i-law

Building Law Monthly

SECTIONAL COMPLETION PROVISIONS DO NOT AMOUNT TO A PENALTY

Liberty Mercian Ltd v Dean & Dyball Construction Ltd [2008] EWHC 2617 (TCC), [2009] BLR 29

In Liberty Mercian Ltd v Dean & Dyball Construction Ltd [2008] EWHC 2617 (TCC), [2009] BLR 29 Mr Justice Coulson held that the liquidated and ascertained damages stipulated to be payable in a clause dealing with sectional completion arrangements of a construction project did not amount to a penalty clause and so were enforceable. The parties were aware of the fact that the work was to be carried out sequentially and that the work on one section could not be started until work on the previous section had been completed. The sums stipulated were not intended as a punish - ment but as a genuine pre-estimate of the loss likely to be suffered and so the provision did not amount to a penalty.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2025 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.