Construction Law Reporter
MCGEE GROUP LTD v GALLIFORD TRY BUILDING LTD
[2017] EWHC 87 (TCC), Technology and Construction Court, Coulson J, 26 January 2017
Delay and disruption claim - Liability capped at 10% - Interpretation of clause containing cap
The claimant sought a declaration that any financial claims brought by the defendant for delay and disruption were capped at 10% of the sub-contract sum, being £1,489,733. The defendant, for its part, accepted that some of its delay and disruption claims were subject to the cap but maintained that others were not.