Lloyd's Maritime Law Newsletter
London Arbitration 6/11
(2011) 827 LMLN 3
Demurrage - Delay at loading port caused by excessive
air draft - Whether time counted - Second period of delay
at loading port - Whether caused by bad weather or by
breakdown in camera on ship loader - Whether time
counted
The vessel was chartered on an amended Gencon form to carry a cargo of iron ore pellets in bulk from a named Canadian port
to China. Box 10 of the charter provided for the loading port in the following terms: