Building Law Monthly
CONTINUING NEGOTIATIONS AND CONTRACT FORMATION
Fitzpatrick Contractors Ltd v Tyco Fire and Integrated Solutions (UK) Ltd [2008] EWHC 1301 (TCC), 13 June 2008
In
Fitzpatrick Contractors Ltd v Tyco Fire and Integrated Solutions (UK) Ltd
[2008] EWHC 1301 (TCC), 13 June 2008, Mr Justice Coulson found that the parties to the litigation had concluded a binding
contract. He was able to find in the negotiations between the parties an initial broad agreement which was then followed by
agreement on various outstanding matters. He rejected the submission that there could be no contract between the parties in
the absence of a deed. Finally, he considered an important issue of interpretation relating to the scope of a clause which
imposed a cap on the liability of the defendants. He held that the cap applied to the liability which the claimants incurred
towards third parties as a result of the defendants’ breach but that it did not apply to claims brought by the claimants in
respect of losses which they had suffered as a result of the defendants’ failure to carry out and complete the sub-contract
works.