggests that a retrospective method of analysis would still be preferred.115 That outcome would, however, severely undermine the agreement of the parties under NEC by which the contractor takes the risk of an inadequate forecast and potentially being under-compensated as a result.116 The courts should not interfere with the risk allocation freely agreed by the parties, even when the results may differ from reality. The alternative is for NEC to incorporate a clear provision under which a prospective assessment is mandated when one party has strictly complied with the contract. That would deter unscrupulous parties from using tactics trying to escape previously agreed terms signed just because the outcome does not turn out in their favour.
Summary and Conclusion
The three standard forms of contracts contain extension of time provisions which promote a prospective assessment. Whilst JCT and FIDIC enable the certifier to retrospectively review the issues encountered during the works and assess if any additional time is due, NEC does not permit any re-evaluation once the compensation event is implemented.117
109 Ibid, paragraph 48.
110 [2018] EWHC 1577 (TCC); 178 Con LR 89.
111 Ibid, paragraph 67.
112 Bwllfa Dare Steam Collier Ltd v The Pontypridd Waterworks Company (HL) [1903] AC 426 at paragraph 431.
113 Golden Strait Corporation v Nippon Yusen Kubishka Kaisha
(The Golden Victory) (HL) [2007] UKHL 12 [2007] 2 Lloyd’s Rep 164; [2007] 2 AC 353; [2007] 2 WLR 691; [2007] 3 All ER 1.
114 Ibid, paragraph 83.
115 Robinson, L, “Claims for Compensation Events – How Should a Contractor Prove its Claim for Time?”, (2002) CLJ 28(6), p 511.
116 Ibid, paragraph 512.
117 NEC4 2017 clause 66.3.
376
The International Construction Law Review [2024
However, such a review can only increase a previously awarded extension of time to provide certainty of when the work will be complete. The fact that no reduction is allowed defeats the purpose of any reassessment, as an employer could in practice simply do nothing until the actual entitlement can be measured. The restriction is not practicable and does not provide a workable mechanism. The provisions should be tailored to allow the parties to reassess once the true effect is known, irrespective of whether the result leads to a reduction. Pacing or other arguments relating to a lack of reasonably expected performance can be resolved by way of factual assessment based on expert evidence. At the very least, this procedure would enable the parties to move on and avoid falling into the trap of an early dispute.
Under NEC, in a dispute after the event, there is legal authority that a retrospective assessment will be carried out irrespective of the approach prescribed in the contract. To protect a compliant party, a provision should be incorporated to restrict the power of the courts to use any other records issued at a later stage. The agreement of the parties should be respected and not undermined simply because one of them has decided not to follow it. By doing so, the ethos of NEC of resolving claims whilst the issue is fresh would be preserved, thereby recognising the value of compliance with the contract.
CONCURRENCY AND CONSTRUCTIVE ACCELERATION
Introduction
Concurrency and constructive acceleration are issues commonly argued in disputes and due to their legal complexity and fact-sensitivity, legal authorities appear to point in opposite directions. There is still no consensus as to the most suitable approach to assess an extension of time. The current position of the law is unsatisfactory and would benefit from authoritative appellate guidance on these matters.118 A standard form of contract should provide the parties with clarity and certainty as to how resolve any controversy without having to resort to the courts. This chapter will explore these issues and how, if at all, each standard form of contract provides an answer to them, and whether based on examples from other jurisdictions, amendments are warranted to improve the certainty of the outcome.
Concurrent Delay
Concurrent delay is one of the most complex issues arising from a construction contract.119 The accepted definition by the English courts is “a period of project overrun which is caused by two or more effective causes of delay
118 Above fn 8, paragraph 11.73.
119 Burr, A, Delay and Disruption Construction Contracts, 5th Edition, (2016).
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
377
which are of approximately equal causative potency”.120 The Malmaison approach is the preferred method for resolving concurrency.121 It is commonly known as “time no money”, as the contractor is entitled to a full extension of time due to the employer’s delay but not to prolongation costs arising from the period of overrun.122 It is also accepted that when there are two effective causes of delay that are not of equal causative potency, the dominant cause test should be deployed, whereby only the event causing the delay, would be considered in the assessment of extension of time.123 However, none of these approaches are included in the standard forms of contract reviewed in this article.
