C SPENCER LTD v MW HIGH TECH PROJECTS UK LTD

Contract – Hybrid contract involving both construction and non-construction operations – Whether payment notice, in order to be valid, was required to distinguish between construction and non-construction operations

The claimant was employed by the defendant as a sub-contractor on a project to design and construct a power plant which was capable of processing refuse derived fuel produced by commercial and industrial waste and municipal solid waste. The claimant was engaged to design and construct the civil, structural and architectural works. It was common ground between the parties that the subcontract works included work that amounted to “construction operations” within the meaning of the Housing Grants, Construction and Regeneration Act 1996 (the 1996 Act) but that it also included work that did not fall within that definition.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2024 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.