NATS (SERVICES) LTD v GATWICK AIRPORT LTD DFS DEUTSCHE FLUGSICHERUNG GMBH (INTERESTED PARTY)
[2015] BLR Plus 1
Public procurement - Implementation of European Directive 2007/66 - Automatic suspension of tender process or equivalent injunction already in place until trial - Pleadings - Amendment of pleadings - application to strike out - Principles applicable to tenders under EC Regulations and whether duty in relation to "abnormally low" tenders - Expedited trial due to issues - Lack of time prior to trial and effect upon amendment
M T HØJGAARD A/S v E.ON CLIMATE AND RENEWABLES UK ROBIN RIGG EAST LTD AND ANOTHER
[2015] BLR Plus 2
Variation Orders under contract - Interpretation of Variation Order - Change in the method of working - Valuation of omitted works - Whether circumstances in which variation was issued were to be taken into account in construing contract
RENDLESHAM ESTATES PLC AND OTHERS v BARR LTD
[2015] BLR Plus 3
Defective Premises Act 1972 - Meaning of "dwelling", "in connection with the provision of a dwelling" and "fitness for habitation" - Measure of damages in respect of common parts - Damages for blight - Damages for inconvenience and distress
EUROCOM LTD v SIEMENS PLC
[2015] BLR Plus 4
Adjudication - Request for nomination of adjudicator - RICS form-identification of named adjudicators with conflicts - Possible fraudulent misrepresentation - Implied term not to subvert nomination process - Vitiation of adjudicator's appointment - Overlap between decisions in two adjudication decisions
WEATHERFORD GLOBAL PRODUCTS LTD v HYDROPATH HOLDINGS LTD AND OTHERS
[2015] BLR Plus 5
Contract - Breach of warranty - Misuse of know-how and confidential information - Inducing breach of contract - Abuse of process - Directors obligations under Companies Act 2006, sections 172 and 175
GARY KITT AND EC HARRIS LLP v THE LAUNDRY BUILDING LTD AND ANOTHER
[2015] BLR Plus 6
Adjudication - Jurisdiction - Attempt by referring party to confine dispute - Natural justice - Adjudicator's fees
SAVOYE AND SAVOYE LTD v SPICIERS LTD
[2015] BLR Plus 7
Adjudication - Enforcement of adjudicator's decision - "Construction operations" - Housing Grants, Construction and Regeneration Act 1996, section 105 - [Fixtures] - "Form part of the land"
IMTECH INVIRON LTD v LOPPINGDALE PLANT LTD
[2015] BLR Plus 8
Adjudication - Adjudication clause in main contract - No adjudication cause expressed in subcontract - Incorporation of main contract terms - Analysis of what was incorporated - Suitability for summary judgment process - One dispute under one subcontract referred to adjudication
PT PERUSAHAAN GAS NEGARA (PERSERO) TBK v CRW JOINT OPERATION (INDONESIA)
[2015] BLR Plus 9
Dispute adjudication board - FIDIC Red book - Binding nature of decision - Reviewable in arbitration - Enforceability of DAB decision - International Arbitration Act 2002 (Singapore) - Jurisdiction of arbitrators to issue interim award - Breach of natural justice rules
TRANSOCEAN DRILLING UK LTD v PROVIDENCE RESOURCES PLC (THE ARCTIC III)
[2015] BLR Plus 10
Contract - Interpretation - Exclusion and Limitation of Liability Clauses - Knock for Knock provisions
ISG CONSTRUCTION LTD v SEEVIC COLLEGE
[2015] BLR Plus 11
Adjudication - Jurisdiction - Entitlement to payment - Valuation of works - Payless notices - Recovery of monies overpaid
THE TRUSTEES OF THE MARC GILBARD 2009 SETTLEMENT TRUST v OD DEVELOPMENTS AND PROJECTS LTD
[2015] BLR Plus 12
Final Certificate - JCT Contract (2009 Edition) - Conclusive effect in any proceedings - Court proceedings started in time - Adjudication to be started later - Whether Final Certificate conclusive in adjudication proceedings