Under NEC, it is widely acknowledged that no concurrent delay exists, as the analysis of the effect of a compensation event is carried out prospectively at the time it occurs, so the actual effect of the contractor’s delay (lack of progress) cannot be fully ascertained.124 Under FIDIC, there is a general statement addressing concurrent delay but it does not describe the process to be followed and merely refers to “be assessed in accordance with the rules and procedures stated in the Special Provisions”.125 Under JCT, no express reference to concurrent delay is identified. The Contract Administrator has a wide measure of discretion in how to assess concurrency. That may involve apportionment, which has divided opinions amongst practitioners.126 If no express provision has been included, the Malmaison approach will generally be followed under English law. The rationale is that the parties have implicitly agreed through the extension of time provisions that “the contractor is entitled to an extension of time for an effective cause of delay”.127
Accordingly, it would appear that the principle emanates directly from the contractual provisions. This view is shared by commentators who suggest that the principle is about risk allocation,128 which infers that under JCT at least, concurrent delay should be considered as a “neutral event” in which
120 Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm); [2011] BLR 384 at paragraph 277, Hamblen J referred to John Marrin QC’s definition in “Concurrent Delay”, (2002) CLJ 18(6) 436, 437.
121 Established in Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd (1999) 70 Con LR 33 by Dyson J.
122 De Beers UK Ltd v Atos Origin IT Services UK Ltd [2010] EWHC 3276 (TCC); [2011] BLR 274; 134 Con LR 151 at paragraphs 177–178. The position is that for an assessment of time the claimant must prove that the relevant event delayed the completion of the works, namely was on the critical path, whereas for an assessment of loss and expense the claimant must prove that “but-for” the relevant event, it would have completed earlier, and as a result, it would not have suffered that loss as a matter of fact.
123 Moran, V, “Causation in Construction Law. The Demise of the ‘Dominant Cause Test’”, (2014) SCL 190.
124 City Inn Ltd v Shepherd Construction Ltd (CSOH) [2007] CSOH 190; [2008] BLR 269 at paragraph 13 (Lord Drummond): “It is clearly only with hindsight that the causative potency of each of the sources of delay can be properly assessed”.
125 FIDIC 2017 sub-clause 8.5.
126 Mastrandrea, F supports the approach in “Apportionment in the Evaluation of Construction Delays”, [2011] ICLR 172. Barry, D considers that an “unnatural” interpretation of the clause in “Concurrent delay in construction law” (2011) CLJ 165, p 176.
127 Furst and Ramsey, Keating on Construction Contracts, paragraph 8-026.
128 McAdam, B, “Apportionment and he common law: has City got it wrong?”, (2009) CLJ 25(2), p 79.
378
The International Construction Law Review [2024
the loss is shared.129 Others believe that the outcome of “all or nothing”130 when applying the Malmaison approach, leads to an unbalanced position.131 In The Royal Brompton Hospital NHS Trust v Hammond (No 7), Seymour HHJ held that if by reason of a contractor being already in delay, the effect of a relevant event does not extend beyond the already delayed date, “the relevant event simply has no effect upon the completion date”.132 In Adyard, Hamblen J approved this principle and concluded that “the act relied on … must cause some actual delay”.133 This has been known as the “first in time” approach and has successfully been used to defend extension of time claims by employers.134 In Thomas Barnes & Sons plc v Blackburn with Darwen Borough Council, Davies J
recently decided that two events were “effective causes of delay”, even though one event arose first and extended even after the effect of the other had ceased.135 This decision appears contrary to the previous approaches in Hammond (No 7) and Abyard. As a result, there is uncertainty as to the precise circumstances in which two events will be held to be concurrent. This was acknowledged in North
Midland Building Ltd v Cyden Homes Ltd
136 where “differences of view expressed in both the first instance cases and the textbooks” were noted, but left unresolved.137 Can standard forms of contract alleviate this situation and provide certainty to the parties?
