Building Law Monthly
TIME LIMITS, CONTRACTS AND ADJUDICATION
Cubitt Building & Interiors Ltd v Fleetgrade Ltd [2006] EWHC 3413 (TCC), 21 December 2006
In
Cubitt Building & Interiors Ltd v Fleetgrade Ltd
[2006] EWHC 3413 (TCC), 21 December 2006, Judge Coulson held that, in the case where the contractual adjudication provisions
comply with the terms of the Housing Grants, Construction and Regeneration Act 1996 (hereafter ‘the 1996 Act’), it is the
terms of the contract, and not the terms of the Act, which should be at the forefront of the court’s consideration of the
parties’ respective rights and liabilities. While Judge Coulson emphasised the importance of compliance with the contractual
timetable, his adoption of a ‘sensible and commercial’ construction of the requirements of the timetable enabled him to enforce
the decision of an adjudicator, notwith-standing the fact that it actually reached the parties some 12 hours after the expiry
of the time available to the adjudicator for him to reach his decision.