ST AUSTELL PRINTING COMPANY LTD v DAWNUS CONSTRUCTION LTD DAWNUS CONSTRUCTION LTD v ST AUSTELL PRINTING COMPANY LTD
[2015] BLR Plus 13
Adjudication - Enforcement adjudicatorâs decision - Part 7 and Part 8 proceedings - Challenge to jurisdiction of adjudicator - Whether dispute had crystallised - Whether referring party could refer part only of claim under interim application
LIBERTY MERCIAN LTD v CUDDY CIVIL ENGINEERING LTD AND ANOTHER (NO 3)
[2015] BLR Plus 14
Agreement to provide a performance bond - Remedies for failure - Senior Courts Act 1981, section 19 - Specific performance impossible - Appropriateness of payment into court as alternative remedy
GROUP M UK LTD v CABINET OFFICE
[2015] BLR Plus 15
Public procurement - Removal statutory suspension - Remedies Directive No 2007/66/EC - Principles governing injunctive relief - So-called "American Cyanamid" and those governing suspension of contract award under - Public Contract Regulations 2006 - Public interest
ASPEN INSURANCE UK LTD v ADANA CONSTRUCTION LTD
[2015] BLR Plus 16
Insurance - Combined contractors' liability policy - Public liability - Product liability - Meaning of product - Failure of work to perform intended function - Appropriateness of negative declaration is sought by insurers - Meaning of "superstructure" - Crane as "superstructure"
CIP PROPERTIES (AIPT) LTD (FORMERLY KNOWN AS NORWICH PROPERTY TRUST LTD) v GALLIFORD TRY INFRASTRUCTURE LTD AND OTHERS
[2015] BLR Plus 17
Costs Management Order - Costs Management Rules - Claimant's costs budget - Dramatic increase in costs incurred - Lack of explanation - Unreliable and disproportionate costs budget - Unreasonable costs - Detailed costs assessment for incurred and estimated costs
TRANSFORMERS & RECTIFIERS LTD v NEEDS LTD
[2015] BLR Plus 18
Contract formation - Battle of Forms - Incorporation of terms and conditions
GALLIFORD TRY BUILDING LTD v ESTURA LTD
[2015] BLR Plus 19
Adjudicator's decision - Application for summary judgment for enforcement purposes - Unfair fully to enforce - Partial stay
GOLDSWAIN AND ANOTHER v BELTEC LTD (T/A BCS CONSULTING) AND ANOTHER
[2015] BLR Plus 20
Professional negligence - Duty to warn - Professional's obligation to warn where possibility harm may occur
ALLIANCE CONCRETE SINGAPORE PTE LTD v SATO KOGYO (S) PTE LTD
[2015] BLR Plus 21
Contract - Frustration of contract - Unspecified source unavailable after contract formation - Whether parties contemplated the unspecified source - Whether parties discharged from further performance - Whether failure to supply sand prior to frustration amount to repudiatory breach
PAICE AND ANOTHER v MJ HARDING (TRADING AS MJ HARDING CONTRACTORS)
[2015] BLR Plus 22
Adjudication - Four adjudications - Same adjudicator for first, third and fourth - Telephone contact between claimants and adjudicator's office - Apparent bias - Test for bias - Fair-minded and informed observer - Adjudicator's explanations relevant matter in considering bias - Waiver of bias ground - Overlap between third and fourth decisions - Lack of jurisdiction in later adjudication
KHURANA AND ANOTHER v WEBSTER CONSTRUCTION LTD
[2015] BLR Plus 23
Adjudication agreement - Binding decision - Access to the courts - Unfair Terms in Consumer Contracts (SI 1999 No 2083), regulations 5 and 7 - Application to stay the action - Principles
HERON BROS LTD v CENTRAL BEDFORDSHIRE COUNCIL
[2015] BLR Plus 24
Public Contracts Regulations 2006 (SI 2006 No 5) - Period for service of claim form - Service of unsealed claim form within statutory period - Application to strike out claim - Discretion to cure irregularity in service of unsealed claim form - Regulation 47F - Service of claim form in accordance with rules of court - Valid service achieved when step taken in accordance with CPR 7.5(1) within seven days of issue of claim form
