Delay and Disruption in Construction Contracts
| Delay and Disruption in Construction Contracts, 6th Edition, (c) 2025 |
Page 550
CHAPTER 13
Variation and change
Introduction
13–001 A variation can come about because the contract makes express provision for D, or the CA on its behalf, to order it, or because, by the terms of the contract, a variation is to be inferred from particular conduct, or circumstances.