ENERGY WORKS (HULL) LTD V MW HIGH TECH PROJECTS UK LTD AND OTHERS

Construction Law Reporter

ENERGY WORKS (HULL) LTD V MW HIGH TECH PROJECTS UK LTD AND OTHERS

Contract – Legal effect of assignment of a subcontract – Novation – Claim for contribution

The claimant and the first defendant entered into a contract under which the first defendant was engaged as main contractor under an EPC contract to design, procure, construct, commission and test a fluidised bed gasification plant which was capable of processing refuse derived fuel produced by commercial, industrial and municipal solid waste. The second defendant provided a parent company guarantee in respect of the first defendant’s performance of the works. The first defendant entered into a subcontract with the Part 20 defendant (“Outotec”) for the supply of key elements of the gasification plant and Outec in turn entered into a deed of collateral warranty in favour of the claimant.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, please enter your details below to log in.

Enter your email address to log in as a user on your corporate account.
Remember me on this computer

Not yet an i-law subscriber?

Devices

Request a trial Find out more