Delay and Disruption in Construction Contracts
| Delay and Disruption in Construction Contracts, 6th Edition, (c) 2025 |
Page 876
CHAPTER 20
Total time, total loss and global claim
Introduction
20–001 In Doyle v Laing,1 Lord Macfadyen identified the problem with global claims as this: