-
BALFOUR BEATTY REGIONAL CONSTRUCTION LTD v GROVE DEVELOPMENTS LTD
Contract – Construction – JCT Standard Form Design and Build 2011 – Interim payments – New schedule agreed that only went to July 2015 – What the contractual regime was for applications after that date – Express terms – Implied terms.
[2017] BLR 1
-
LESLIE v FARRAR CONSTRUCTION LTD
Contract – Overpayment – Restitution – Money paid without full calculation of actual “build costs” – Whether recoverable.
[2017] BLR 21
-
CONNECT PLUS (M25) LTD v HIGHWAYS ENGLAND COMPANY LTD
Expert determination – Jurisdiction – Contractual interpretation – “A matter comprised in the Dispute” – Stay of proceedings.
[2017] BLR 33
-
THE COUNCIL OF THE BOROUGH OF MILTON KEYNES v VIRIDOR (COMMUNITY RECYCLING MK) LTD
Procedure – Amendment – Late application for permission to amend Defence by adding second defendant. – Rectification – Claimant seeking to rectify contract with defendant – Relevance of acquisition of shares in defendant by another party.
[2017] BLR 47
-
BEUMER GROUP UK LTD v VINCI CONSTRUCTION UK LTD
Adjudication – Enforcement – Natural justice – Adjudicator's failure to disclose involvement in separate adjudication involving same party and same subject matter – Inconsistent factual cases in separate adjudications – Impartiality – Disclosure of documents from separate adjudication – Denial of opportunity to advance case – Materiality of breach.
[2017] BLR 53
-
WILLMOTT DIXON CONSTRUCTION LTD v ROBERT WEST CONSULTING LTD
CPR 17.1(2)(b) – Application to amend Response to Request for Further Information – Vicarious liability – Independent contractors – Exceptionally hazardous or inherently dangerous works – Withdrawal of Support – Contributory negligence.
[2017] BLR 67
-
BITUMEN INVEST AS v RICHMOND MERCANTILE LTD FZC
Guarantee – Whether “on demand” guarantee – Construction of terms – Summary judgment – CPR Part 24.
[2017] BLR 74
-
OCTOESSE LLP v TRAK SPECIAL PROJECTS LTD
JCT Intermediate Building Contract (IC 2011) – Clauses 2.22 and 2.23. – Deduction of liquidated damages – Certificates of non-completion. – Costs – Recovery of claims consultants’ fees.
[2017] BLR 82
-
ENERGY SOLUTIONS EU LTD v NUCLEAR DECOMMISSIONING AUTHORITY
Public procurement – Francovich conditions – Breaches need to be sufficiently serious – Factors to be taken into account – Non-exhaustive list of factors – Individual manifest errors in conjunction leading to wrong tenderer selection – Winning tenderer should have been disqualified.
[2017] BLR 92
-
DACY BUILDING SERVICES LTD v IDM PROPERTIES LLP
Adjudication – Jurisdiction – No contract – Difference as to the parties to the contract – Clarity as to who the contract parties are – Reservation as to jurisdiction.
[2017] BLR 114
-
MICHAEL WILSON & PARTNERS LTD v THOMAS SINCLAIR
Costs order – Execution – Stay – CPR Part 3.1(2)(f) – CPR Part 83.7 – Principles – Discretion.
[2017] BLR 125
-
HIS ROYAL HIGHNESS EMERE GODWIN BEBE OKPABI AND OTHERS v ROYAL DUTCH SHELL PLC AND SHELL PETROLEUM DEVELOPMENT COMPANY OF NIGERIA LTD
Foreign claimants – Pollution in the Niger Delta – Holding and operating companies sued – CPR 11(1)(a) and (b) – Duty of Care by holding company – Foreseeability, proximity and reasonableness – Applicable substantive law – Nigerian law – Regulation EC 864/2007 (Rome II) – Expert evidence – Permission to call expert evidence – The position of the claimant's solicitors – CFAs or equivalent available in Nigeria.