In North
Midland, an express term dealing with concurrency was agreed by the parties, which negated the Malmaison approach resulting in the contractor not being entitled to an extension of time for any period of concurrent delay. The Court of Appeal approved the validity of the clause so it is now established precedent that the parties can decide the principle by agreement. Some commentators suggest that this will increase the number of expressed concurrent delay clauses added to construction contracts.138 This author considers the potential increase in expressly stated concurrent delay provisions in contracts, to be not only an advantage that will increase certainty, but it should also be the way forward for standard forms of contract. As Coulson LJ stated, “there is no reason in principle why a workable concurrency clause could not be agreed”.139 In other jurisdictions, the courts have also held that if the parties have agreed an approach to concurrent
129 The contractor is not entitled to be paid for the extended period. The employer is not entitled to receive liquidated damages.
130 Coulson, P, “Prevention or Cure? Delay Claims and the Rise of Concurrency Clauses”, (2019)
SCL 218.
131 Balen, M, “Concurrent Delay, Over-determination and the Problem of Default Rules”, (2016) CLJ 32(3), p 269.
132 (2000) EWHC Technology 39 at paragraph 31.
133 Above fn 120 at paragraph 282.
134 Saga Cruises BDF Ltd and Another v Fincantieri SPA (QBD (Comm)) [2016] EWHC 1875 (Comm).
135 [2022] EWHC 2598 (TCC); 204 Con LR 143 at paragraph 140.
136 [2018] EWCA Civ 1744; [2018] BLR 565; 180 Con LR 1.
137 Ibid, paragraph 50.
138 Twivy M, “The Prevention Principle after North Midland v Cyden Homes: Time for Change?”, 2019 SCL 215.
139 Above fn 130, paragraph 45.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
379
delay, this must be respected.140 In Australia, standard forms of contract already incorporate clear provisions by which the approach to concurrent delay is understood. Australian AS 4000-1997 states that if concurrent delay arises, “the Superintendent shall apportion the resulting delay”, according to the contribution of each party.141 Accordingly, standard forms of contract should follow the approach in North
Midland of including express provisions describing how concurrency should be assessed, thereby providing certainty to throw this debate into oblivion.
Constructive Acceleration
“Constructive acceleration” is a doctrine that originated in the US that enables contractors to recover acceleration costs where the employer or certifier in a contract refuses to grant genuine time extension requests, forcing the contractor to accelerate to avoid liquidated damages. Bramble and Callahan suggest that an “implied contract” would be a more conventional ground for these type of claims.142 This alleged acceleration is not voluntarily accepted by the contractor which is implicitly obliged to accelerate the works by the employer’s refusal to award any additional time. The employer would argue that the delay is the responsibility of the contractor, whereas the latter would claim that it is entitled to an extended contract period. When the contractor is denied a genuine extension of time under the contract, it faces a dilemma; should it accelerate the work in an attempt to still achieve the original completion date or continue as normal hoping that the employer will award any additional time due and not deduct liquidated damages?143 In other jurisdictions, there are standard forms of contract
that include express provisions to deal with this scenario. By way of an example, the Swedish ABT06 provides the contractor with the opportunity to accelerate being “entitled to compensation for the acceleration” if later it is found that it was genuinely entitled to an extension of time.144 Should this be the general approach for all standard forms?
Opinions are divided on the legal basis under English law on which to support such constructive acceleration claims. Lane points out that a claim could be based on an implied instruction to accelerate by the certifier’s wrongly refused extension of time request.145 Gusman argues that it could also be based on a claim for a breach of contract by demonstrating that the certifier has failed to fulfil an obligation under the contract.146 Conversely,
140 SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391 (VSC).
141 Australian AS 4000-1997, clause 34.4.
142 Bramble, B and Callahan, M, Construction Delay Claims, 4th Edition, (Wolters Kluwer, Law & Business, 2010) ch 6.05.
143 Whaley, A R, McAdam, W B and Crowe, P, “The acceleration dilemma: can English law accommodate constructive acceleration?” 2015 IJOLIBE 248, p 250.
