i-law

Construction Law Reporter

MCGEE GROUP LTD v GALLIFORD TRY BUILDING LTD

Delay and disruption claim - Liability capped at 10% - Interpretation of clause containing cap

The claimant sought a declaration that any financial claims brought by the defendant for delay and disruption were capped at 10% of the sub-contract sum, being £1,489,733. The defendant, for its part, accepted that some of its delay and disruption claims were subject to the cap but maintained that others were not.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, click Log In button.

Copyright © 2024 Maritime Insights & Intelligence Limited. Maritime Insights & Intelligence Limited is registered in England and Wales with company number 13831625 and address 5th Floor, 10 St Bride Street, London, EC4A 4AD, United Kingdom. Lloyd's List Intelligence is a trading name of Maritime Insights & Intelligence Limited.

Lloyd's is the registered trademark of the Society Incorporated by the Lloyd's Act 1871 by the name of Lloyd's.