[2017] BLR 136
-
SOUTH COAST CONSTRUCTION LTD V IVERSON ROAD LTD
Adjudication – Enforcement – Insolvency Act 1986 – Administration – Notice of intention to appoint an administrator – Permission to proceed with enforcement application. – Adjudication – Enforcement – Jurisdiction – Scope of dispute – Construction of notice of adjudication – Decision on issues raised in a cross-claim.
[2017] BLR 169
-
MAILBOX (BIRMINGHAM) LTD v GALLIFORD TRY CONSTRUCTION LTD
Assignment – Party entitled to maintain claim in adjudication – Enforcement of Adjudicator's decision.
[2017] BLR 180
-
SURREY AND SUSSEX, HEALTHCARE NHS TRUST V LOGAN CONSTRUCTION (SOUTH EAST) LTD
Adjudication - Part 8 - Validity of Interim Payment Notice and Pay Less Notice.
[2017] BLR 189
-
CARILLION CONSTRUCTION LTD v EMCOR ENGINEERING SERVICES LTD AND EMCOR (UK) LTD
DOM/2 subcontract form – Delay – Extension of time – How such extension was to be fixed – Whether “contiguous” or “non-contiguous”.
[2017] BLR 203
-
MILTON KEYNES BOROUGH COUNCIL v VIRIDOR (COMMUNITY RECYCLING MK) LTD
Contracts – Mistake – Common mistake – Unilateral mistake – Rectification – Defences – Laches – Acquiescence. – Contracts – Entire agreement clauses – Whether a bar to rectification. – Public Procurement – Public Contract Regulations 2006 (SI 2006 No 5) – Regulations 18(25) and 18(26) – Whether breach of Regulations is a bar to rectification.
[2017] BLR 216
-
WHEELDON BROTHERS WASTE LTD v MILLENNIUM INSURANCE COMPANY LTD
Experts – CPR Part 35 – Defendant retains expert initially – Claimant engages same expert – Confidentiality – Defendant's ability to retain expert for litigation – Expert's duty to the court – Overriding objective.
[2017] BLR 234
-
COSTAIN LTD v TARMAC HOLDINGS LTD
Arbitration Act 1996, section 9 - Construction of Dispute Resolution provisions in NEC 3 Framework Contract and NEC 3 Supply Short Contract - Whether the Arbitration Agreement is inoperative under the Arbitration Act 1996, section 9(4) - Whether Arbitration Agreement is null and void because Adjudicator exceeded his jurisdiction - Whether party estopped from relying on Arbitration Agreement.
[2017] BLR 239
-
JOSEPH GLEAVE & SON LTD v SECRETARY OF STATE FOR DEFENCE
Public procurement – Challenge to tender documents – Contract not yet awarded – Whether expedited trial should be ordered before contract award – Whether stay should be granted pending contract award.
[2017] BLR 264
-
LEJONVARN v BURGESS AND ANOTHER
Duty of care – Services provided gratuitously – Correct test for establishing whether a duty of care is owed – Scope of duty.
[2017] BLR 277
-
SYMBION POWER LLC v VENCO IMTIAZ CONSTRUCTION COMPANY
Arbitration – Serious irregularity – Arbitration Act 1996, section 68(2)(d) – Tribunal's failure to deal with all issues put to it – Principles applicable – Substantial injustice required – Arbitrator's confidential communication with one party – Remission or setting aside – Confidentiality.
[2017] BLR 297
-
CELTIC BIOENERGY LTD v KNOWLES LTD
Arbitration – Arbitration Act 1996, section 68 – Application to set aside award based on serious irregularity – Fraud.
[2017] BLR 312
-
AECOM DESIGN BUILD LTD v STAPTINA ENGINEERING SERVICES LTD
Adjudication – Jurisdiction – Whether dispute extended to the proper assessment of deductions for defects – Enlargement of dispute by responding party. – Adjudication – Natural justice – Adjudicator's decision different from position advanced by either party – Whether parties given sufficient opportunity to make submissions.
[2017] BLR 329
-
HUTTON CONSTRUCTION LTD v WILSON PROPERTIES (LONDON) LTD
Adjudication – Enforcement – Part 8 proceedings.