144 Swedish ABT06 General Conditions of Contract, Chapter.4.6 “Acceleration”.
145 Lane, N, Constructive acceleration, 2000 CLJ, 16(4), 231.
146 Gusman, R, “Constructive change – A theory labelled wrongly”, (1974) PCLJ (6), 229.
380
The International Construction Law Review [2024
Bailey argues that it is difficult to attribute the breach of contract to the employer, as there is no express instruction to accelerate and the certifier is not a party to the contract.147 Unless an employer directly influences or exerts pressure on the contractor to accelerate, it is unclear how the employer could be held liable for a wrongful administration of the contract by the certifier. This is reflected in the greatly reduced number of available decisions under English law in which a claim directly or indirectly based on “constructive acceleration” has ever succeeded. In Amex Process and Energy Ltd v Stork Engineers BV
148 a contractor was allowed to recover as damages the additional costs of the measures implemented to overcome the effect of a breach of contract by the employer.149 In Great Eastern Hotel Company Ltd v John Laing Construction Ltd and Another
150 the court endorsed acceleration measures that were “adopted in order to mitigate [the employer’s] losses and as such the costs […] are recoverable from the contract breaker”.151 However, in Ascon Contracting it was held that a contractor cannot claim damages as a result of an extension of time and simultaneously, as a loss by way of mitigation “unless it is alleged and established that the attempt at mitigation, although reasonable, was wholly ineffective”.152 Perhaps the most relevant case is Motherwell Bridge Construction Ltd (t/a Motherwell Bridge Storage Tanks) v Micafil Vakuumtechnik
153 where a claim for acceleration costs was accepted under the circumstances of a refusal to grant an extension of time.154 However, the legal basis for the decision was not stated.
The general position of English law concerning how a contractor should deal with a “constructive acceleration” scenario has been clearly described by the Court of Appeal. In Lubenham Fidelities and Investments Co Ltd v South Pembrokeshire District Council,155 the argument that the employer was obliged to intervene and correct the certifier’s defaults was rejected, concluding that the “one simple remedy available [to the claimant] was to go to arbitration”.156 Accordingly, if a contractor considers that it is entitled to an extension of time, it should make use of the dispute resolution machinery included in the contract. This principle was reaffirmed in Pacific Associates Inc v Baxter and Others
157 in which Purchas LJ emphasised the mechanism is set within the “contractual provisions in the contract which afforded an avenue enabling the contractor to recover from the employer”.158 Adjudication is available under JCT
147 Above fn 8, paragraph 11.198.
148 (1999) 68 Con LR 17.
149 Above, paragraph 110.
150 [2005] EWHC 181 (TCC); 99 Con LR 45.
151 Ibid, paragraph 321.
152 Above fn 94 at paragraph 56.
153 (QBD (TCC)) (2002) 81 Con LR 44.
154 Ibid, paragraphs 140–141.
155 (1986) 33 BLR 39.
156 Ibid, paragraph 47.
157 (1989) 44 BLR 33; [1989] 3WLR 1150; [1989] 2 All ER 159.
158 Ibid, paragraph 180.
Pt 4] Shut Your Eyes, Grope in The Dark And … Never Look Back?
381
and NEC both as an express contractual provision159 and as a statutory right for those construction projects under the umbrella of the Construction Act.160 It provides a speedy and binding resolution of any dispute as to the contractor’s entitlement.161 Similarly, under FIDIC, the contractor can apply to obtain a DAB decision, which after the amendments made in the 2017 Edition, would provide a binding decision on both parties,162 who shall promptly give effect to it, irrespective of whether a notice of dissatisfaction is given.163 This can be referred directly to arbitration if the other party fails to comply.164 It is therefore apparent that any inclusion of an express clause to enable a constructive acceleration claim would provide little added practical benefit to the contractor under these standard forms of contract.
