Building Law Monthly
Adjudication and natural justice
In Stellite Construction Ltd v Vascroft Contractors Ltd [2016] EWHC 792 (TCC) Carr J held that an adjudicator had not breached
the principles of natural justice. The adjudicator had decided the case on the basis of the material before him in circumstances
where the parties were each aware of the relevant material and where the issues to which the dispute gave rise had been fairly
canvassed before him. However, in so far as the adjudicator went on to consider what would be a reasonable time for completion
of the works, it was held that the adjudicator had exceeded his jurisdiction because the dispute which had been referred to
adjudication was the entitlement of the claimant to recover liquidated damages and what would be a reasonable time for completion
was beyond that jurisdiction.