i-law

Practical Guide to Engineering Procurement and Construction Contracts


Page 151

Index

Index

  • Basic Design and Engineering Package (BDEP) 5
  • BDEP see Basic Design and Engineering Package (BDEP)
  • bias: in dispute causes 2;
    • optimism and 31;
    • political 2, 48, 56;
    • psychological 2, 48, 56
  • cap on liability 65
  • causal connection, in claims 107–108
  • change control: in contract management 94
  • change valuation 105–106
  • choice of law: Joint Ventures and 126, 147
  • claim(s): anticipation 95;
  • collaboration 54–55
  • conceptual design 34–35
  • concurrent delay 76–77;
    • see also delay
  • confidentiality: Joint Ventures and 121–122, 140–141
  • consequential changes 103
  • consequential or indirect damages 50
  • Consortium: expulsion from 148;
    • formation of 126–128;
    • insurance in 118–119;
    • Joint Venture vs. 126–127;
    • leader 147–148;
    • liabilities 148;
    • offer by 117;
    • reasons for forming 114;
    • securities in 117–118;
    • steering committee with 147;
    • see also Joint Venture (JV)
  • construction/erection all risks insurance 118, 137
  • construction management: daily tasks of 69;
    • responsibilities of 68–69;
    • setting out in 69–70;
    • team 67
  • Construction Program Manual (CPM) 94
  • constructive acceleration 103–105
  • constructive changes 101
  • contract conditions 36–37, 46, 47, 52–57;
    • change control in 94;
    • claim anticipation in 95;
    • method of performance changes and 102;
    • subcontract 64–65
  • contract management: change valuation and 105–106;
    • claims management in 95–96;
    • consequential changes and 103;
    • constructive acceleration and 103–105;
    • constructive changes and 101;
    • Contractor-ordered changes and 100;
    • defective specifications and 101;
    • defects and 96–101;
    • documentation control in 93–94;
    • entitlement preservation and 110–111;
    • information supply and 3;
    • notices and 108–109;
    • over-inspection and 102;
    • Owner-ordered changes and 99–100;
    • Owner-provided defective materials or property and 102–103;
    • plans and procedures in 93;
    • program 93–96;
    • purpose of 91–92;
    • records in 109–110;
    • and rejection of conforming work 102;
    • schedule control in 94;
    • third party changes and 100;
    • variation orders and 98–99
  • Contractor: in contract tendering and negotiation 49–52
  • contract review 93
  • contract tendering and negotiation: award criteria in 47;
  • contractual exclusions 50
  • cooperation 29
  • cost control 67
  • damage: as dispute cause 21–24;
    • liability for, as Owner obligation 42–44
  • damages: for delay, liquidated 19;
    • as dispute cause 21–24;
    • penalties vs. liquidated 19
  • defect(s): contract management and 96–101;
    • Contractor-ordered changes and 100;
    • failure to remedy 89;
    • Owner-ordered changes and 99–100;
    • price reduction for 89;
    • search 88–89;
    • subcontractor warranties and 97–98;
    • third party changes and 100;
    • variation orders and 98–99
  • defective specifications 101
  • Defects Liability Period 87–88, 96
  • delay: delay-causing events 75–76;
    • concurrent 76–77;
    • as dispute source 18–19;
    • liquidated damages for 19;
    • sequential 77–78
  • design: complexities of 60;
    • liability 58–60;
    • submission of documents, to Owner 59–60;
    • variations provision and 60–61
  • Design Brief 4
  • dispute causes 1–26;
    • bias in 2;
    • damages in 21–24;
    • delay in 18–19;
    • information supply in 2–4;
    • origins of 1;
    • from outside contractual parties 15–17;
    • payment in 11–15, 13;
    • price in 9–11;
    • quality in 19–20;
    • rely-upon information and 3;
    • scope of work in 4–6;
    • site access as 7–8
  • dispute resolution 24
  • documentation control 93–94
  • drawings: as Owner obligation 39
  • due diligence: decision-making after, in project conception 30–32
  • duty of non-interference 39–40
  • Employer’s Requirements: conceptual design in 34–35;
    • contract conditions in 36–37;
    • facility requirements in 35;
    • general requirements in 35;
    • overview of 34;
    • Owner’s obligations in 37–44;
    • particular requirements in 35;
    • tender phase in 35–36
  • entitlement preservation 110–111
  • environmental protection 71–72
  • EOT see extension of time (EOT)
  • equipment: Ownership of 73;
    • Owner-supplied 72
  • exchange rates 10
  • exclusions: in contract tendering and negotiation 50;
    • in scope of work 6
  • experience 29
  • expulsion: from Joint Venture 122–124
  • extension of time (EOT) 94
  • facility requirements 35
  • feasibility study 28–30
  • FEED see Front-End Engineering and Design (FEED)
  • Final Acceptance 41–42, 89
  • financing: in Joint Venture 120
  • fixed price contract 9–10
  • Flyvbjerg, Bent 2, 31, 48, 56
  • Force Majeure 17
  • forward contract 10
  • fossils 70
  • Front-End Engineering and Design (FEED) 36, 48, 58
  • general purchase conditions 65
  • general requirements 35
  • Health, Safety and Environment (HSE) 68;
    • see also safety
  • hold harmless 22–23
  • HSE see Health, Safety and Environment (HSE)
  • information: as Owner obligation 39
  • information supply: as dispute cause 2–4
  • innovation 29
  • inspection: joint 88;
  • instructions: as Owner obligation 39
  • insurance: construction/erection all risks 118;
  • invoicing: in Joint Venture 119, 138
  • knock-for-knock 21–23, 26, 42
  • knowledge sharing 30
  • labour shortage 76
  • late payments 11–12
  • L/C see letter of credit (L/C)
  • letter of credit (L/C) 12–13, 13
  • liability: Consortium and 148;
    • in contract tendering and negotiation 50–52;
    • for damages 124;
    • design 58–60;
    • Joint Ventures and 122, 141–142, 144–145;
    • as Owner obligation 42–44;
    • for work provided 124
  • liability insurance 119
  • loss of profit, loss of use 50
  • lump sum pricing 9–10, 55
  • marine cargo/transportation insurance 118, 137
  • materials: Ownership of 73;
    • Owner-supplied 72;
    • shipping responsibility for 73
  • method of performance changes 102
  • milestone payments 18
  • mineral deposits 70
  • mutual hold harmless 22–23
  • non-interference, duty of 39–40
  • notices 108–109
  • optimism 31
  • option contract: exchange rates in 10
  • overall liability cap 50
  • over-inspection 102
  • Owner: changes ordered by 99–100;
    • in contract tendering and negotiation 46–49;
    • defective materials or property provided by 102–103;
    • equipment supplied by 72;
    • materials supplied by 72;
    • plant supplied by 72;
    • services to be supplied by 72;
    • submission of design documents to 59–60;
    • supplies to be supplied by 72
  • Owner’s obligations: acceptance of work as 41–42;
    • approvals as 38;
    • drawings as 39;
    • duty of non-interference as 39–40;
    • in Employer’s Requirements 37–44;
    • information as 39;
    • instructions as 39;
    • liability as 42–44;
    • payment as 40–41;
    • permits as 38;
    • site access in 37–38;
    • site possession in 37–38;
    • start date as 38–39
  • Owner’s risks 17
  • particular requirements 35
  • payment: advance 11;
  • penalties: liquidated damages vs. 19
  • performance measurement 20
  • performance tests 79–80
  • permits: as Owner obligation 38
  • physical conditions, unforeseeable 15–17
  • Planning Fallacy 31
  • plant: Ownership of 73;
    • Owner-supplied 72
  • political bias 2, 48, 56
  • price: as dispute cause 9–11;
    • reduction, defects and 89
  • procurement, project 32
  • project conception: cooperation in 29;
    • due diligence in, decision-making after 30–32;
    • experience in 29;
    • feasibility study in 28–30;
    • innovation in 29;
    • knowledge sharing in 30;
    • management in 27–28;
    • preparation in 29;
    • procurement and 32;
    • standardisation in 29
  • project management: in Joint Venture 116–117, 131–133

