BREACH OF NATURAL JUSTICE IN FAILING TO GIVE PARTIES THE OPPORTUNITY TO COMMENT ON REPORT
RSL (South West) Ltd v Stansell Ltd [2003] EWHC 1390 (TCC)
Online Published Date:
01 October 2003
Appeared in issue:
Vol 20 No 10 - 01 October 2003
BREACH OF NATURAL JUSTICE IN FAILING TO GIVE PARTIES THE OPPORTUNITY TO COMMENT ON REPORT
RSL (South West) Ltd v Stansell Ltd [2003] EWHC 1390 (TCC)
Online Published Date:
01 October 2003
Appeared in issue:
Vol 20 No 10 - 01 October 2003
CONTRACTOR NOT ENTITLED TO AN EXTENSION OF TIME AS A RESULT OF FAILURE TO COMPLY WITH AGREED PROCEDURE
City Inn Ltd v Shepherd Construction Ltd (unreported, 20 May 2003)
Online Published Date:
01 October 2003
Appeared in issue:
Vol 20 No 10 - 01 October 2003
NON-PAYMENT BY EMPLOYER HELD TO BE A REPUDIATORY BREACH ENTITLING CONTRACTOR TO SUSPEND WORK
C. J. Elvin Building Services Ltd v Noble [2003] EWHC 837 (TCC)
Online Published Date:
01 October 2003
Appeared in issue:
Vol 20 No 10 - 01 October 2003