Accordingly, unless expressly stated in the contract, it would appear that the answer to the contractor’s dilemma is not to embark on a voyage into the unknown under the flag of “constructive acceleration”, but rather to seek recourse through the existing dispute resolution procedures available in the contract to demonstrate its entitlement to additional time.
CONCLUSION AND RECOMMENDATIONS
There is room for reform of extension of time provisions in standard forms of contract. It is crucial to define a workable contractual machinery by which the parties can resolve their claims effectively. This is not the current situation, partly due to the rigid operation of these provisions and partly due to the parties’ conduct. They should not strive for precision but rather for principles of fairness and reasonableness.
To provide further flexibility this author recommends the Australian and Swedish approaches are followed. Time entitlement should not be conditional on the issue of a notice in circumstances where an employer’s act of prevention is the cause of the delay. A discretion should be given to the certifier to assess whether the employer was aware of the consequences of its actions and, if so, assess the claim based on its merits fairly and impartially.
A notice should still be considered as a condition precedent for neutral events outside the employer’s responsibility and for which the contractor should proactively activate its right to additional time. The following wording should be included:
159 JCT SBC/Q 2016 section 9.2, NEC4 Secondary Option W.
160 Housing Grants, Construction and Regeneration Act 1996, section 108.
161 Within 28 days of the dispute being referred to the adjudicator or 42 days if extended by the referring party.
162 Within 84 days of the dispute being referred to the DAAB.
163 FIDIC 2017 sub-clause 21.4.
164 FIDIC 2017 sub-clause 21.6. Obtaining a DAAB decision is a condition precedent to referring that dispute to arbitration (sub-clause 21.4.4).
382
The International Construction Law Review [2024
“The Contractor may apply to waive the requirement to give a notice as a precondition to an extension of time only if all the following conditions are met:
(a) the Contractor does so as soon as practicable after being formally informed in writing that its claim is time-barred;
(b) the Employer is responsible for the event or circumstance giving rise to such entitlement and;
(c) there is evidence that the Employer had prior knowledge of the claim and its potential consequences.
The Contract Administrator will have the power to override the contractual requirement to serve a notice condition if it is ‘fair and reasonable’ to do so.”
Standard forms that include a retrospective second stage assessment, such as JCT or FIDIC, should permit a reduction to be made with the onus of proof falling on the employer. Arguments around the contractor pacing the works should be resolved by resorting to those provisions relating to due diligence already contained in the contract. The following wording is proposed:
“The Contract Administrator shall determine each extension of time on its own merits and review previous awards by fixing a revised Completion Date later in time, or by decreasing the total extension of time already awarded only if:
(a) the Employer has applied for such reduction formally in writing and provided particulars substantiating a potential earlier Completion by the Contractor;
(b) it is fair and reasonable to do so given all the circumstances.”
Those standard forms that solely prescribe a prospective assessment should reinforce that methodology by unreservedly mandating such an approach when one party has fully complied with the provisions thereby preserving the agreement made by the parties. A proposed wording for NEC could be:
“Any assessment of delay to Completion shall only be carried out following the procedures stated in this Contract which cannot be altered, varied or diverted from in any way by a decision-maker at later legal proceedings when a Party has fully complied with the relevant provisions stipulated in this Contract.”
Similarly, following the example of Australia, standard forms should take a clear stance as to how concurrent delay should be identified and assessed by introducing additional express provisions. Parties would then be free to select the standard form depending on their risk appetite. A sample wording is provided below for the options of no entitlement for the contractor and equal apportionment.
“Any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account/shall be equally apportioned between the Parties.”
Finally, following the Swedish approach, an express provision for constructive acceleration could potentially be incorporated in the standard forms of contract revised in this paper, however, this would have very little practical utility for the resolution of disputes after the decisions in Lubenham. Contractors can typically seek recourse via adjudication under JCT or NEC, whether by statute or contract, or via DAB under FIDIC which provides a speedy resolution of a potential refusal to award a genuine extension of time to the contract.