[2017] BLR 344
-
NUCLEAR DECOMMISSIONING AUTHORITY v ENERGY SOLUTIONS EU LTD (NOW CALLED ATK ENERGY EU LTD)
Procurement – Damages – Application of Francovich conditions – Requirement for breach(es) to be “sufficiently serious”. – Automatic stay – Failure to issue in time to prevent contract being entered into with other bidder – Whether failure to mitigate.
[2017] BLR 351
-
SUN ALLIANCE (BAHAMAS) LTD AND ANOTHER v SCANDI ENTERPRISES LTD
Insurance contract – Interpretation – Whether existing structure is part of contract works – Whether policy a valued policy.
[2017] BLR 371
-
RCS CONTRACTORS LTD v CONWAY
Adjudication – Jurisdiction – Multiple contracts.
[2017] BLR 376
-
PEEL PORT SHAREHOLDER FINANCE COMPANY LTD v DORNOCH LTD
Pre-action disclosure – CPR 31.16 – Third Parties (Rights against Insurers) Act 2010 – Application for disclosure of insurance policy against a solvent company – Whether to exercise discretion to grant disclosure – Relevance of statutory and procedural landscape.
[2017] BLR 382
-
GOODLIFE FOODS LTD v HALL FIRE PROTECTION LTD
Fire – Exclusion clause – Unfair Contract Terms Act 1977 – Consumer Protection Act 1987, section 41(1) – Electrical Equipment (Safety) Regulations 1994 (SI 1994 No 3260) – Claim in negligence and breach of statutory duty – Exclusion clause partly unenforceable – Effect on remainder of clause – Reasonableness of clause.
[2017] BLR 389
-
PERSIMMON HOMES LTD AND OTHERS v OVE ARUP & PARTNERS LTD AND ANOTHER
Contract – Purported exclusion of liability – Exemption clauses – Exclusion clauses – Construction of clause stating “liability for any claim in relation to asbestos is excluded”.
[2017] BLR 417
-
RUSSELL AND ANOTHER v PETER STONE (TRADING AS PSP CONSULTANTS) AND OTHERS
Contracts – Standstill Agreements – Interpretation – Whether effect is to extend time or suspend the running of time – Whether protection of earlier agreement is lost by conclusion of a further agreement – Relevance and effect of recitals – Relevance of unamended standard form or template agreement – Commercial common sense – Clear words.
[2017] BLR 429
-
MAILBOX (BIRMINGHAM) LTD v GALLIFORD TRY BUILDING LTD (FORMERLY KNOWN AS GALLIFORD TRY CONSTRUCTION LTD)
Part 8 – Serial adjudication – Liquidated damages – Extensions of time.
[2017] BLR 443
-
VILCA AND OTHERS v XSTRATA LTD AND OTHERS
Expert evidence – Foreign law – Two experts previously instructed – Most recent expert withdrew because of ill-health – Application for extension of time for exchange of expert reports – Whether court should impose condition that previous experts’ reports should be disclosed.
[2017] BLR 460
-
AFRICAN EXPORT-IMPORT BANK AND OTHERS v SHEBAH EXPLORATION & PRODUCTION COMPANY LTD AND OTHERS
Unfair Contract Terms Act 1977, section 3 – Dealing on the other's written standard terms of business – Standard industry terms.
[2017] BLR 469
-
M T HOJGAARD A/S v E.ON CLIMATE & RENEWABLES UK ROBIN RIGG EAST LTD AND ANOTHER
Construction of a contract for the design and installation of wind turbines - Warranty of fitness for purpose - Whether provision requiring compliance with industry standard qualified obligation of fitness for purpose - Whether obligation to comply with contractual technical standard imposed a strict obligation.
[2017] BLR 477
-
ATLANTISREALM LTD v INTELLIGENT LAND INVESTMENTS (RENEWABLE ENERGY) LTD
Privilege - Disclosure - Inadvertent disclosure of privileged document - CPR 31.20 - Relevant principles.
