Building Law Monthly
ADJUDICATION, PROPER SERVICE OF THE NOTICE OF REFERRAL AND NATURAL JUSTICE
Primus Build Ltd v Pompey Centre Ltd [2009] EWHC 1487 (TCC), [2009] All ER (D) 14 (Jul)
In
Primus Build Ltd v Pompey Centre Ltd
[2009] EWHC 1487 (TCC), [2009] All ER (D) 14 (Jul), Mr Justice Coulson rejected the submission that a notice of adjudication
had not been served in accordance with the requirements of the contract. But he did point out that, if the service had been
invalid, it would have deprived the adjudicator of jurisdiction. It is therefore vital to ensure that a notice is validly
served. He also held that there had been a breach of the rules of natural justice in that the adjudicator had based his decision
on a point which both parties had agreed was irrelevant and he had failed to give to the parties an opportunity to make submissions
on the approach which he proposed to adopt. The adjudicator therefore had no jurisdiction to reach the decision which he had
reached and his decision was not enforced.