AGREEMENT TO RESOLVE DISPUTE THROUGH ADR HELD TO BE ENFORCEABLE
Cable & Wireless plc v IBM United Kingdom Ltd [2002] 2 All ER (Comm) 1041
Online Published Date:
01 February 2003
Appeared in issue:
Vol 20 No 2 - 01 February 2003
CONSTRUCTION OF A COMPROMISE AGREEMENT
Mostcash plc v Fluor Ltd [2002] EWCA Civ 975; [2002] BLR 411
Online Published Date:
01 February 2003
Appeared in issue:
Vol 20 No 2 - 01 February 2003
‘DECISION’ OF ADJUDICATOR THAT HE WAS UNABLE TO DECIDE A NULLITY
Ballast plc v The Burrell Company (Construction Management) Ltd (unreported, 17 December 2002)
Online Published Date:
01 February 2003
Appeared in issue:
Vol 20 No 2 - 01 February 2003
ADJUDICATOR’s AWARD HELD TO BE IMMEDIATELY BINDING
A v B (unreported, Outer House of the Court of Session, 17 December 2002)
Online Published Date:
01 February 2003
Appeared in issue:
Vol 20 No 2 - 01 February 2003