  • Page 154

    psychological bias 2, 48, 56
  • public convenience 71
  • public utilities 72
  • Punch List 89
  • purchase conditions 65
  • quality: as dispute cause 19–20
  • recordkeeping 109–110
  • Reference Class Forecasting 31–32, 48–49, 56–57
  • rely-upon information 3
  • requirements: facility 35;
    • general 35;
    • particular 35
  • Ruskin, John 48
  • safety: in construction 70–71;
    • see also Health, Safety and Environment (HSE)
  • schedule control: in contract management 94
  • scope of work: as dispute cause 4–6;
    • exclusions in 6;
    • subcontract and 64
  • securities: in Joint Venture/Consortium 117–118, 136
  • sequential delay 77–78;
    • see also delay
  • setting out 69–70
  • shipping responsibility 73
  • site access: as dispute source 7–8;
    • failure, in delay 76;
    • as Owner obligation 37–38
  • software issues 88
  • specifications, defective 101
  • standardisation 29
  • start date: as Owner obligation 38–39
  • storage responsibility 73
  • strikes 76
  • subcontract: conditions 64–65;
    • scope of work and 64
  • subcontractor warranties 97–98
  • substitution: expulsion by 124, 145
  • Taking-Over: assessment procedures after 84;
    • certificate 83–84;
    • conditions 82;
    • procedure 83;
    • relevance of 84;
    • responsibility transfer in 82–83
  • taxes: and Joint Ventures 121, 140
  • tender phase 35–36
  • termination: of Joint Venture 125
  • tests, performance 79–80
  • third parties: disputes arising from 15–17
  • third-party liability insurance 138
  • time management 67
  • transportation insurance 118
  • unforeseeable physical conditions 15–17
  • variation orders 98–99
  • variations provision 60–61
  • warranty: contractual 50–52;
    • quality and 20;
    • subContractor 97–98
  • wear and tear 88
  • workman’s compensation insurance 119, 137–138

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2026 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.