Construction Industry Law Letter
ISSUE: June 2012
ISBN: 0269-0039

01 Jun 2012Construction Industry Law Letter

Contract formation - price - insurance provisions - incorporation of arbitration clause

Technology and Construction Court; before Mr Justice Edwards-Stuart; judgment delivered 28 May 2012

The facts During 2003 Merit Process Engineering Limited (‘Merit’) entered into negotiations with Balfour Beatty Engineering Services (HY) Limited (‘BBES’) for three separate sub-contract work packages for plant and pipeworks. The first two packages, referred to as the Main Installation Package and the Vacuum Drainage Package, concerned the Diamond Synchrotron Project at Chilton in Oxfordshire. The third package related to the Isis Project at Didcot. Both projects were for the construction of scientific and research facilities.

The rest of this document is only available to i-law.com online subscribers.

If you are already a subscriber, please enter your details below to log in.

Username:
Password:
Email address:
Remember my details on this computer:

If you are not already a subscriber, please select one of the options below.

Sign up for a free trial or for further assistance call your Account Manager or our Customer support: +44 (0)20 7017 7701 Technical Support: +44 (0) 20 7017 4161 .