[2017] BLR 489
-
CHRISTOPHER LINNETT LTD AND ANOTHER v MATTHEW J HARDING (TRADING AS M J HARDING CONTRACTORS)
Adjudication – Adjudicator's engagement – Adjudicator's fees – Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013 (SI 2013 No 3134) – Whether commercial contract – Interest – Late Payment of Commercial Debts (Interest) Act 1998 – Late Payment of Commercial Debts Regulations 2013 (SI 2013 No 395).
[2017] BLR 498
-
ADVA OPTICAL NETWORKING LTD AND ANOTHER v OPTRON HOLDING LTD, ROTRONIC INSTRUMENTS (UK) LTD; ROTRONIC INSTRUMENTS (UK) LTD v A ONE DISTRIBUTION (UK) LTD
Relief from sanction - Judgment in default - Extension of time for service of defence - Serious default â Absence of delay to proceedings or additional costs â Whether judgment in default is desirable if contrary to claimant's primary position and contingent upon the claimant's liability up the line.
[2017] BLR 516
-
POLYTEC OVERSEAS LTD AND ANOTHER v GRAND DRAGON INTERNATIONAL HOLDINGS COMPANY LTD AND ANOTHER
Arbitration Ordinance – Mandatory stay to arbitration – Construction of contracts.
[2017] BLR 523
-
THE ROYAL DEVON AND EXETER NHS FOUNDATION TRUST v ATOS IT SERVICES UK LTD
Contract – Limitation of liability – Consequential damages – Exclusion of liability – So-called “wasted expenditure” – Points of construction – Preliminary issues.
[2017] BLR 533
-
VINCI CONSTRUCTION UK LTD v BEUMER GROUP UK LTD
Sectional completion – Liquidated damages – Interpretation – Whether works falling within sections were sufficiently identifiable and certain – Whether liquidated damages clause operable/enforceable.
[2017] BLR 547
-
MEDITERRANEAN SHIPPING COMPANY v SOTRAMON LTD
Negligence – Mauritian Civil Code – Doctrine of faute lourde – Gross negligence delict – Whether duplicated by claim in contract – Damages for faute lourde same as for breach of contract.
[2017] BLR 558
-
MOTT AND ANOTHER v LONG AND ANOTHER
Costs – Failure to serve costs budget pursuant to CPR 3.13 – Relief from sanctions under CPR 3.9 – Test to be applied and factors to be assessed.
[2017] BLR 566
-
CRUDEN BUILDING & RENEWALS LTD v SCOTTISH WATER
Nuisance – Negligence – Breach of statutory duty – Escape of foul water.
[2017] BLR 575
-
LUNGOWE AND OTHERS v VEDANTA RESOURCES PLC AND ANOTHER
Jurisdiction – Whether claims by Zambian nationals should be brought in England – Recast Brussels Regualtion – Forum conveniens – Principles applicable.
[2017] BLR 585
-
NORTH MIDLAND BUILDING LTD v CYDEN HOMES LTD
Acts of prevention – JCT Design and Build Contract 2005 – Extension of time – Concurrent delay caused by Contractor – Clause requiring such concurrent delays to be disregarded enforceable.
[2017] BLR 605
-
SQUIBB GROUP LTD v POLE 2 POLE SCAFFOLDING LTD
Arbitration award – Application for extension of time to appeal against award – Arbitration Act 1996, sections 69, 70 and 80 – 12 weeks’ delay – Need for reasonable explanation – Whether prejudice suffered by delay – Other factors to be taken into account – Need for speedy finality.
[2017] BLR 613
-
JACOBS UK LTD (FORMERLY KNOWN AS JACOBS ENGINEERING UK LTD) v SKANSKA CONSTRUCTION UK LTD
Adjudication – Agreed procedure and timetable – Withdrawing and restarting adjudication – Serial adjudications – Whether unreasonable and oppressive – Injunctions restraining adjudication – Compensation for wasted/additional cost.
[2017] BLR 619
-
THE GOVERNORS AND COMPANY OF THE BANK OF IRELAND AND ANOTHER v WATTS GROUP PLC (NO 2)
Costs – Basis of assessment – Indemnity or standard – Relevance of defendant's offers (Part 36 and otherwise). – Costs – Interim payment on account – Relevance of approved costs budget.
[2017] BLR 626