Customer support: +44 (0)20 7017 7701 Technical Support: +44 (0) 20 7017 4161

Related Content

Publication Details
Building Law Monthly
ISSUE: Vol 23 No 5
ISBN: 0957-0628

01 May 2006Building Law Monthly

DELAY AND TIME OF THE ESSENCE

Shawton Engineering Ltd v DGP International Ltd [2005] EWCA Civ 1359; [2006] BLR 1

In Shawton Engineering Ltd v DGP International Ltd [2005] EWCA Civ 1359; [2006] BLR 1 the Court of Appeal held that contractors were not entitled to terminate a contract with sub-contractors on account of the delay on the part of the sub-contractors in completing the works. The contractors could not show that the parties had agreed to make time of performance of the essence of the contract, nor could they show that the failure of the sub-contractors to complete the works within a reasonable time was a fundamental breach such that the effect of the breach was substantially to deprive the contractors of the whole benefit of the promised contractual performance.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, please enter your details below to log in.

Username:
Password:
Email address:
Remember my details on this computer:

If you are not already a subscriber, please select one of the options below.

Sign up for a free trial or for further assistance call your Account Manager or our Customer support: +44 (0)20 7017 7701 Technical Support: +44 (0) 20 7017 4161 .