Building Law Monthly
SECTIONAL COMPLETION PROVISIONS DO NOT AMOUNT TO A PENALTY
Liberty Mercian Ltd v Dean & Dyball Construction Ltd [2008] EWHC 2617 (TCC), [2009] BLR 29
In
Liberty Mercian Ltd v Dean & Dyball Construction Ltd
[2008] EWHC 2617 (TCC),
[2009] BLR 29 Mr Justice Coulson held that the liquidated and ascertained damages stipulated to be payable in a clause dealing with sectional
completion arrangements of a construction project did not amount to a penalty clause and so were enforceable. The parties
were aware of the fact that the work was to be carried out sequentially and that the work on one section could not be started
until work on the previous section had been completed. The sums stipulated were not intended as a punish - ment but as a genuine
pre-estimate of the loss likely to be suffered and so the provision did not amount to a penalty.