ECOVISION SYSTEMS LTD v VINCI CONSTRUCTION UK LTD
[2015] BLR Plus 25
Adjudication - Jurisdiction - Contractual interpretation - Applicable adjudication rules - Bias
SECRETARY OF STATE FOR DEFENCE v TURNER ESTATES SOLUTIONS LTD
[2015] BLR Plus 26
Arbitration - Preliminary issues - Arbitration Act 1996, section 45 - Criteria for court ordering preliminary issues - Question law - Substantial effect on parties' rights - Substantial costs savings - Construction of contract - Canons of construction
HARLEQUIN PROPERTY (SVG) LTD AND ANOTHER v WILKINS KENNEDY (A FIRM)
[2015] BLR Plus 27
Security for costs - After the event insurance - CPR 25.12 and 25.13 - Third Parties (Rights Against Insurers) Acts 1930 and 2010 - Contracts (Rights of Third Parties) Act 1999
MT HØJGAARD A/S v E.ON CLIMATE AND RENEWABLES UK ROBIN RIGG EAST LTD AND ANOTHER
[2015] BLR Plus 28
Construction of a contract for the design and installation of wind turbines - Warranty of fitness for purpose - Whether provision requiring compliance with industry standard qualified obligation of fitness for purpose - Whether obligation to comply with contractual technical standard imposed a strict obligation - Meaning of 20-year design life
PHILPOTT AND ANOTHER (AS JOINT LIQUIDATORS OF WGL REALISATIONS 2010 LTD) v LYCEE FRANCAIS CHARLES DE GAULLE SCHOOL
[2015] BLR Plus 29
Liquidation - Taking of account under rule 4.90 of Insolvency Rules 1986 - Stay under section 9 of Arbitration Act 1996 - Whether any legal proceedings brought by liquidators to ascertain net balance would be stayed - Whether right to adjudicate remained
AL-WADDAN HOTEL LTD v MAN ENTERPRISE SAL (OFFSHORE)
[2015] BLR Plus 30
FIDIC - Clause 67.1 - Absence of engineer's decision - Notice of arbitration
HERON BROS LTD v CENTRAL BEDFORDSHIRE COUNCIL (NO 2)
[2015] BLR Plus 31
Judgment handed down - Application to revisit judgment prior to sealing - Principles to be applied
ASPECT CONTRACTS (ASBESTOS) LTD v HIGGINS CONSTRUCTION PLC
[2015] BLR Plus 32
Adjudication - Proceedings challenging adjudicator's decision - Cause of action - Implied term of repayment - Unjust enrichment
ILIFFE AND ANOTHER v FELTHAM CONSTRUCTION LTD AND OTHERS
[2015] BLR Plus 33
Summary judgment - CPR Part 24.2 - No real prospect of success - Other compelling reason - Fire case - Joinder of third parties - Issues about causation - Third party pleadings not closed - Damages remaining to be assessed in any event
OBRASCON HUARTE LAIN SA v HER MAJESTY'S ATTORNEY GENERAL FOR GIBRALTAR
[2015] BLR Plus 34
FIDIC - Termination - Unforeseeable ground conditions
SAINT GOBAIN BUILDING DISTRIBUTION LTD (T/A INTERNATIONAL DECORATIVE SURFACES) v HILLMEAD JOINERY (SWINDON) LTD
[2015] BLR Plus 35
Sale of goods - Incorporation of standard terms and conditions - Sufficient Notice - Sale of Goods Act 1979 - Implied terms about quality or fitness - Unfair Contract Terms Act 1977 Schedule 2 - Whether standard terms satisfied statutory test of reasonableness
PT PERUSAHAAN GAS NEGARA (PERSERO) TBK v CRW JOINT OPERATION (INDONESIA)
[2015] BLR Plus 36
Adjudication - FIDIC Contract Red Book - Clause 20 - Dispute adjudication board - International Arbitration Act 2002 - Partial and interim awards - Provisional awards - Final awards - DAB decision given effect to - Final and binding nature of decisions ad awards - Impact of later Partial Award on merits
WOODS BUILDING SERVICES v MILTON KEYNES COUNCIL
[2015] BLR Plus 37
