Delay and Disruption in Construction Contracts
| Delay and Disruption in Construction Contracts, 6th Edition, (c) 2025 |
Page 900
CHAPTER 21
Apportionment
Introduction
21–001 Apportionment of some sort is necessary in many issues of causation. In its simplest form, it is merely a mental process of rationalisation of facts, without which some issues could not be resolved at all, as in the following scenario.