Procurement - Evaluation criteria - Duty of transparency - Duty of fairness and equal treatment - Undisclosed criteria - Manifest error - Role of unsuccessful tenderer's ex-employee in evaluation exercise by authority - Conflict of interest - Use by successful tenderer of competitor's confidential information taken unlawfully
WOODS BUILDING SERVICES v MILTON KEYNES COUNCIL (No 2)
[2015] BLR Plus 38
Procurement - Authority in breach of duties of transparency, fairness and equal treatment - Remedy - Corrected evaluation score showed claimant out-scored successful tenderer - Whether court would order authority to contract with claimant - Damages
NORTHROP GRUMMAN MISSIONS SYSTEMS EUROPE LTD v BAE SYSTEMS (AL DIRIYAH C4I) LTD
[2015] BLR Plus 39
Incorporation of terms - Need to establish intention - Contract to be governed by other contract - Disregard of inappropriate incorporated terms - Factual matrix - Relevance to contract terms
CALEDONIAN MODULAR LTD v MAR CITY DEVELOPMENTS LTD
[2015] BLR Plus 40
Adjudication - Payment applications - Final determination of dispute
NH INTERNATIONAL (CARIBBEAN) LTD v NATIONAL INSURANCE PROPERTY DEVELOPMENT COMPANY LTD (NO 1) AND (NO 2)
[2015] BLR Plus 41
FIDIC Contract for Construction 1999 1st Edition - Clause 2.4 Employer's financial arrangements made and maintained - Reasonable evidence to be provided - Termination by contractor for breach of clause 2.4 - Question of fact for arbitrator - Clause 2.5 Employer's rights to set off and cross-claim - Employer's notice and particulars as condition precedent
PORTSMOUTH CITY COUNCIL v ENSIGN HIGHWAYS LTD
[2015] BLR Plus 42
PFI contract - Highway network - Service points for defaults by contractor - Good faith - Expressed and implied - Contract interpretation - Limited scope of good faith duty - Best Value Duty
HENIA INVESTMENTS LTD v BECK INTERIORS LTD
[2015] BLR Plus 43
Part 8 proceedings - Interim Application for Payment - Interim Certificate - Pay Less Notice - Payment provisions - JCT Standard Building Contract without Quantities 2011 - Housing Grants, Construction and Regeneration Act 1996 (as amended)
GSK PROJECT MANAGEMENT LTD (IN LIQUIDATION) v QPR HOLDINGS LTD
[2015] BLR Plus 44
Costs Management Order - Precedent/Form H - Costs - Proportionality - Reasonableness - Incurred costs taken into account - Set cost budget
OPENVIEW SECURITY SOLUTIONS LTD v MERTON LONDON BOROUGH COUNCIL
[2015] BLR Plus 45
Regulations 47A, C, G to L - Public Contracts Regulations 2006 (as amended) (SI 2006 No 5) - Automatic suspension where alleged breach by contracting authority to economic operator - Application to set aside automatic suspension - Whether damages an adequate remedy
WYCOMBE DEMOLITION LTD v TOPEVENT LTD
[2015] BLR Plus 46
Adjudication enforcement - CPR Part 24 - Reference of multiple disputes - Breaches of natural justice - Adjudicator refusing to make visit to site - Adjudicating deciding valuation basis on alternative methodology without opportunity to comment
ROB PURTON (T/A RICHWOOD INTERIORS) v KILKER PROJECTS LTD
[2015] BLR Plus 47
Adjudication - Jurisdiction - Existence of contract - Formation of contract
THE CENTRAL TENDER BOARD v VERNON WHITE (TRADING AS WHITE CONSTRUCTION SERVICES)
[2015] BLR Plus 48
Tender - Public body - Finance (Administration) Act 2008 (Montserrat), section 57 - Procurement and Stores Regulations - Ultra vires - Tender accepted - Time for completion not expressed in tender - Implied contract between tenderers and employer - Duty to act fairly in treatment of tenderers
SSE GENERATION LTD v HOCHTIEF SOLUTIONS AG AND ANOTHER
[2015] BLR Plus 49
NEC Contract (2nd Edition) - Indemnity provisions - Insurance provisions - Inter-relationship of such provisions - No presumption that insurance provisions had primacy - No implied term that one co-assured could not sue another